Plans STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0118

Plans and drawings: the text below has words only, no drawings.

Very large file (30.4 MB): may take a few minutes to open.

Log in to see the plans as drawn
    GENERAL NOTES                                                                                                    EARTHWORKS NOTES                                                                                ROADWORKS NOTES                                                                               PAVEMENT SPECIFICATIONS
    1.    ALL SITE EXISTING TOPSOIL TO BE STRIPPED WITHIN DEVELOPMENT FOOTPRINT AND STOCKPILED                       1.     SOILS REPORT                                                                             1.    LEVELS AND GRADIENTS AT JUNCTIONS WITH EXISTING WORKS MAY BE VARIED AS REQUIRED TO      1.   FIRE ACCESS TRACK FLEXIBLE PAVEMENT -
          ON SITE FOR REUSE. LOCATION FOR STOCKPILE TO BE AS ADVISED BY SUPERINTENDENT.                                     ALL EARTHWORKS AND SITE PREPARATION TO BE CARRIED OUT IN ACCORDANCE WITH THE                   ACHIEVE SATISFACTORY CONNECTIONS AND THE COSTS DEEMED INCLUDED IN THE RELEVANT                 150mm THICK TMR TYPE 2.1 BASE COURSE
          SHOULD EXISTING TOPSOIL NOT BE SUITABLE FOR REUSED. CONTRACTOR TO ALLOW TO DISPOSE                                RECOMMENDATIONS IN THE GEOTECHNICAL REPORT 226707 DATED ON 06/03/2024 PREPARED BY              SCHEDULE ITEMS.                                                                                150mm THICK TMR TYPE 2.4 SUB-BASE COURSE
          OF OFFSITE WITHIN THEIR TENDER SUBMISSION.                                                                        DOUGLAS PARTNERS. A COPY OF THIS CAN BE OBTAINED FROM THE SUPERINTENDENT.                2.    THE LOCATION OF EXISTING SERVICES AS SHOWN ON THE PLAN IS INDICATIVE ONLY AND THE
    2.    ALL UNSUITABLE OR UNCONTROLLED FILL THAT IS DEEMED NOT SUITABLE FOR REUSE WITHIN                           2.     SITE PREPARATION                                                                               CONTRACTOR MUST ASCERTAIN THE POSITION OF ALL SERVICES (I.E. WATER, ELECTRICITY,
                                                                                                                                                                                                                                                                                                                   2.   CONCRETE PAVEMENT -
          THE PROJECT GEOTECHNICAL REPORT IS TO BE DISPOSED OF OFF SITE.CONTRACTOR TO                                       EXCAVATE AND REMOVE ALL VEGETATION, ORGANIC TOPSOIL, UNCONTROLLED FILL AND OTHER               TELECOM, GAS ETC.), BEFORE COMMENCING CONSTRUCTION.
                                                                                                                                                                                                                                                                                                                         150mm THICK N32 CONCRETE
          INCLUDE DUE ALLOWANCE FIR DISPOSAL OFF SITE WITHIN THEIR TENDER SUBMISSION.                                       DELETERIOUS MATERIAL FROM SITE. EXCAVATE AND TRIM THE BUILDING OR PAVEMENT               3.    ALL EXISTING SERVICES AND STRUCTURES ARE TO BE MAINTAINED IN GOOD ORDER FOR THE
                                                                                                                                                                                                                           DURATION OF THE CONTRACT AND WHERE RELOCATION IS REQUIRED REFER SPECIFICATION.                SL82 MESH 50mm TOP COVER
    3.    CONTRACTORS AND SUB-CONTRACTORS TENDERING ON THIS PROJECT ARE TO MAKE                                             PLATFORMS AS REQUIRED.
          THEMSELVES FULLY AWARE OF ALL REQUIREMENTS. IF IN DOUBT OR FURTHER CLARIFICATION IS                               SITE PREPARATION TO BE IN ACCORDANCE WITH THE RECOMMENDATIONS OF THE                     4.    SUBSOIL DRAINS TO BE PROVIDED UNDER ALL KERB AND CHANNEL AND KERB.                            150mm THICK TMR TYPE 2.4 SUB-BASE COURSE
          REQUIRED, THE CONTRACTOR IS TO OBTAIN CLARIFICATION FROM THE ENGINEERS PRIOR TO                                   GEOTECHNICAL REPORT.                                                                     5.    NOT WITHSTANDING THE LIMITS OF EARTHWORKS SHOWN ON THE DRAWINGS, THE ACTUAL LIMITS
          SUBMITTING TENDER PRICES. SHOULD THE CONTRACTOR FAIL TO OBTAIN CLARIFICATION FROM                                 IF THE GEOTECHNICAL REPORT DOES NOT PROVIDE ADVICE ON SITE PREPARATION THEN PROOF              SHALL BE DETERMINED ON SITE BY THE SUPERINTENDENT.                                      3.   CONCRETE PATHWAYS, RAMPS & LANDINGS -
          THE ENGINEERS IT IS DEEMED THAT THE CONTRACTOR HAS BEEN PROVIDED SUFFICIENT                                       ROLL THE EXPOSED SUBGRADE USING SIX PASSES OF A 10 TONNE MINIMUM STATIC WEIGHT           6.    ROADS AND STRUCTURAL FORMATIONS INCLUDING EMBANKMENTS, FOOTPATHS, PAVED AREAS                 100mm N32 CONCRETE
          INFORMATION TO ADEQUATELY PRICE THE ENTIRE WORKS AND THAT THE CONTRACTOR HAS                                      VIBRATORY PAD TYPE ROLLER TO IDENTIFY ANY SOFT SPOTS. THESE ZONES MUST BE INSPECTED            AND SHOULDERS ARE TO BE COMPACTED TO 100% STANDARD DRY DENSITY LESS THAN 0.3m                 SL72 MESH CENTRAL
          ALLOWED FOR ALL WORKS REQUIRED. IN PROVIDING CLARIFICATION, THE ENGINEER HAS NOT                                  BY AN APPROVED GEOTECHNICAL ENGINEER TO ASSESS THEIR EXTENT.                                   BELOW SUBGRADE AND 98% STANDARD DRY DENSITY MORE THAN 0.3m BELOW SUBGRADE TO
          ASSUMED A DUTY OF CARE TO THE CONTRACTOR OR SUBCONTRACTOR, BUT IS ONLY ACTING AS                                  SOFT SPOTS SHALL BE EXCAVATED AND REPLACED WITH SELECT BACKFILL COMPACTED IN                   AS1289 5.1.1. AND LOCAL GOVERNMENT AUTHORITY SPECIFICATIONS.                                   SUBGRADE REPLACEMENT IS REQUIRED IF CBR IS LESS THAN 5.
          THE OWNER’S AGENT.                                                                                                LAYERS NOT EXCEEDING 150mm COMPACTED THICKNESS TO COMPACTION LISTED UNDER "FILL          7.    ELECTRICAL AND COMMUNICATIONS CONDUIT LOCATIONS ARE SHOWN FOR INFORMATION ONLY.                150mm LAYERS OF CBR 15 TYPE 2.5 PAVEMENT GRAVEL
    4.    PRIOR TO COMMENCEMENT OF WORKS THE CONTRACTOR IS TO IDENTIFY AND BE SATISFIED OF                                  MATERIAL".                                                                                     FOR EXACT LOCATIONS REFER TO ELECTRICAL CONSULTANTS LAYOUT PLANS. FOR WATER
                                                                                                                                                                                                                                                                                                                          COMPACTED TO 98% STANDARD COMPACTION
          THE CORRECT LOCATION OF ALL EXISTING SERVICES WHETHER INDICATED OR NOT ON THE                                     THE CONTRACTOR IS RESPONSIBLE FOR THE DESIGN AND CERTIFICATION OF A SUITABLE                   CONDUIT LOCATIONS REFER WATER RETICULATION DRAWINGS.
          PLANS. ANY DAMAGE TO EXISTING SERVICES IS TO BE RECTIFIED AT THE CONTRACTOR'S                                     WORKING PLATFORM FOR THE SITE, INCLUDING BUT NOT LIMITED TO CRANES AND MACHINERY.        8.    MINIMUM COVER TO ROOFWATER PIPES TO BE 450MM EXCEPT WHERE LESS COVER IS
          EXPENSE.                                                                                                          THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING SAFE BATTERS AND EXCAVATIONS.                      NECESSARY TO DISCHARGE TO STREET KERB AND CHANNEL.
                                                                                                                                                                                                                     9.    CONTRACTOR TO APPLY FOR AND RECEIVE APPROVAL FROM THE LOCAL GOVERNMENT
    5.    CONTRACTOR TO PROVIDE DILAPIDATION REPORT OF EXISTING SERVICES AND STRUCTURES
          PRIOR TO CONSTRUCTION.                                                                                     3.
                                                                                                                            BUILDING PAD, SUBGRADE AND PREPARATION TO EXTEND 1m PAST STRUCTURAL SLAB EXTENTS.
                                                                                                                            FILL MATERIAL                                                                                  AUTHORITY FOR THE PROPOSED FOOTPATH AND CROSSOVER WORKS PRIOR TO CONSTRUCTION.          PROVISION FOR TRAFFIC & EXTERNAL WORKS
    6.    CONTRACTOR TO ALLOW FOR ALL SERVICE STRUCTURES (FOR EXAMPLE, POWER POLES,                                         BUILDING PAD FILL SHALL BE COMPACTED IN MAXIMUM 150mm THICK LAYERS (COMPACTED            10.   CONTRACTOR TO ARRANGE INSPECTION OF PROPOSED CROSSOVERS AND FOOTPATHS WITH              1.   THE CONTRACTOR HEREBY COVENANTS THAT IT WILL AT ALL TIMES INDEMNIFY AND KEEP
          COMMUNICATIONS PITS OR VALVE BOXES) TO BE MODIFIED TO SUIT THE FINISHED SURFACE                                   THICKNESS) TO 98% STANDARD DRY DENSITY RATIO.                                                  COUNCIL IN ACCORDANCE WITH DEVELOPMENT APPROVAL AND OPERATIONAL WORKS APPROVAL.              INDEMNIFIED, THE PRINCIPAL FROM AND AGAINST ALL ACTIONS CLAIMS, DEMANDS, LOSSES,
          LEVEL IN ACCORDANCE WITH THE SERVICE PROVIDES SPECIFICATIONS.                                                     FILL UNDER ROADS TO BE IN ACCORDANCE WITH ROADWORKS NOTES.                               11.   CONTRACTORS AND SUB-CONTRACTORS TO CONFIRM CROSSOVER AND ADJACENT PAVEMENT                   DAMAGES, COSTS, CHARGES AND EXPENSES, OR OTHER LIABILITIES WHATSOEVER, IN RESPECT
    7.    PRIOR TO COMMENCEMENT OF WORKS THE CONTRACTOR WILL PROVIDE SCOUR AND EROSION                                      ALL BUILDING PADS AND STRUCTURE FILLING SHALL BE UNDER LEVEL 1 GEOTECHNICAL                    LEVELS AND GRADES PRIOR TO THE START OF CONSTRUCTION. IF IN DOUBT OR FURTHER                 OF, OR ARISING FROM, ANY DAMAGES TO THE ROAD FRONTING THE SITE DURING THE
          PROTECTION INCLUDING PROVISION OF SEDIMENT TRAPS AND FENCES TO MINIMISE DEPOSITION                                SUPERVISOR BY RPEQ GEOTECHNICAL ENGINEER AND SHALL BE IN BULK EARTHWORKS TENDER                CLARIFICATION IS REQUIRED, THE CONTRACTOR IS TO OBTAIN CLARIFICATION FROM THE                CONSTRUCTION OF THE WORKS.
          OF MATERIAL ONTO DOWNSTREAM OF THE PROPERTY AS INDICATED ON THE DRAWINGS.                                         ALLOWANCE.                                                                                     ENGINEERS PRIOR TO CONSTRUCTION.                                                        2.   THE CONTRACTOR SHALL:
    8.    THIS DRAWING SHALL BE READ IN CONJUNCTION WITH ALL OTHER WORKING DRAWINGS AND                                     THE FREQUENCY OF TESTING FILL COMPACTION SHALL BE AS SPECIFIED IN SECTION 8 OF AS 3798   12.   CONTRACTOR TO PROVIDE CBR TEST RESULTS A MINIMUM OF TWO WEEKS PRIOR TO ROAD                     a. OBTAIN PERMISSION FROM LOCAL COUNCIL AND THE QUEENSLAND DEPARTMENT OF MAIN
          SPECIFICATIONS AND WITH SUCH OTHER WRITTEN INSTRUCTIONS AS MAY BE ISSUED DURING THE                               "GUIDELINES ON EARTHWORKS FOR COMMERCIAL AND RESIDENTIAL DEVELOPMENTS" FOR THE                 CONSTRUCTION TO CONFIRM ROAD SUBGRADE DESIGN. TESTS TO BE TAKEN AT A MINIMUM OF                     ROADS FOR ACCESS TRACKS BEFORE OR DOING ANY WORK EXTERNAL TO THE SITE.
          COURSE OF CONSTRUCTION. ALL DISCREPANCIES AND VARIATIONS SHALL BE REFERRED TO THE                                 LEVEL SPECIFIED IN NOTE 5 BELOW.                                                               50m CENTERS OR TO LOCAL AUTHORITY STANDARDS. TESTS TO BE TAKEN AT SUBGRADE BOX                  b. INDEMNIFY LOCAL COUNCIL, THE PRINCIPAL, STP CONSULTANTS, AND THE QUEENSLAND
          ENGINEER BEFORE PROCEEDING WITH THE WORK.                                                                         FILL SHALL BE COMPACTED AND MAINTAINED AT MOISTURE CONTENTS AT PLACEMENT WITHIN                DEPTH.
                                                                                                                                                                                                                                                                                                                               DEPARTMENT OF MAIN ROADS AGAINST CLAIMS RESULTING FROM THE CONTRACTOR'S
    9.    CONTRACTOR TO OBTAIN ALL APPROVALS AND PERMITS FOR WORKING WITHIN LOCAL                                           THE RANGE PLUS 2% TO MINUS 2% OF STANDARD OPTIMUM MOISTURE CONTENT U.N.O.                13.   PROVIDE KERB RAMP AT ALL PEDESTRIAN CROSSINGS AND WALKWAYS TO LOCAL GOVERNMENT
                                                                                                                                                                                                                           AUTHORITY STANDARDS.                                                                                OPERATIONS OF PLANT EXTERNAL TO THE SITE.
          GOVERNMENT AUTHORITY ROADS AND STATE GOVERNMENT ROADS.                                                            FILL MATERIAL SHALL BE OF UNIFORM QUALITY AND FREE FROM VEGETABLE MATTER.
                                                                                                                            IMPORTED STRUCTURAL FILL TO BUILDING PADS OF STRUCTURES TO CONFORM TO THE                14.   ALL ROAD WORKS KERB TRANSITIONING BETWEEN KERB TYPES TO BE CARRIED OUT OVER 1.5m                c. COMPLY WITH THE DIRECTIONS AND REQUIREMENTS OF LOCAL COUNCIL AND THE
    10.   CONTRACTOR TO ENSURE THAT ALL THE REQUIRED CONDITIONS OF THE DEVELOPMENT
          APPROVAL HAVE BEEN SATISFIED PRIOR TO STARTING ON SITE.                                                           FOLLOWING:-                                                                                    MINIMUM.                                                                                            DEPARTMENT OF MAIN ROADS 'MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES' WITH
    11.   ALL WORK TO CONFORM TO NOOSA SHIRE COUNCIL STANDARDS AND SPECIFICATIONS UNLESS                                    CBR                           15% MIN.                                                                                                                                                             RELATION TO WARNING SIGNS AND TRAFFIC CONTROL.
          OTHER WISE SHOWN ON PLANS OR DIRECTED BY THE SUPERINTENDENT.                                                      LINEAR SHRINKAGE              8% MAX.                                                                                                                                                          d. REPAIR, MAINTAIN AND MAKE GOOD TO THE SUPERINTENDENT'S SATISFACTION, ANY
    12.   CONTRACTOR TO ENSURE THAT ALL WORK, SERVICES AND PRODUCTS TO BE FIT FOR PURPOSE.                                  LIQUID LIMIT                  35% MAX.                                                   AS CONSTRUCTED                                                                                            DAMAGE.
    13.   ALL 'WORKS AS CONSTRUCTED' INFORMATION SHALL BE SUPPLIED IN BOTH HARD COPY AND                                    PLASTICITY INDEX              15% MAX.                                                   1.    THE CONTRACTOR SHALL ARRANGE FOR AN INDEPENDENT LICENSED SURVEYOR TO CARRY OUT          3.   THE CONTRACTOR SHALL SUBMIT ANY TRAFFIC DIVERSION SCHEMES TO THE LOCAL COUNCIL
          ELECTRONIC DATA FORMAT TO THE REQUIRED AUTHORITIES.                                                               SHRINK/ SWELL INDEX           1.0% MAX.                                                        'WORKS AS CONSTRUCTED' SURVEY AND SUBMIT DETAILS SHOWN ON A PLAN TO THE                      FOR APPROVAL, PRIOR TO IMPLEMENTATION OF SUCH A SCHEME AND PROVIDE A FULL COPY OF
    14.   ALL SETOUT TO ARCHITECTS DETAILS UNLESS NOTED OTHERWISE (U.N.O.).                                                 BEARING CAPACITY              TO STRUCTURAL ENGINEERING DESIGN REQUIREMENTS NOT                SUPERINTENDENT AT COMPLETION OF CONSTRUCTION.                                                SUCH SCHEME TO THE SUPERINTENDENT
    15.   DIMENSIONS SHALL NOT BE OBTAINED BY SCALING THE DRAWINGS.                                                                                       LESS THAN 100KPa ALLOWABLE. FILL SHALL ALLOW REACTIVITY                                                                                                  4.   ALL TRAFFIC DIVERSION SCHEMES SHALL CONFORM TO THE REQUIREMENTS OF THE
                                                                                                                                                          TO BE RECLASSIFIED AS 'CLASS S' TO AS2870-2011.            2.    'WORKS AS CONSTRUCTED' SURVEY IS TO SHOW BUT NOT BE LIMITED TO:
    16.   STP CONSULTANTS PTY LTD MAY PROVIDE, BY AGREEMENT WITH CERTAIN PARTIES, MATERIALS                                                                                                                                                                                                                             DEPARTMENT OF MAIN ROADS PUBLICATION 'MANUAL IF UNIFORM TRAFFIC CONTROL DEVICES'.
          STORED ELECTRONICALLY. THE PARTIES RECOGNIZE THAT DATA, PLANS, SPECIFICATIONS,                                    AS SIEVE                      % PASSING                                                          · LEVEL AND LOCATION OF RETAINING WALLS, FEATURES, EARTHWORKS AND FINISHED            5.   IT IS TO BE CLEARLY UNDERSTOOD THAT THE CONTRACTOR SHALL NOT COMMENCE WORK ON
          REPORTS, DOCUMENTS, OR OTHER INFORMATION RECORDED ON OR TRANSMITTED AS                                            75mm                          100%                                                                 SURFACE LEVELS                                                                           THE SITE UNTIL THE APPROPRIATE PERMITS HAVE BEEN OBTAINED FROM LOCAL COUNCIL.
          ELECTRONIC MEDIA (INCLUDING BUT NOT NECESSARILY LIMITED TO "CAD AND 12D DOCUMENTS")                               4.75mm                        30 - 100%                                                          · LEVEL AND LOCATION OF NEW KERB, KERB AND CHANNEL, CONCRETE INVERT AND KERB               COPIES OF THE PERMITS SHALL BE FORWARDED TO THE SUPERINTENDENT AND AN ADDITIONAL
          ARE SUBJECT TO UNDETECTABLE ALTERATION, EITHER INTENTIONAL OR UNINTENTIONAL, DUE TO,                              0.0075mm                      3 - 30%                                                              RAMP                                                                                     COPY SHALL BE MAINTAINED ON-SITE.
          AMONG OTHER CAUSES, TRANSMISSION, CONVERSION, MEDIA DEGRADATION, SOFTWARE ERROR,                           4.     SUB-GRADE REPLACEMENT (SUB-BASE 2)                                                               · LEVEL AND LOCATION OF ALL DRAINAGE STRUCTURES, PIPES SIZES AND INVERT LEVELS FOR            PERMITS SHALL BE OBTAINED FROM THE COUNCIL PRIOR TO:
          OR HUMAN ALTERATION. ACCORDINGLY, ALL SUCH DOCUMENTS ARE PROVIDED TO THE PARTIES                                  SUB-BASE 2 MATERIAL SHALL BE ROADBASE MATERIAL OF:-                                                STORMWATER DRAINAGE, SEWERAGE RETICULATION AND WATER RETICULATION                           a. CROSSING THE KERB WITH HEAVY VEHICLES.
          FOR INFORMATIONAL PURPOSES ONLY AND NOT AS AN END PRODUCT OR AS A RECORD                                          MINIMUM CBR:                            15%                                                      · ANY DETAILS RELATED TO FINAL ROAD TRUNCATION, ROAD WORKS AND SERVICES                       b. WORKING IN THE ROAD RESERVE.
          DOCUMENT. ANY RELIANCE THEREON IS DEEMED TO BE UNREASONABLE AND UNENFORCEABLE.                                    SUB-BASE 2 MINIMUM THICKNESS:           150mm                                                    · ANY DETAILS REQUIRED BY THE DEVELOPMENT APPROVAL                                            c. CONNECTION TO A COUNCIL ROAD.
          THE SIGNED AND/OR STAMPED HARD COPIES OF THE ENGINEERING DRAWINGS ARE THE ONLY                                    MAXIMUM PARTICLE SIZE:                  40mm
                                                                                                                            MAXIMUM LIQUID LIMIT:                   35%                                              3.    AS CONSTRUCTED SURVEY IS TO BE PROVIDED IN .DWG, .PDF AND ADAC FORMATS.                         d. STORING OF MATERIAL ON THE FOOTPATH OR ROAD.
          TRUE CONTRACT DOCUMENTS OF RECORD.
    17.   IN CASE OF DOUBT, ASK!                                                                                            MAXIMUM PLASTICITY INDEX:               12%                                                                                                                                                    e. THE PROVISION OF HOARDING AND GANTRIES
                                                                                                                                                                                                                                                                                                                   6.   IF DAMAGE IS CAUSED TO EXISTING ROADWAYS OR FOOTPATHS BY THE CONTRACTOR, THE
                                                                                                                            UNLESS OTHERWISE APPROVED BY GEOTECHNICAL ENGINEER.
                                                                                                                            PLACE CBR 15 MATERIAL TO FINAL COMPACTED THICKNESS OF 150mm COMPACTED TO 98%
                                                                                                                                                                                                                     PAVEMENT MARKING AND SIGNAGE NOTES                                                                 DAMAGED SECTIONS SHALL BE REPAIRED OR REPLACED AT THE CONTRACTORS COST TO THE
    EROSION AND SEDIMENT CONTROL NOTES:                                                                                     STANDARD MAXIMUM DRY DENSITY IN ACCORDANCE WITH AS 1289.                                 1.    PRIOR TO COMMENCEMENT OF WORKS THE CONTRACTOR IS TO IDENTIFY AND BE SATISFIED OF             ENTIRE SATISFACTION OF THE SUPERINTENDENT. IN THE EVENT THAT THE CONTRACTOR FAILS TO
                                                                                                                     5.     EXTERNAL FOOTPATHS & SLABS                                                                     THE CORRECT LOCATION OF ALL EXISTING SERVICES WHETHER INDICATED OR NOT ON THE                MAKE ANY NECESSARY REPAIRS, OR THE COUNCIL MOVES TO RECOVER THE COST OF ANY
    1.    THE CONTRACTOR SHALL PREPARE AN EROSION AND SEDIMENT CONTROL PLAN AND SUBMIT TO
                                                                                                                            PROVIDE WATERPROOF DAMP COURSE 0.2µ VAPOUR BARRIER ON 50MM SAND BED & 150MM                    PLANS. ANY DAMAGE TO EXISTING SERVICES IS TO BE RECTIFIED AT THE CONTRACTOR'S                REPAIRS FORM THE PRINCIPAL, THE PRINCIPAL SHALL BE EMPOWERED, ON THE CERTIFICATION
          THE SUPERINTENDENT PRIOR TO UNDERTAKING ANY WORKS ON SITE.                                                                                                                                                                                                                                                    OF THE SUPERINTENDENT AS OFTEN AS THE SAME SHALL HAPPEN, TO DEDUCT FROM MONIES, OR
                                                                                                                            SUB-BASE 2 IF SUBJECT TO LIGHT VEHICLE TRAFFIC.                                                EXPENSE.
    2.    DEVICES TO BE PLACED BY A BUILDER TO SUIT STAGE OF WORKS & COMPLIANCE WITH THE BEST                                                                                                                        2.    ALL PAVEMENT MARKING, SIGNAGE AND RETROREFLECTIVE RAISED PAVEMENT MARKERS (RRPM)             WHICH MAY BECOME DUE, TO THE CONTRACTOR THE AMOUNT PAID IN SUCH CASES TO THE
          PRACTICE GUIDELINES AND IECA STANDARDS.                                                                    6.     CUT MATERIAL
                                                                                                                            ALL CUT AREAS ARE TO BE COMPACTED TO 100% COMPACTION. ALL EXCESS CUT                           TO BE IN ACCORDANCE WITH THE TMR AND AS 1742 MANUAL FOR UNIFORM TRAFFIC CONTOUR              COUNCIL.
    3.    CONSTRUCTION OF ALL SEDIMENT MANAGEMENT DEVICES SHALL BE COMPLETED AND EFFECTIVE                                                                                                                                 DEVICES.                                                                                7.   ALL OTHER PERMITS REQUIRED TO COMPLETE THE WORKS FROM BUT NOT LIMITED TO THE
                                                                                                                            MATERIAL,TOPSOIL, DEBRIS AND WASTE TO BE REMOVED FROM SITE.
          PRIOR TO :                                                                                                 7.     CUT AND FILL                                                                             3.    GUIDE POSTS TO BE IN ACCORDANCE WITH THE TMR AND AS 1742 MANUAL FOR UNIFORM TRAFFIC          QUEENSLAND POLICE SERVICE, QUEENSLAND FIRE AND RESCUE AUTHORITY AND QUEENSLAND
          - STRIPPING OF TOPSOIL AND GRASS                                                                                  IS THE RESPONSIBILITY OF THE EARTHWORKS CONTRACTOR WHO IS TO PROVIDE COMPACTION                CONTROL DEVICES.                                                                             AMBULANCE SERVICE SHOULD BE OBTAINED BY THE CONTRACTOR.
          - BULK EARTHWORKS TO THE SITE                                                                                     CERTIFICATION BY A SUITABLY QUALIFIED AND EXPERIENCED GEOTECHNICAL ENGINEER THAT         4.    FOR SIGNAGE AND ASSEMBLY DETAILS REFER TMR STANDARD DWG.                                8.   ANY ASSOCIATED FEES WITH OBTAINING THE REQUIRED PERMITS SHALL BE PAID BY THE
          - SERVICE INSTALLATION                                                                                            THE WORKS HAVE BEEN COMPLETED TO THE REQUIRED LEVEL.                                     5.    STREET NAME SIGNS SHALL BE TO LOCAL GOVERNMENT STANDARDS.                                    CONTRACTOR AND INCLUDED IN THE LUMP SUM GENERALLY.
                                                                                                                            PROVIDE SUB-BASE AS DETAILED IN NOTES ABOVE.                                             6.    FOR ROADWORK DELINEATOR DETAILS REFER TMR STANDARD DWG.                                 9.   WHENEVER WORK UNDER THIS CONTRACT ABUTS ON EXISTING ROADS, THE CONNECTION
    4.    ALL SEDIMENT MANAGEMENT DEVICES ARE TO REMAIN IN PLACE UNTIL COMPLETION OF WORKS.
                                                                                                                            EARTHWORKS UNDER PROPOSED STRUCTURES TO BE TO THE STRUCTURAL ENGINEERS                   7.    EXISTING PAVEMENT MARKING ARE TO BE REMOVED BY GRINDING.                                     THERETO SHALL BE NEAT, SMOOTH AND WORKMANLIKE AND TO THE SUPERINTENDENTS
    5.    BOTH TEMPORARY AND PERMANENT SEDIMENT MANAGEMENT DEVICES SHALL BE MAINTAINED AT                                                                                                                                                                                                                               SATISFACTION.
                                                                                                                            SPECIFICATIONS. REFER TO STRUCTURAL ENGINEERS DETAILS FOR SAFE BEARING CAPACITY          8.    LONGITUDINAL LINE MARKING SHALL BE DULUX A1 SOLVENT BASED PAVEMENT MARKING OR
          A SUITABLE LEVEL/CONDITION THROUGHOUT CONSTRUCTION. SEDIMENT FENCES ARE TO BE                                                                                                                                    APPROVED EQUIVALENT. TRANSVERSE LINE MARKING SHALL BE THERMOPLASTIC OR APPROVED
          CLEANED WHEN CAPACITY IS REDUCED BY 30%.                                                                          REQUIREMENTS.
    6.    IF EROSION AND SEDIMENT CONTROL DEVICES HAVE BEEN FOUND TO BE DEFECTIVE OR FAILED IN
                                                                                                                     8.     GEOTECHNICAL INSPECTIONS AND TEST CERTIFICATES
                                                                                                                                                                                                                     9.
                                                                                                                                                                                                                           EQUIVALENT.
                                                                                                                                                                                                                           PEOPLE WITH DISABILITY PARKING SPACE, SYMBOLS, BOLLARDS AND SHARED SPACE TO BE IN
                                                                                                                                                                                                                                                                                                                   REQUIRED HOLD POINT INSPECTIONS
                                                                                                                            THE GEOTECHNICAL ENGINEER SHALL PROVIDE ALL SERVICES AS REQUIRED TO SATISFY LEVEL 1
          SERVICE, DUE TO UNFORESEEN CIRCUMSTANCES, CORRECTIVE ACTION IS TO BE UNDERTAKEN                                                                                                                                  ACCORDANCE WITH AS2890.                                                                 CONTRACTOR IS REQUIRED TO COMPLETE ALL HOLD POINT INSPECTIONS. FAILURE TO DO SO WILL
                                                                                                                            SUPERVISION AS SPECIFIED IN SECTION B OF AS 3798.
          IMMEDIATELY.                                                                                                      WHERE THE GEOTECHNICAL ENGINEER IS NOT APPOINTED BY THE PRINCIPAL. THE CONTRACTOR        10.   ALL LINE MARKING SUBJECT TO PEDESTRIAN TRAFFIC SHALL MEET THE MINIMUM PENDULUM OR       RESULT IN NON-ISSUANCE OF FORM 12. REQUIRED HOLD POINT INSPECTIONS LISTED BELOW:
                                                                                                                            SHALL BE RESPONSIBLE FOR APPOINTING THE GEOTECHNICAL ENGINEER AND ORGANISING THE               RAMP RECOMMENDATIONS IN THE PEDESTRIAN SURFACES NOTES.                                  ·    PRE-START MEETING
    EXISTING SERVICES NOTES:                                                                                                COMPACTION TESTS. THE COST OF THESE SHALL BE ALLOWED FOR BY THE CONTRACTOR.                                                                                                            ·    SUBGRADE PROOF-ROLL INSPECTION
    1.    THE CONTRACTOR IS MAKE THEMSELVES FULLY AWARE OF ALL EXISTING SERVICES, FOR                                       TEST CERTIFICATES ON THE FILL MATERIAL SHALL BE SUPPLIED TO THE SUPERINTENDENT FOR       PEDESTRIAN SURFACES NOTES                                                                     ·    PRE-SEAL INSPECTION
                                                                                                                            APPROVAL PRIOR TO THE USE OF THE FILL MATERIAL                                                                                                                                         ·    STORMWATER PRIOR TO BACKFILL INSPECTION
          EXAMPLE DIAL BEFORE YOU DIG TO BE CONTACTED FOR THE LOCATION OF EXISTING PUBLIC                                                                                                                            1.    ALL SURFACES SUBJECT TO PEDESTRIAN TRAFFIC SHALL MEET THE MINIMUM PENDULUM OR
                                                                                                                     9.     SERVICES                                                                                                                                                                               ·    RETAINING WALL FOUNDATION REINFORCEMENT INSPECTION (IF APPLICABLE)
          UTILITIES PRIOR TO EXCAVATION.                                                                                    PRIOR TO THE COMMENCEMENT OF WORKS THE CONTRACTOR IS TO IDENTIFY AND BE SATISFIED              RAMP RECOMMENDATIONS CONTAINED IN TABLE 3 OF AUSTRALIAN STANDARD HANDBOOK
    2.    THE ALIGNMENT & LEVEL OF EXISTING SERVICES SHOWN ON THIS DRAWING HAS BEEN COMPILED                                                                                                                               HB197:1999 - AN INTRODUCTORY GUIDE TO THE SLIP RESISTANCE OF PEDESTRIAN SURFACE
                                                                                                                                                                                                                                                                                                                   ·    PRE-BACKFILL INSPECTION
                                                                                                                            OF THE CORRECT LOCATIONS OF ALL EXISTING SERVICES WHETHER INDICATED OR NOT ON THE                                                                                                      ·    PRACTICAL COMPLETION
          FROM SURVEY DATA & COUNCIL RECORDS & IS INDICATIVE ONLY. PRIOR TO COMMENCING                                      PLANS. ANY DAMAGE TO EXISTING SERVICES IS TO BE RECTIFIED AT THE CONTRACTORS                   MATERIALS. COMPLIANCE WITH THE RECOMMENDATIONS SHALL BE VERIFIED BY TESTING TO
          CONSTRUCTION OR ORDERING ANY MATERIALS THE CONTRACTOR IS TO CONFIRM THE                                           EXPENSE.                                                                                       EITHER:- AS/NZS 4586:2004 - SLIP RESISTANCE CLASSIFICATIONS OF NEW PEDESTRIAN SURFACE
          ALIGNMENT & LEVEL OF ALL SERVICES AFFECTED BY THE PROPOSED WORKS.                                          10.    EARTHWORKS VOLUMES                                                                             MATERIALS, OR AS/NZS 4663:2004 - SLIP RESISTANCE MEASUREMENT OF EXISTING PEDESTRIAN
    3.    WHILE DUE CARE IS TAKEN BY STP CONSULTANTS IN CONFIRMING THE LOCATION OF EXISTING                                 ALL VOLUMES PROVIDED EXCLUDE ANY COMPACTION OR BULKING FACTORS.                                SURFACES AS APPROPRIATE IN BOTH INSTANCES COMPLIANCE SHALL BE DEMONSTRATED BY
          SERVICES IT IS THE CONTRACTORS RESPONSIBILITY TO CONFIRM THESE SERVICE LOCATIONS. IN                              ALL VOLUMES PROVIDED EXCLUDE LANDSCAPE TOPSOIL REQUIREMENTS, DETAILED EXCAVATION,              APPLYING CLAUSE 5.3 - MEANS OF DEMONSTRATING COMPLIANCE OF AS/NZS 4586:2004 - SLIP
          SOME INSTANCES SERVICES MAY BE OMITTED FROM THE DRAWINGS.                                                         FOOTING AND TRENCHING REQUIREMENTS.                                                            RESISTANCE CLASSIFICATION OF NEW PEDESTRIAN SURFACE MATERIALS.
                                                                                                                            ALL VOLUMES PROVIDED ARE INDICATIVE AND ARE TO BE CONFIRMED ON SITE BY THE
    4.    A REPRESENTATIVE FOR EACH SERVICE PROVIDER TO BE PRESENT ON SITE WHEN WORKING                                                                                                                              2.    IN GENERAL, THE CLASSIFICATION OF A SURFACING MATERIAL OR FINISH SHALL BE MADE ON A
                                                                                                                            CONTRACTOR.
          WITHIN 3.0m OF EACH SERVICE IF THE SERVICES ARE PUBLIC ASSET SERVICES.                                     11.    EROSION CONTROL                                                                                WORST CASE BASIS AS DETERMINED BY PENDULUM TESTING USING BOTH THE FOUR S AND TRL
    5.    SHOULD INVERT LEVELS OR LOCATION OF ANY SERVICE CONNECTION POINTS DIFFER TO THAT                                  REFER TO EROSION AND SEDIMENT CONTROL PLAN AND NOTES FOR DETAILS.                              RUBBER SLIDER. WHERE ADDITIONAL TEST RESULTS ARE AVAILABLE (OIL -WET RAMP, WET/
          INDICATED ON THE DRAWINGS THEN THE SUPERVISING ENGINEER SHALL BE NOTIFIED                                         ALL DISTURBED GROUND IS TO BE GRASS SEEDED AND HYDROMULCHED TO ENSURE THAT ALL                 BAREFOOT RAMP) THESE MAY BE TAKEN INTO CONSIDERATION.
          IMMEDIATELY.                                                                                                      EXPOSED AREAS ARE STABILISED WITHIN ONE MONTH OF BEING DISTURBED. ALL BATTERS            3.    ALL PITS, STRUCTURES AND INLETS WITHIN A PEDESTRIAN TRAFFIC AREA ARE TO HAVE HEEL
    6.    ANY WORK ON EXISTING SERVICES THAT REQUIRE RELOCATION SHALL BE CARRIED OUT BY THE                                 STEEPER THAN 1V:6H ARE TO BE TOPSOILED AND TURFED U.N.O.                                       PROOF, NON-SLIP, BOLT DOWN LIDS.
          RELEVANT AUTHORITY SHALL BE CO-ORDINATED BY THE CONTRACTOR. CONTRACTOR TO OBTAIN
          REQUIRED APPROVALS FROM THE RELEVANT AUTHORITY.
                                                                                                                     DILAPIDATION SURVEY                                                                             EXCAVATION OF TRENCHES, SHORING AND LIABILITY FOR
    SAFETY NOTE                                                                                                      1.    CONTRACTOR SHALL ARRANGE A FULL DILAPIDATION CONDITION REPORT (AT BUILDERS COST_          DAMAGE
                                                                                                                           FOR THE FOLLOWING EXISTING BUILDINGS PRIOR TO UNDERTAKING ANY DEMOLITION AND CIVIL
    STP CONSULTANTS RECOGNIZES THE IMPORTANCE OF OCCUPATIONAL HEALTH AND SAFETY. HOWEVER,                                  EARTHWORKS                                                                                1.    THE CONTRACTOR SHALL SUPPLY AND DISPLAY ON SITE OF WORKS, ALL APPROPRIATE
    STP CONSULTANTS HAS NOT BEEN ENGAGED TO DEVELOP, CHECK, SUPERVISE OR CONTROL WORKERS                                      ALL EXISTING STRUCTURES WITHIN 5m OF PROPOSED WORKS INCLUDING COUNCIL                        NOTIFICATION SIGNS AND SAFETY MARKING APPLICABLE FOR A CONSTRUCTION SITE IN
    OR METHODS OF WORK. STP CONSULTANTS DOES NOT HAVE THE CAPACITY OR AUTHORITY TO                                                                                                                                         ACCORDANCE WITH ALL REQUIRED REGULATORY GUIDELINES AND LEGISLATION.
                                                                                                                              STORMWATER INFRASTRUCTURE
                                                                                                                                                                                                                     2.    IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO ENSURE THAT ALL TRENCH
    CONTROL WORKERS OR METHODS OF WORK. NOTHING IN THESE DESIGNS SHOULD BE INTERPRETED AS                                                                                                                                  EXCAVATION IS CARRIED OUT IN ACCORDANCE WITH THE MINES REGULATION ACTS, THE
    GOING BEYOND THE STRUCTURAL INTEGRITY OF THE SUBJECT MATTER OF THE DESIGNS AND THEY                              2. UPON COMPLETION THE CONTRACTOR SHALL PREPARE A FINAL DILAPIDATION SURVEY IF ANY                    WORKPLACE HEALTH AND SAFETY ACT 2011.
    SHOULD NOT BE USED AS AN INDICATOR OF THE APPROPRIATE METHODS OF WORK ON, IN OR AROUND                              DAMAGE IS CAUSE TO THE EXISTING BUILDINGS THE CONTRACTOR SHALL ARRANGE FOR                   3.    DURING THE EXCAVATION, ET CETERA AND CONSTRUCTION OF THE WORKS OF THE CONTRACT,
    THE SUBJECT MATTER. CONCERNS ABOUT THE CONDUCT OF WORKERS OR METHODS OF WORK SHOULD                                 APPROPRIATE REPAIR AT FULL COST                                                                    THE CONTRACTOR IS TO ADOPT EVERY PRECAUTION AND PROVIDE ALL MATERIALS, LABOUR, ET
    BE RAISED WITH THE APPROPRIATE SAFETY OFFICIAL ON SITE.                                                                                                                                                                CETERA AND CAREFULLY EXECUTE AT HIS OWN COST WHENEVER CONSIDERED NECESSARY BY
                                                                                                                     MAINTENANCE NOTE                                                                                      THE SUPERINTENDENT AND TO HIS ENTIRE SATISFACTION, STRONG SHORING AND IN SANDY OR
                                                                                                                                                                                                                           LOOSE SOIL, CLOSE TIMBERING AND OTHER WORK THAT MAYBE REQUIRED TO PREVENT EARTH
                                                                                                                     1.     CONTRACTOR TO ATTEND ON-MAINTENANCE INSPECTION WITH ENGINEER AND LOCAL COUNCIL
    SURVEY




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          NOTE.
                                                                                                                                                                                                                           OR OTHER MATERIALS AT SIDES OF EXCAVATION FROM BEING SHAKEN, SLIPPING OR FALLING IN.
                                                                                                                            OFFICERS IF REQUIRED.                                                                    4.    THE CONTRACTOR SHALL ENSURE THAT ALL TRENCHES OVER 1.5m IN DEPTH ARE SHORED IN
    1.    ALL LEVELS ARE TO BE TO A.H.D LEVEL DATUM. REFER TO SURVEY DRAWING No. 200070-005-VER                      2.     SUCH MAINTENANCE SHALL BE CARRIED OUT IN ACCORDANCE WITH THE PROVISIONS OF THE                 ACCORDANCE WITH THE REQUIREMENTS OF THE WORKPLACE HEALTH AND SAFETY ACT 2011.
                                                                                                                            GENERAL CONDITIONS OF CONTRACT WITH RESPECT TO MAKING GOOD DEFECTS AND OTHER                   WHERE APPROVED BY OFFICERS OF THE DIVISION OF OCCUPATIONAL SAFETY, TRENCHES MAY BE
    DISCLAIMER                                                                                                              FAULTS DUE TO FAULTY REPAIR AND/OR WORKMANSHIP AND SHALL INCLUDE CLEANING UP AND               BATTERED BACK, THE ABSOLUTE MAXIMUM SLOPE OF THE BATTER IS TO BE FORTY-FIVE (45)




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          ST
    WHILST EVERY EFFORT HAS BEEN MADE TO ENSURE THAT THE INFORMATION PROVIDED IN THIS DRAWING/DESIGN WAS                    REPAIR DUE TO STORM DAMAGE.
    ACCURATE AT THE TIME IT WAS COMPILED, AS PART OF THE LOCAL COUNCILS "AS CONSTRUCTED" RECORDS, IT REMAINS THE                                                                                                           DEGREES FROM THE HORIZONTAL FROM A POINT 1.5m MAXIMUM ABOVE THE BOTTOM OF THE
    RESPONSIBILITY OF PROPERTY OWNERS AND THEIR CONTRACTORS, SUB-CONTRACTORS, EMPLOYEES, SERVANTS AND AGENTS         3.     THE DEFECTS LIABILITY PERIOD FOR MINOR DEFECTS SHALL BE 12 MONTHS FROM THE DATE OF             TRENCH. THE ACTUAL MAXIMUM BATTER SLOPE IS TO BE DETERMINED AFTER INSPECTION OF THE
    AS APPROPRIATE IN THE CIRCUMSTANCES TO MAKE ALL REASONABLE EFFORTS TO ASCERTAIN THE PRECISE LOCATION OF                 PRACTICAL COMPLETION OR DATE WORKS ARE ACCEPTED ON MAINTENANCE BY LOCAL COUNCIL,               STABILITY OF THE TRENCH.




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          ST
    EXISTING INFRASTRUCTURE INCLUDING WATER MAINS, SEWERS AND DRAINS BEFORE UNDERTAKING EXCAVATION OR                       WHICHEVER OCCURS LAST.
    CONSTRUCTION WORK.                                                                                                                                                                                               5.    THE CONTRACTOR SHALL BE WHOLLY RESPONSIBLE SHOULD AN ACCIDENT OCCUR OR DAMAGE
    USERS OF THE INFORMATION SHOULD BE AWARE THAT SINCE THE ORIGINAL RECORDING OF THE DEPTHS IN RELATION TO
                                                                                                                     4.     THE DEFECTS LIABILITY PERIOD FOR MAJOR DEFECTS OR STRUCTURAL FAILURE SHALL BE SEVEN            TO PROPERTY RESULT FROM THE CONTRACTORS WORK AND SHALL RESTORE SAME AT HIS OWN
    GROUND LEVELS, CHANGES MAY HAVE OCCURRED AS A RESULT OF SUBSEQUENT WORK OR ACTIVITIES INVOLVING FILLING OR              YEARS FROM THE DATE OF PRACTICAL COMPLETION OR DATE WORKS ARE ACCEPTED ON                      COST.
                                                                                                                            MAINTENANCE BY LOCAL COUNCIL, WHICHEVER OCCURS LAST.




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          o
    EXCAVATION. CONSEQUENTLY, THE LOCAL GOVERNMENT AUTHORITY AND STP CONSULTANTS TAKES NO RESPONSIBILITY FOR                                                                                                         6.    THE CONTRACTOR SHALL ENSURE THAT ALL TRENCHES IN UNSUITABLE MATERIAL ARE SHORED
    ANY APPARENT ERROR OR INACCURACIES THAT ARE SHOWN TO EXIST AS AT THE DATE INFORMATION WAS PROVIDED OR AT A       5.     CONTRACTOR TO ATTEND OFF-MAINTENANCE INSPECTION WITH ENGINEER AND LOCAL COUNCIL
    LATER DATE.                                                                                                                                                                                                            OR SHIELDS ARE USED DURING PIPE LAYING OPERATIONS. AT ALL TIMES WHEN TRENCHES AND
                                                                                                                            OFFICERS AFTER TWELVE MONTH DEFECTS LIABILITY PERIOD.




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          Noo
    THE ABOVE ALSO APPLIES TO LOCATION AND DEPTH OF ALL OTHER PUBLIC UTILITIES.                                                                                                                                            EXCAVATIONS ARE OPEN AND THE CONTRACTOR AND HIS EMPLOYEES ARE NOT IN ATTENDANCE
                                                                                                                                                                                                                           THE TRENCHES SHALL BE BARRICADED. THIS SHALL APPLY PARTICULARLY TO MANHOLES AND
                                DIAL BEFORE YOU DIG TO BE CONTACTED                                                                                                                                                        CHAMBERS PRIOR TO AND DURING CONSTRUCTION.




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          O
                                FOR THE LOCATION OF EXISTING PUBLIC                                                                                                                                                  7.    TRENCH WIDTHS SHALL CONFORM TO INSTITUTE OF PUBLIC WORKS ENGINEERING AUSTRALIA
                                UTILITIES PRIOR TO EXCAVATION                                                                                                                                                              QUEENSLAND DIVISION INC. STANDARD DRAWINGS AND BE OF WIDTH TO SUIT NUMBER OF
                                                                                                                                                                                                                           SERVICES.




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          ST
                                                                                                                                                                                                                     8.    DEPTHS TO PIPE INVERTS SHOWN ON JOB DRAWINGS SHALL BE INCREASED TO ALLOW FOR
                                                                                                                                                                                                                           BEDDING. PIPE BEDDING REQUIREMENTS VARY WITH STRATA AND MUST COMPLY WITH THE
                                                                                                                                                                                                                           REQUIREMENTS OF THE RELEVANT STANDARD PLANS AND SPECIFICATION.




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          o
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          ST
                                                                                                                                                                                                                                                                                                                                                                                     D               AS        S                                          A   o
                                                                                                                   IN ASSO IATION WIT                                                                                                         OOLLA CONSTRUCTIONS                                                                                      CIVIL




                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          o D A Do
B   OPERATIONAL       OR S ISSUE                                                     DCZ         E    04 0 24                                                                                                                                                                                                                                                                        D               N
                                                                                                                                                                                                                                 o
A   PRELI INARY                                                                      HJD         E    2 0 24                                                                                                                                OZCARE NOOSA                                                                                                                             D            J N                                                     Jo N    .    D    No.   R   o
                                                                                                                                                                                                                                                                                                                                                                                                               THIS DRAWING IS COPYRIGHT © DO NOT
R                                   D        o                                       B       A          D                                                                                                                                   80 COOYAR STREET, NOOSA HEADS                                                                                                                            E         SCALE DRAWING ORIGINAL DRAWING IS A1
                                                                                                                                                                                                                                                                                                                                                                                                                                                          STP24-0253       C101       B
                                                                                                                                                                                                                                                                                                                                                                                     A   o                     SIZE. THIS DRAWING IS NOT TO BE USED FOR
                                                                                                                                                                                                                             D       T                                                                                                                                                               E         CONSTRUCTION UNLESS THE APPROVED
                                                 A END ENTS                                                                                                                                                                                 PROJECT NOTES - SHEET 1                                                                                                                  R E No.                   SIGNATURE HAS BEEN ADDED.                      NOT FOR CONSTRUCTION

Used in these records

About this file

File size
30.4 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Plans STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdf · 30.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.