Officer: 	Tara Norley
Direct Telephone: 	07 5329 6486
Our Reference:	51994.1292.04
Your Reference:	20220592
28 March 2023
K Chapman & B Piscioneri
C/- Adapt Town Plannng + Development Management (Tiani Boulton)
PO Box 7618
SIPPY DOWNS  QLD  4556
[email protected]
Dear Sir/Madam,
Decision Notice – Minor Change
Planning Act 2016
I refer to your application received on 25 January 2023, requesting a minor change to an existing development approval. Council decided your requested changes.
Details of the decision are as follows:
APPLICATION details
Application No:	51994.1292.04
Street address:	Pacific Outlook 47 & 8/47 Elanda St, Sunshine Beach
Real property description:	Lot 0 BUP 102822 and Lot 8 BUP 102822
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
The following type of approval was issued on 23 June 1994
Development Permit for Town Planning Consent Permit – Multiple dwelling of 9 units.
In relation to the request to make a minor change to the existing approval, Council on 23 March 2023, decided to approve the requested changes. The changes are detailed below.
A.	Approve the change.
B.	Amend Condition 1 & 2.
C.	Add Conditions 32, 33 and 34.
currency period of approval
Not applicable
assessment manager conditions
Submission to and approval by Council of building plans in accordance with the Building Act, Council’s By-laws and Policies, the conditions of this approval and substantially in accordance with plans SP1 to SP5 submitted to Council on the 21st April 1994, and the Shire of Noosa Planning Scheme apart from where amendments are required or dispensations have been granted in conjunction with this approval.
The plans submitted for Building Approval are to comply with the following requirements:-
The maximum building height is to be 12 metres from assumed natural ground level, except where altered by Conditions 32 and 33 of this approval. The plans are to be supported by the submission of levels of floor and roof lines to confirm building height.
The carparking and landscaping arrangements are to be amended at the frontage of the site to improve the landscaped appearance and shield the basement carpark wall. Specifically the car park designated as visitor parking No. 1 is to be deleted and replaced with mounded landscaping and natural ground level is to be maintained along the south-eastern boundary adjacent to the driveway.
The building setbacks from the side boundaries are to provide satisfactory fire separation to the satisfaction of the Building Surveyor. In this regard, it is likely that amendment to the building is required.
Provision of at least 15 off-street car parking spaces, comprising 9 covered spaces and 5 uncovered spaces, and access thereto which are to be provided with a sealed pavement and designed, drained, constructed and maintained in accordance with the Planning Scheme, Council’s Policies and to the reasonable satisfaction of the Shire Engineer. In this regard, minor amendment is required to the carparking layout in order for it to comply. Specifically:-
The internal driveway width is required to be 6.5 meters
Additional manoeuvring are is required at the frontage of the site.
Plans and specifications for these works are to be submitted to the Shire Engineer for approval in conjunction with the Building Application. A Building Approval shall not be granted until the Shire Engineer has approved of the carparking and access scheme.
Finished driveway levels are to be in accordance with Council’s Standards Drawing 9020. Details of driveway profiles are to be submitted and approved by the Shire Engineer, prior to Building Approval.
Payment to Council of $450 in accordance with Council’s Policy on Beach Access Contributions, prior to the issue of Building Approval.
There is to be no detrimental effect upon the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other emissions.
The open space and setback areas are to be landscaped in accordance with Council’s Policy on Landscaping Guidelines and a properly prepared landscape plan to be submitted to and approved by the Shire Planner, prior to the issue of a Building Approval. Such landscaping is to be completed in accordance with the approved landscape plan, prior to the premises being occupied and maintained at all times thereafter to the reasonable satisfaction of the Shire Planner.
Screen fencing is required on the side of the boundaries of the side adjacent to the proposed balconies on the lower floor. Any other fencing provided in conjunction with the development is to be setback an average of two (2) meters to any road frontage pursuant to clause 36 (6) (c) of the Schedule to the Planning Scheme. The landscaping plans referred to above are to indicate the proposed fencing arrangements.
Existing trees on the site and within road reserves are to be retained, except where required to be removed due to building operations or the conduct of the approved use. The landscape plans referred to above are to denote area of existing vegetation or existing trees proposed to be retained.
Construction work and other associated activities are permitted only during the hours of 7.00 a.m. to 6.00 p .m. Monday to Saturday No work is permitted on public holidays, except where extended hours are approved by the Building Surveyor.
All separate, adjoining lots that form part of this application are to be amalgamated into one undivided lot in accordance with Section 5.11 of the Local Government (Planning and Environment) Act, prior to the issue of a Building Approval.
Payment of contributions in accordance with Council’s Policy on Water Supply and Sewerage Headworks. An estimate only of the charges as at January 1994, under the current policy is as follows:-
Water Supply	$24,030
Sewerage		$20,557

TOTAL:		$44,587

Headworks contributions shall be calculated and paid in accordance with one of the following alternatives:-
Prior to the issue of a Building Approval, in the amount calculated under the Policy at that date: or
Deferred to the soonest of the following dates:-
Prior to Council sealing plans of the development for titling purposes;
Prior to the issue of a Certificate of Classification for any building approved under this application; or
Prior to commencement of the approved use at the relevant premises.
Where the option of a deferred payment is used in accordance with b. above, the following conditions shall also apply:-
Prior to the issue of a Building Approval, a trading bank guarantee is to be submitted ti the value of the headworks which are due, plus 20%.
The subsequent payment of headworks shall include interest charged at the rate set by the Queensland Treasury Corporation for Local Government borrowings as the apply to Noosa Shire and current at the time the trading bank guarantee is submitted.
Should the contributions not be paid at the due time, Council shall call upon the sum secured by the trading bank guarantee.
The trading bank guarantee will be returned on payment of the required contributions plus interest or on expiry of the relevant Building Approval, whichever is sooner.
Construction of roadworks, drainage and footpath improvements across the full frontage of the development to the satisfaction of the Shire Engineer. Such works shall involve the construction of kerb and channel, bitumen widening, associated drainage, hot mix correction to the existing pavement, where required and footpath upgrading works. In this regard, plans prepared by the registered Civil Engineer are to be submitted to and approved by the Shire Engineer, prior to the issue of Building Approval.
The footpath across the frontage of the site is to be upgraded by the provisions of a 1.2 meters wide concrete footpath and the forming, grassing and topsoiling of the remaining area to the standards and requirements of the Shire Engineer. The applicant is to contact Council’s Engineering Department to determine the footpath alignment prior to the commencement of any works.
The developer shall bear the cost of alterations of any public utility or other facilities necessitated by the development of the land or associated constructions works external to the site.
Connection to Council’s existing water supply and sewerage reticulation systems at the developer’s expense to the standards and requirements of the Shire Engineer.
The developer shall provide metered water connections from the water supply system to the proposed development, in accordance with Council’s standards and to the satisfaction of the Shire Engineer.
Stormwater disposal of roof and surface water is to be piped to locations to the satisfaction of the Shire Engineer. In this regard, where possible, all roof and balcony runoff is to be discharged to the kerb and channel in Elanda Street. The remaining collected surface water is to be disposed of on-site as to cause no scour or damage to adjoining properties. Details of the method of on-site disposal and piped drainage is to be submitted to and approved by the Shire Engineer, prior to Building Approval.
Provisions of approved refuse containers in accordance with the requirements of the Refuse Management Regulations of 1983 for the storage and collection of refuse to the satisfaction of Council’s Environmental Health Officer.
Provisions of an imperviously paved area upon which to stand all refuse containers together with a suitable enclosure, if required, to enclose the refuse container area to the satisfaction of the Environmental Health Officer.
Any flat or unit intended to be let out for fee or reward is to be licensed annually with Council’s Health Department in accordance with provisions of Chapter 43 of Council’s By-Laws prior to such letting.
The swimming pool shall be licensed annually with Council’s Health Department in accordance with provisions of Chapter 42 of Council’s By-Laws.
Submission of a cash bond or trading bank guarantee to the sum of $10,000 to secure performance of conditions, prior to the issue of Building Approval. The cash bond or trading bank guarantee will be returned upon performance of the conditions of approval.
The provisions of this approval are to be effected, prior to the commencement of the approved use. Council reserves the right to call upon the bond or guaranteed sum referred to in this approval for the purposes of litigation should the use not be conducted in accordance with this approval.
The Town Planning Consent Permit may be revoked pursuant to Section 4.14 of the Local Government (Planning and Environment) Act if commencement of erection or works have not been made in accordance with that Permit or the rights conferred by that permit are not exercised within two (2) years of the date of issue of the Permit.
The Town Planning Consent Permit lapses where:-
The use or erection of a building or other structure associated with the use, has not been commenced within four (4) years of the date of issue of the Town Planning Consent Permit, unless application is made and approved by Council for extension; or
The use of any premises pursuant to the Town Planning Consent Permit ceases for a period of twelve (12) months.
Additional Conditions – 23 February 2005
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are named roof plan, elevations & section, numbered Sheet 01 prepared by Smart Design and dated July 2004 and as may be amended by these conditions.
The development must be undertaken and operated in a manner that causes no detrimental effect upon the amenity of the neighborhood by reason of the creation of excessive noise, lighting nuisance or other emissions.
The roof of the proposed pergola shall have minimum pitch not more than 5% with the total height of the structure not exceeding 2.5 meters.  The pergola is to integrate with the roof top structure and be constructed of lightweight building materials.
The area of the pergola shall not exceed 9% of the roof top terrace area.
Any balustrades, upstands, fencing, screening or partitioning is to be constructed of open or transparent materials and must be setback at least 1.0 meter from the edge of the rooftop.
Additional Conditions – 23 March 2023
Development authorised by this approval must be undertaken generally in accordance with the Approved Plans listed in the table below.
Plan No.	Rev.	Plan/Document Name	Date
100.01	C	Site Context - Proposed Site Plan, prepared by Minnow Studio Annotated by Council	07/03/2023
200.01	C	Planning Concepts - Second Level Apartment Plan, prepared by Minnow Studio Annotated by Council	14/12/2022
200.02	D	Planning Concepts - Roof Terrace Floor Plan, prepared by Minnow Studio Annotated by Council	07/03/2023
210.01	B	Planning Concepts - Roof Plan, prepared by Minnow Studio Annotated by Council	07/03/2023
300.01	C	Building Elevations - West Elevation (Street) - Proposed Elevations, prepared by Minnow Studio Annotated by Council	07/03/2023
300.02	C	Building Elevations - North Elevation - Proposed Elevations, prepared by Minnow Studio Annotated by Council	07/03/2023
300.03	C	Building Elevations - East Elevation - Proposed Elevations, prepared by Minnow Studio Annotated by Council	07/03/2023
300.04	C	Building Elevations - South Elevation - Proposed Elevations, prepared by Minnow Studio Annotated by Council	07/03/2023
400.01	C	Building Sections (Section A-A - Proposed Sections), prepared by Minnow Studio Annotated by Council	07/03/2023
Building Height
The maximum height of the development must not exceed 12 metres above the ground level, except the ‘Open Trellis Structure with Stainless Steel Wires’ as shown on the approved plans, which may be a maximum of 12.31 metres above the ground level.
Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which certifies that Open Trellis Structure with Stainless Steel Wires structure does not exceed the maximum height requirement of this Decision Notice.
referral agencies
Not applicable
advisory notes
Infrastructure Charges
All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges
property notes
Not applicable.
variation approval details
Not applicable.
further development permits required
Type of Development Permit Required	Subject of the required Development Permit
Development Permit for Building Works	All Building Works
submissions
Not applicable.
rights of appeal
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
other details
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.
Yours faithfully
Tara Norley
Development Planner

Enc:	Appeal Rights
Approved Plans/Documents
cc.	Unitywater
DECISION NOTICE HISTORY
Original Decision Notice – 24 June 1994 – TPC2655.
Decision Notice – Minor Change - 51994.1292.02 – 23 February 2005, add additional conditions, 27, 28, 29, 30 and 31.
Generally in Accordance Approval – 51994.1292.03 – 20 April 2017
Decision Notice – Minor Change -51994.1292.04 – 23 March 2023, with an amendment to condition 1 and 2 and additional conditions, 32, 33 and 34.

	Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1)	Schedule 1 of the Planning Act 2016 states –
(a)	Matters that may be appealed to –
(i)	either a tribunal or the P&E Court; or
(ii)	only a tribunal; or
(iii)	only the P&E Court; and
(b)	The person-
(i)	who may appeal a matter (the appellant); and
(ii)	who is a respondent in an appeal of the matter; and
(iii)	who is a co-respondent in an appeal of the matter; and
(iv)	who may elect to be a co-respondent in an appeal of the matter.
(2)	An appellant may start an appeal within the appeal period.
(3)	The appeal period is –
(a)	for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or
(b)	for an appeal against a deemed refusal – at any time after the deemed refusal happens; or
(c)	for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or
(d)	for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or
(e)	for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or
(f)	for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person.
Note –
See the P&E Court Act for the court’s power to extend the appeal period.
(4)	Each respondent and co-respondent for an appeal may be heard in the appeal.
(5)	If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal.
(6)	To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about-
(a)	the adopted charge itself; or
(b)	for a decision about an offset or refund-
(i)	the establishment cost of trunk infrastructure identified in a LGIP; or
(ii)	the cost of infrastructure decided using the method included in the local government’s charges resolution.
230 Notice of appeal
(1)	An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that-
(a)	is in the approved form; and
(b)	succinctly states the grounds of the appeal.
(2)	The notice of appeal must be accompanied by the required fee.
(3)	The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to –
(a)	the respondent for the appeal; and
(b)	each co-respondent for the appeal; and
(c)	for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and
(d)	for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and
(e)	each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and
(f)	for an appeal to the P&E Court – the chief executive; and
(g)	for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate.
(4)	The service period is –
(a)	if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or
(b)	otherwise – 10 business days after the appeal is started.
(5)	A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6).
(6)	A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person.
231 Other appeals
(1)	Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable.
(2)	The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error.
(3)	A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter.
(4)	In this section –
decision includes-
(a)	conduct engaged in for the purpose of making a decision; and
(b)	other conduct that relates to the making of a decision; and
(c)	the making of a decision or failure to make a decision; and
(d)	a purported decision; and
(e)	a deemed refusal.
non-appealable, for a decision or matter, means the decision or matter-
(a)	is final and conclusive; and
(b)	may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and
(c)	is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground.
232 Rules of the P&E Court
(1)	A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal.
(2)	However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court

[word/footer1.xml]
Page 6 of 8

[word/footer2.xml]
NOOSA COUNCIL
ABN: 97 969 214 121
NOOSA COUNCIL
ABN: 97 969 214 121	
					PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 8

[word/footer3.xml]
Page 2 of 3

[word/header2.xml]
3

Used in these records

About this file

File size
111 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Minor Change -51994.1292.04.docx · 111 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.