Performance outcomes Acceptable outcomes Response Comment
contained in the National assessment guidelines for dredging,
Australian Government Department of Environment, Water,
Heritage and the Arts, 2009.
Within a wild river area: riparian and wildlife corridor functions
PO4 The clearing of native marine plants AO4.1 Clearing of marine plants within a wild river area
within a wild river area is minimised. can only occur to the extent of the works, plus the
prescribed area around the development to allow for
maintenance.
PO5 Development within a wild river area No acceptable outcome is prescribed.
does not impact fish passage.
PO6 There is no net loss in marine plants AO6.1 Any marine plant damaged during construction in a
beyond the extent of the works in a wild wild river area is replaced at the completion of the
river area. development with the same species of plant in the
disturbed area outside the footprint of the development.
PO7 Works within a wild river area does AO7.1 Works located in tidal waters within a wild river
not impact on fish habitat values. area are designed and constructed using materials, and
located to ensure that the activities do not impact on fish
habitat values and function.
Within a wild river area: hydrological processes
PO8 Development within a wild river area No acceptable outcome is prescribed.
does not impound natural drainage lines
or flow paths, during both construction
and operation.
Within a wild river area: geomorphic processes
PO9 Excavation and filling for prescribed No acceptable outcome is prescribed.
tidal work within a wild river area is
carried out only to the extent necessary
for the development.
PO10 Works in a tidal area within a wild AO10.1 Where it is necessary to remove a marine plant,
river area are designed and constructed the root system must be left in the substrate to minimise
in a way to ensure they do not adversely disturbance to bed and banks.
affect the stability of the bed and banks AND
of any waterway.
AO10.2 When the works are completed, any tidal lands
disturbed by activities beyond the footprint of the works
are restored to pre-disturbance condition to promote
State development assessment provisions Module 10 — Coastal protection 21 June 2013 Page 14 of 15
10.1 Tidal works, or development in a coastal management district state code