C TrimDek Ultra Roof Sheeting
Profile & Finish as per Scope Of Works.
Fixing to Manufacturers Specification.
Anticon Roof Insulation
Finish as per Scope Of Works& Energy
20
Efficiency Report .Fixing to 10 Polycarbonate Roof Sheeting
0
Manufacturers Specification. Fix per Manufacturers Specifications.
0
44 P3 Profile & Finish as per Scope Of Works.
P1
Refer to Structural
Refer to Structural
Custom Orb Roof Flashing Engineering Documentation
Engineering
Heavy Gauge Material Documentation
TrimDek Ultra Roof Sheeting Sarking
Profile & Finish as per Scope Of Works. As Required
Fixing to Manufacturers Specification.
10 Polycarbonate Soffit Lining.
P3 Polycarbonate Soffit Sheet to Line Up with Plywood Face &
200
Refer to Structural Inner Flange Face. Profile & Finish as per Scope Of Works.
Engineering Documentation
RL.10.39 (8190 FFFL)
Sarking
As Required P1
Refer to Structural 6 Plywood
Engineering Documentation Face of Plywood to Line Up with Inner Flange Face.
9mm Compressed Fibre Cement Sheeting Return Plywood around RB2.Timber Species,
Finish as per Scope Of Works
Profile & Finish as per Scope Of Works
WH2
Refer to Structural Engineering Documentation
6 Plywood ST1
Timber Species, Profile Refer to Structural
Packing Engineering Documentation Support Bracket For Box Gutter
& Finish as per
Fix brackets to P3 @ 600 Centres.
As Required Scope Of Works
Folded Aluminium Flashing
Heavy Gauge Material - Mill Finish Packing
As Required RB1
Refer to Structural
Box Gutter
25 x 25 Aluminium Profile Engineering Documentation Refer to Hydraulic Engineering Documentation
Heavy Gauge Material - Mill Finish For Size. Finish as per Scope Of Works.
10 Shadowline Profile
C1 Profile & Finish as per Scope
Refer to Structural Of Works.
Engineering Documentation
4 Roof Wall Junction 3 Boxgutter, at Junction of Roof 01 & Roof 02
12 Scale 1:10 12 Scale 1:10
C
18mm Plywood
Timber Species, Profile
& Finish as per Scope Of Works
Render to Concrete Blockwork
Finish as per Scope Of Works
25 x 25 Aluminium Profile Packing Sarking
As Required 70 x 35 Stud Wall Below As Required
Heavy Gauge Material - Mill Finish Below Windows
Render to Concrete Blockwork
Finish as per Scope Of Works 42mm x 19mm Finger Jointed Pine
Paint Finish as per Scope Of Works Gusseted Door Head Guide (3000 FFFL) RL.5.200
10 Shadowline Profile Refer to Structural
Profile & Finish as per Scope Engineering Documentation
125mm Hardwood Chamferboard
Folded Aluminium Flashing Of Works.
Front Face to Line Up with Front Face of
Heavy Gauge Material - Mill Finish 10mm Plate Stiffener. Timber Species,
Polished Concrete Slab Profile & Finish as per Scope Of Works
Finish as per Scope Of Works
RL.2.200
Rendered Blockwork 125mm Hardwood
Finish as per Scope Of Works Chamferboard
Mastic Seal Front Face to Line Up with
Finish as per Scope Of Works
Dressed Hardwood Cover Plate
Front Face of 10mm Plate to Timber
Stiffener. Timber Species, Timber Species, Profile & Finish as per
300
Profile & Finish as per Scope Scope Of Works
Of Works
Flashing
Finish as per
Scope Of Works 20 70 20 250 100
Door Opening
110
D
5 Window / Masonry Wall Junction 6 Public Amenities, Accessible Toilet 7 Public Amenities, Accessible Toilet
12 Scale 1:10 12 Scale 1:10 12 Scale 1:10
For Construction
www.barkdesign.com.au
07 5471 0340
07 5471 0343
0418 876 394
0412 127 904
Email [email protected]
Australia 4567
Use figured dimensions
Noosa Heads
Bark Design Architects
Notes Rev. Date Description Rev. Date Description Project Drawing Title Project No.
in preference to scale. All
A 12.06.08 Issue for Construction dimensions to be verified
and checked on site. Noosa VIC Section Details3 0714
These designs,drawings,
specifications and the Drawing No.
copyright thereof are the
property of Bark Design
RAIA Member
28409
Noosa Heads CD.25
Steve Guthrie
Pty Ltd and must not be Noosa Council
PO Box 1355
Queensland
Lindy Atkin
Tourism Noosa
Telephone
used, retained or copied Architects
R
Revision
Facsimile
without the written Registration No.
authority of Bark Design 3664 (LA)
Date June 2008 Scale 1:10 @ A2
A
Web
Pty Ltd. 3668 (SG)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
0714 Noosa VIC Construction Set 12.06.08.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.