2015-06-23 Infrastructure & Services Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 23 JUNE 2015
3 CAPITAL PROGRAM DELIVERY STATUS - JUNE 2015
DOCUMENT INFORM AT ION
Author Asset Planning Coordinator, Bryan O’Connor
Planning & Infrastructure Department
Index ECM/ Subject/ 2014-2015 Annual Capital Works Program
Attachments 1. Capital Projects Delivery Status, 11 June 2015
EXECUTIVE SUMMARY
The project delivery status report is currently presented monthly to the Infrastructure and
Services Committee until the end of the financial year, with the escalated activities around the
delivery of Council’s capital program. The report highlights projects that have been completed
and a general overview of the current and future activities of the projects being delivered.
This report also provides a capital project delivery spreadsheet (Attachment 1) that provides a
general overview of the projects completed and the status of current projects being delivered.
The previously presented capital delivery project dashboard can be utilised to demonstrate an
individual project’s status at any given time throughout the delivery of this report.
RECOMMENDATION
That Council note the report by the Asset Planning Coordinator to the Infrastructure & Services
Committee Meeting dated 23 June 2015 providing an update on the status of the projects being
delivered in the 2014/15 Capital Works Program.
REPORT
The purpose of this report is to inform the Infrastructure & Services Committee of the overall
status of the Capital Works Program projects to 19 June 2015. The report also provides an
opportunity to highlight and discuss projects within the program and also confirm the completion
of projects as they are being delivered throughout the 2014/2015 financial year.
1. Current Projects
The focus for delivery has continued throughout the second half of the financial year and it is
estimated that over 80% of the 2014/2015 capital program will be either financially completed or
committed by 30 June 2015. There are currently 159 active projects in the 2014/15 capital
program with a value of $23.1m (not including Emergent Works reserve) as of 11 June 2015.
There are now 42 projects completed with the remaining projects commenced and in varying
stages of delivery.
Some of the projects that are nearing or are physically completed include:
Noosaville Lions Park, Pirate Playground Renewal
Information Technology Mobility project
Multiple Bus Stop Shelter Upgrades
Noosaville Wallace Park Pathways
Noosaville Gibson Road – Road Safety improvements
Tewantin Cooroy Noosa Road Stage 1
Tewantin Primary School safety improvements
Noosaville Primary School safety improvements
Tewantin River Walk Pathway & Lighting Upgrade
Page 15 of 51
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.