Decision Notice - Approved by Delegation of Authority - MCU26 0060 (As Published)
Currency Period
2. This development approval authorises a temporary use, and the use is to cease operations
by 27 August 2031, or within 60 days of completion of the Lake Macdonald Dam
Improvement Project, whichever comes first, unless otherwise approved by Council.
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below. Where there is any inconsistency between the
approved plans and documents and the conditions of this approval, the conditions of this
approval prevail.
Plan No. Rev. Plan/Document Name Date
Sheet 1 of 2 A Site Plan prepared by Seqwater 10 April 2026
2026
Sheet 2 of 2 A Elevation Plan & Indicative Render 10 April 2026
prepared by Seqwater 2026
Annotated by Council
Amendments Prior to building works, revised elevation plans (park-side view) are to
be provided to Council for endorsement. External colours and finishes
must be of muted/environmental tones that blend with the natural
environment and low-reflective roofing and cladding materials.
Nature and Extent of Approved Use
4. The maximum number of people attending the site at any time must not exceed 9 persons,
with no events that may attract greater numbers permitted to be held from the site.
5. Persons associated with the use are not permitted to attend the site before 6:00am or after
6:30pm.
6. All storage of vessels must be fully contained within the enclosed structure; no outdoor
storage is approved.
7. The building’s purpose is to be clearly sign posted in a way that the structure is clearly for
private use.
Amenity
8. The approved Operational Management Plan/Code of Conduct must be implemented at all
times and made available to all club members and visitors. A copy must also be displayed in
a prominent location within the club structure.
9. The operation of the approved use must not detrimentally affect the residential amenity
(including but not limited to noise, overlooking, light spill or odour) enjoyed by surrounding
residents or cause a nuisance, including a noise nuisance.
10. No flood lighting must be used on site. Any vertical illumination resulting from direct, reflected
or other incidental external lighting emanating from the site must not exceed 8 lux when
measured at any point 1.5 metres outside the boundary and at any level from ground level
upward.
Building Appearance
11. External colours and finishes must be of muted/environmental tones that blend with the
natural environment and low-reflective roofing and cladding materials.
Building Height
12. The maximum height of the development must not exceed 4 metres above the ground level.
including where excavation is undertaken.
Page 2 of 6
Document Set ID: 25104561
Version: 5, Version Date: 02/09/2026