Skip to the record
The definitive source for everything Noosa Council.

Original source · versioned page text

RFI - Ecological Assessment Report

of 435

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file (67.6 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 203, section 1. The text section number identifies this passage in the reader.

SITE MANAGEMENT RULES FOR ENVIRONMENTAL PROTECTION – ECOLOGICAL RESTORATION PLAN (ERP)                                 B-1

APPENDIX B: SITE MANAGEMENT RULES FOR ENVIRONMENTAL
            PROTECTION – ECOLOGICAL RESTORATION PLAN
            (ERP)
The EMP for the ERP for the Settlers Cove project describes various management actions that will need to be
implemented for the duration of the project. Within these actions, there are a number of overarching Site
Management Rules that are to be stringently applied at the areas of implementation of the ERP ie. the Public
Open Space for Conservation and Waterways Protection (POSCWP), The RF Thompson Environmental Park,
the Esplanade and Council Park.

These rules are specified below . These rules are to be presented at the Site Induction Program to all personnel
who will be working on site. These rules will be given as a handout at the induction program and each person
attending the course will be required to sign a copy indicating that they have read, understood and will comply
with these rules. These rules will also be presented on a notice board clearly visible near the ERP contractors
office.

Any person found to be in breach of these rules will :
•   be advised of such by the ERP Contractor
•   be asked for an explanation as to why the rule has been broken
•   be advised to rectify the breach immediately
•   be required to show cause why they should not be excluded from further work at the site.
•   If necessary, the offender will be required to vacate the site.
•   Any costs for rectification of any breach will be deducted from the relevant contract.

RULES

A) General

        1.      All personnel working at the site are required to attend the Site Induction Training Program
                unless specifically permitted not to do.

        2.      All personnel are to read and sign a Site Management Rules form and provide this to the ERP
                Contractor . A copy of the Site Management rules are to be retained by all personnel who have
                undertaken the training program.

        3.      ‘Duty of Care’ applies to all personnel working at the site.

        4.      Entry to Ecological Restoration Areas (indicated on an attached plan) is prohibited except for
                personnel authorised in writing by the ERP Contractor in liaison with the Restoration Ecologist.

        5.      Any survey pegs or other markings and signs are not to be disturbed or destroyed

        6.      No dogs, cats or other domestic animals are to be brought onto site




          S:\PROJECT MANAGEMENT\4.0 OVERALL DEVELOPMENT SITE\MANAGEMENT PLANS\EMP 3 (WBM OCEANICS).DOC 8/10/07 14:10
Log in to download the original file

RFI - Ecological Assessment Report.pdf · 67.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.