EMP – CONSTRUCTION PHASE 4-5
Strategy: To identify and protect vegetation that is to be retained and manage clearing of
other areas in an environmentally sensitive manner.
10. The location of the ecological restoration launch area (see Ecological Restoration plan) plus
locations for stockpiles, waste disposal areas, etc in relation to the separation distances to
retained bushland areas are to be determined in accordance with guidelines presented in the
respective EMP.
11. The Wildlife Ecologist, Clearing Contractor, SEO and Landscape Architect will then check that
protection measures (including exclusion fencing) are appropriately located as part of the Pre
start meeting. The Clearing Contractor is then to be fully briefed on clearing requirements by
these personnel and the Principal Contractor.
12. Tree limbs (of trees that are to be retained) that are likely to be in the way of earthworks are to be
pruned by the arborist prior to construction activity commencing on the advice of and direction
of the Wildlife Ecologist.
13. Tree roots (of trees that are to be retained) that are likely to interfere with machinery are to be cut
the arborist and the remaining roots treated with a suitable fungicide.
14. Weed control measures prior to clearing are to be implemented in accordance with Element C.4
of the EMP’s and the Ecological Restoration Plan for the POSCWP areas (see Annexure 3 in that
document). Prior to commencement of clearing, weed species are to be identified by the Wildlife
Ecologist.
15. All weeds within the construction area are to be treated and/or removed from the property prior
to clearing.
Clearing Activities
16. Clearing of other non-habitat vegetation within the development area will be undertaken in strict
accordance with this “vegetation clearing and retention strategy”
17. The Wildlife Ecologist, SEO and Clearing Contractor are to make a final check of areas for
clearing immediately prior to commencement.
18. The Principal Contractor/ SEO is to ensure that staff involved in the clearing program have
undertaken the Site Induction Program and followed the Site Management Rules as described in
the Environmental Management Plans.
19. The SEO is to be contacted during the construction phase should access to the Habitat Protection
areas by otherwise unauthorised personnel be necessary.
20. No machinery will be permitted to access Habitat Protection areas unless for approved
infrastructure development.
21. No burning of vegetation or burning and burying of rubbish/waste will be permitted.
22. Stabilization of cleared areas is to be undertaken in accordance with Element C.5 of the
Environmental Management Plans.
23. Clearing will proceed in a staged approach with the initial removal of smaller non-habitat trees
followed by the supervised (wildlife ecologist or spottercatcher) removal of larger habitat trees.
24. Prior to clearing works the area proposed for daily clearing will be surveyed to identify koalas in
G:\ADMIN\B15184.G.DAH\R.B15184.001.05..DOC 22/7/05 10:07
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.