4 November 2022


Noosa Council
[email protected]


RE:    Response to Information Request RAL22/0016 and OPW22/0180
 – 6 Wyandra St, Noosa Heads


Council issued an information request on 30 September 2022. The applicant provides the following
additional information in response to the items:
    1. Provide revised plans set in respect of the Material Change of Use development
       permit, i.e. implement conditions relating to landscaping, footpath requirement etc.

Please find attached an updated set of Operational Works drawings, including earthworks,
stormwater, footpath, driveway sections and landscaping plans from Element.


    2. Provide a Geotechnical Engineer report certifying that the proposed stormwater
       system is suitable to be constructed within the site. The report must be prepared by
       a suitably qualified person (RPEQ – Registered Professional Engineer of
       Queensland).

See attached response from RPEQ.

    3. Provide written advice from a Cadastral Surveyor that clearly indicates if the
       proposed common property over the dividing wall is in accordance with the Land
       Tile Act and would be suitable for registration upon the completion of the
       development.
David Lau from Noosa Cooloola Land Surveys (NCLS) confirms that a community title subdivision
format is suitable for registration. The standard format plan will include the common wall on
common property and the rest of the original parcel subdivided into the 2 lots as per the lodged
application plan. There would be no need for exclusive use allocation of common property with this
model.
Statutory easements will exist for access and services for all community titles schemes hence the
need for the services location diagram with the final Plan Sealing application after the building is
constructed. NCLS will prepare the survey plan, services plans showing the location of proposed
reticulated water, sanitary drainage, rainwater drainage, electricity and communications after the
as-constructed details from the installers are provided.

---------------------------------------------------------------------------------------------------------------------
In addition to the response, please find attached a DA Form 2 for DBW associated with the
demolition of the existing house. We seek for the application to consider this additional element of
the development and for conditions to be included on the Permit accordingly.

Pursuant to the Development Assessment Rules, the applicant has given the assessment manager
the information requested in the information request. Please proceed with the assessment of the
application at your earliest convenience.

If you have any further queries in relation to the above, please do not hesitate to contact myself.

Regards,




Jack Lewis B.Sc Hons UNSW M.Plan Otago MPIA MQELA
Planner/Director
Pivotal Perspective Pty Ltd
0406 334 227
Log in to download the original file

response to information request - OPW 6 wyandra.pdf · 534 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.