Original source · versioned page text
1-22276-01 site plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnProject No. 1-22276 Page | 19
February, 2020
Ref: 1-22276, 2020-02-28, BR VER 2
Wessel Petroleum Pty Ltd – GEOTECHNICAL INVESTIGATION - Proposed Service Station Reconstruction, 52-54 Mary Street and Weyba Road,
Noosaville
Pavement gravels should be compacted to the following minimum density ratios as
determined by AS 1289 Test 5.2.1 (Modified compaction):-
Base material 98%
Sub-base material 95%
Blanket material 95%
Backfill to service trenches should be placed in uniform layers over the full width of the
excavations, with the layers not exceeding 200mm loose thickness using wheeled plant
and 100mm loose thickness using vibrating plates.
The backfill material should be compacted to the above specifications for cohesive
and/or cohesionless materials.
Other comparable compaction specifications may be adopted for earthwork procedures;
however, Soil Surveys Engineering Pty Limited should be consulted to confirm these.
Consideration should be given to adopting a Level 1 earthworks control, in accordance
with the requirements outlined in AS 3798-2007, for the earthworks preparation and
filling operations to ensure the required civil specifications are met for structural support,
and long term integrity of pavements. Level 1 supervision infers that the geotechnical
testing authority provides a full time inspection and testing service on all earthworks on
the project, or the section contracted for, and decides the locations and timing of the
testing. On completion of the earthworks the geotechnical testing authority will provide a
report certifying the fill, setting out inspections, sampling and testing that have been
carried out and the locations and results thereof.
Field density testing should be carried out to check the standard of compaction achieved
and the placement moisture content. The frequency and extent of testing should be as
per guidelines in AS 3798-2007, Section 8.0 or as directed by the Level 1 engineering
supervisor.
Sands should be compacted to achieve the required density index (AS 1289 Test Series
5). Test method AS 1289 6.3.2 ‘Determination of Penetration Resistance of a soil using
the 9kg Dynamic Cone Penetrometer’ is recommended to verify compaction using
accepted density index correlation tables.
Earthworks Supervision
Engineering supervision of the earthworks operations by Soil Surveys Engineering Pty Limited
is recommended.
Following production of AS 3798-2007, the terms "Level 1 and 2 Supervision" have been
adopted in earthworks specifications to describe what could also be termed Engineering
Supervision. Whilst there is no particular problem with using these terms, there does not seem
to be wide agreement as to what Level 1 or 2 Supervision actually means or entails.
Regardless of terminology, it should be made clear in any earthworks specification as to what is
actually required in terms of certification.
It is recommended that the following objectives (as a minimum) be incorporated into the
earthworks specification:-
SOIL SURVEYS
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.