1-22276-01 site plan

of 69

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Project No. 1-22276                                                                                                                               Page | 1
March, 2020
Ref: 1-22276, 2020-03-25, ASSMP VER 2
Wessel Petroleum Pty Ltd – Acid Sulfate Soil Investigation and Management Plan - Proposed Service Station Reconstruction, 52-54 Mary Street and
Weyba Road, Noosaville




Objective

The objective of the ASSMP is to control net acidity levels within the soils disturbed during
construction and to restrict to an acceptable level any potential on-site and off-site
environmental impacts during construction.

Disturbance Due to Filling

In accordance with SPP 2013 ASS Guideline, assessment of potential disturbance to insitu ASS
from filling is required. Considering investigation findings, geotechnical engineering analysis
and proposed earthworks, we advise the following:-

           Actual ASS not currently in contact with water will not contact groundwater due to filling
            given the on-site material characteristics (strength, etc.) and the filling proposed.
           Potential ASS will not be displaced/extruded due to filling given the on-site material
            characteristics (strength, etc.) and the proposed filling.
The above has been considered in formulating the ASSMP.

Groundwater

The hydrological regimes that operate in an area affect the behaviour of ASS and the transport
of oxidation products. Considering investigation findings and the proposed development, we
advise the following:-

           Filling activities, where carried out, will not cause changes to the groundwater regime
            given the proposed filling.
           Groundwater is expected to be encountered during construction.
The above has been considered in formulating the ASSMP.

The following section, which have been prepared in accordance with Appendix B of SPP 2013
ASC guidelines, present the recommended ASSMP for this site.

ASS Management Strategies

The preferred management strategy for ASS is to avoid or minimise the disturbance of these
materials.

Given the proposed development, avoidance of ASS will not be possible and neutralisation of
the disturbed material will be required.

To mitigate and manage potential environmental impacts associated with ASS during the
construction works. This will be achieved as follows:-

           The excavation of soils during construction requires a material handling management
            strategy and procedure for the appropriate treatment of the ASS to be in place.
           Monitoring of groundwater collected within the site to ensure discharge water complies
            with water quality criteria.




                                                                                                                  SOIL SURVEYS
Log in to download the original file

1-22276-01 site plan.pdf · 5.6 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.