Attachment 2 - 1856-EW01_10

of 10

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

     GENERAL NOTES                                                                                    EARTHWORKS AND PAVEMENT
     GN1.        ALL DIMENSIONS AND SET OUT POINTS ARE TO THE KERB LINE OF THE                        CONSTRUCTION NOTES CONTINUED                                                                            SEDIMENT & EROSION CONTROL
                 SPECIFIED KERB TYPE. REFER LOCAL AUTHORITIES STANDARD DRAWINGS FOR
                                                                                                      EW6.          ALL FILLING SHALL BE CLEAN EXCAVATED MATERIAL FREE FROM TOPSOIL
                                                                                                                                                                                                              NOTES
                 KERB TYPE DETAILS.
                                                                                                                    AND VEGETATION.
                                                                                                                                                                                                              SE1.   GENERAL:
     GN2.        FINAL LOCATIONS OF CONDUITS SHALL BE PROVIDED WHEN AVAILABLE FROM                                                                                                                                       a. TEMPORARY DRAINAGE CONTROL. FLOW SHOULD BE
                                                                                                      EW7.          THE EXISTING SITE WON MATERIALS MAY CONTAIN ROCKS AND COBBLES
                 SERVICE AUTHORITIES. (IF REQUIRED).                                                                                                                                                                          DIVERTED AROUND THE WORK SITE WHERE POSSIBLE.
                                                                                                                    AND THESE SHALL BE EXCLUDED OVER 100mm NOMINAL SIZE IN ANY
                                                                                                                    EXISTING MATERIAL USED AS FILLING.                                                                   b.   ALL DRAINAGE, EROSION AND SEDIMENT CONTROLS TO BE
     GN3.        ALL CONSTRUCTION SHALL JOIN SMOOTHLY TO EXISTING.                                                                                                                                                            INSTALLED AND BE OPERATIONAL BEFORE COMMENCING
                                                                                                      EW8.          ANY IMPORTED FILLING MATERIAL REQUIRED TO MAKE UP SHORTFALLS IN                                           UP-SLOPE EARTHWORKS.
     GN4.        NOTIFY ALL RELEVANT AUTHORITIES PRIOR TO COMMENCEMENT OF WORK                                                                                                                                           c.   ALL SEDIMENT & EROSION CONTROL DEVICES MUST BE
                                                                                                                    QUANTITIES SHALL BE CLEAN SOIL MATERIAL FREE FROM TOPSOIL,
                 WITHIN EXISTING ROAD RESERVES.                                                                                                                                                                               REGULARLY INSPECTED AND MAINTAINED BY THE
                                                                                                                    VEGETABLE MATTER AND OTHER DELETERIOUS MATERIAL. THE FILLING
                                                                                                                    SHALL BE FREE FROM COBBLES OR ROCKS IN EXCESS OF 100mm NOMINAL                                            CONTRACTOR. INSPECTIONS SHOULD OCCUR ON A WEEKLY
     GN5.        THE CONTRACTOR SHALL CONTACT ALL RELEVANT SERVICE AUTHORITIES FOR                                                                                                                                            BASIS (MINIMUM), ALONG WITH BEFORE AND AFTER
                 DETAILED LOCATION AND LEVEL OF SERVICES PRIOR TO COMMENCEMENT OF                                   SIZE. THE MATERIAL SHALL HAVE A MINIMUM SOAKED CBR 15 UNLESS
                                                                                                                    OTHERWISE APPROVED BY THE SUPERINTENDENT.                                                                 SIGNIFICANT RUNOFF PRODUCING STORMS.
                 WORKS AND THE SITE. ANY DAMAGE TO EXISTING SERVICES SHALL BE                                                                                                                                            d. ALL DISTURBED LAND MUST BE RENDERED EROSION-PROOF
                 RECTIFIED AT THE CONTRACTORS EXPENSE.                                                                                                                                                                        BY THE ESTABLISHMENT OF 80% EFFECTIVE GROUND
                                                                                                      EW9.          ALL FILLING SHALL BE PLACED IN MAXIMUM 200mm LOOSE LAYER
                                                                                                                    THICKNESS WITH EACH LAYER COMPACTED TO AT LEAST 98% COMPACTING                                            COVER WITHIN 28 DAYS OF FINAL EARTHWORKS TRIM.
     GN6.        ALL WORK SHALL CONFORM WITH THE RELEVANT LOCAL AUTHORITY'S                                                                                                                                              e. IN AREAS WHERE RUNOFF TURBIDITY IS TO BE
                 SPECIFICATIONS AND REQUIREMENTS.                                                                   AS MEASURED BY THE STANDARD METHOD DESCRIBED IN AS 1289.
                                                                                                                                                                                                                              CONTROLLED, EXPOSED SURFACES TO BE EITHER
                                                                                                      EW10.         REFER TO THE GEOTECHNICAL REPORT REGARDING REMOVAL AND                                                    MULCHED, COVERED WITH EROSION CONTROL BLANKETS
     CLEARING OF VEGETATION                                                                                         REPLACEMENT OF EXISTING FILLING MATERIAL. THIS NOTE SHALL APPLY TO                                        OR TURFED IF EARTHWORKS ARE EXPECTED TO BE
                                                                                                                    THE SUBGRADE UNDER ALL ROADS, DRIVEWAYS AND FILL BATTERS.                                                 DELAYED FOR MORE THAN 14 DAYS.
     VE1.        NO CLEARING SHALL BE CARRIED OUT BEYOND THE EXTENT                                                 FOLLOWING THE SITE STRIP AND DRIVEWAY SET OUT THE ENGINEER SHALL                                     f.   STRAW BALE SEDIMENT TRAPS ARE A SECONDARY OPTION
                 OF EARTHWORKS OR WHERE NECESSARY FOR SERVICES                                                      BE CALLED TO SITE TO DETERMINE THE PRESENCE OF ANY EXISTING FILL                                          WHICH GENERALLY SHOULD NOT BE USED IF OTHER
                 CONSTRUCTION WITHOUT THE WRITTEN APPROVAL OF THE                                                   UNDER DRIVEWAYS AND ASSOCIATED BATTERS. PROVIDE A BACKHOE FOR                                             OPTIONS ARE AVAILABLE.
                 SUPERINTENDENT.                                                                                    THE TEST PIT EXPLORATION. THE ENGINEER MAY DIRECT EXISTING LOOSE
                                                                                                                    FILL TO BE REMOVED AND RE-COMPACTED.                                                      SE2.   SEDIMENT CONTROL FENCE:
     VE2.        MILLABLE LOGS ARE TO BE REMOVED FOR SAWMILLING.                                                                                                                                                         g. NOT TO BE LOCATED IN AREAS OF CONCENTRATED FLOW.
                                                                                                      EW11.         ALL DRAINAGE, EROSION AND SEDIMENT CONTROLS TO BE INSTALLED AND                                      h. NORMALLY LOCATED ALONG THE CONTOUR WITH A
     VE3.        SUITABLE MATERIAL IS TO BE MULCHED FOR REUSE ON SITE.                                              FULLY OPERATIONAL BEFORE COMMENCING UP-SLOPE EARTHWORKS.                                                 MAXIMUM CATCHMENT AREA 0.6 HA PER 100M LENGTH OF
                                                                                                                                                                                                                             FENCE.
     EARTHWORKS AND PAVEMENT                                                                          EW12.         ALL EXISTING UNDERGROUND SERVICES TO BE LOCATED AND MARKED                                           i.  WOVEN FABRICS ARE PREFERRED, NON-WOVEN FABRICS
                                                                                                                    PRIOR TO COMMENCING EARTHWORKS.                                                                          MAY BE USED ON SMALL WORK SITES, I.E. OPERATIONAL
     CONSTRUCTION NOTES                                                                                                                                                                                                      PERIOD LESS THAN 6 MONTHS OR ON SITES WHERE
                                                                                                      EW13.         FILL DENSITY TESTING SHALL CONFORM TO THE FOLLOWING:                                                     SIGNIFICANT SEDIMENT RUNOFF IS NOT EXPECTED.
     EW1.        THE CONTRACTOR SHALL PROVIDE CERTIFICATION FROM A RPEQ QUALIFIED                                         a. 1 TEST PER 500 cu.m - GENERALLY                                                             j.  WHERE FENCES NEED TO BE LOCATED ACROSS THE
                 ENGINEER THAT THE WHOLE OF THE EARTHWORKS AND GEOTECHNICAL                                              b. 1 TEST PER 2 LAYERS PER 40m - TRENCH BACKFILL                                                    CONTOUR - REFER IPEAW STANDARD DRAWING D-0040 FOR
                 SUPERVISION COMPLIES WITH AS3798 FOR                                                                                                                                                                        DETAILS.
                                                                                                      EW14.         PLACEMENT OF FILL SHALL CONFORM TO THE FOLLOWING MINIMUM DRY                                         k. FENCES ARE REQUIRED 2m MIN FROM TOE OF CUT OR FILL
     EW2.        THE CONTRACTOR SHALL REFER TO GEOTECHNICAL INVESTIGATION                                           DENSITY RATIO (M.D.D.R.) COMPACTION STANDARDS:                                                           BATTERS, WHERE NOT PRACTICAL ONE FENCE CAN BE AT
                 REPORT - (IF AVAILABLE)                                                                                c.   ALLOTMENTS = 98% STD                                                                            THE TOE WITH A SECOND FENCE 1M MIN AWAY. FENCE
     EW3.        ALL EXISTING UNDERGROUND SERVICES TO BE LOCATED AND MARKED PRIOR                                       d. ROAD VERGES/EMBANKMENTS = 98% STD                                                                 SHOULD NOT BE LOCATED PARALLEL WITH TOE IF
                 TO COMMENCING EARTHWORKS.                                                                              e. PAVEMENT SUBGRADE = 100% STD FOR NON-COHESIVE                                                     CONCENTRATION OF FLOW WILL OCCUR BEHIND THE FENCE.
                                                                                                                             MATERIALS, M.D.D.R. = 80%
     EW4.        THE LIMITS OF CUTTING AND FILLING SHALL BE GENERALLY AS SHOWN ON THE                                                                                                                         SE3.   TEMPORARY CONSTRUCTION ENTRY/EXIT SEDIMENT TRAP:
                 DRAWINGS. THE CONTRACTOR SHALL SET OUT THESE LIMITS FOR INSPECTION                   EW15.         ALL ALLOTMENTS OR AREAS SUBJECT TO EARTHWORKS ARE TO BE FREE                                         l. ADJACENT STORMWATER RUNOFF TO BE DIVERTED AWAY
                 BY THE ENGINEER PRIOR TO CONSTRUCTION. AMENDMENTS TO EARTHWORKS                                    DRAINING WITH A MINIMUM SLOPE OF 1:100.                                                                 FROM ENTRY/EXIT.
                 AND FINISHED SURFACE CONTOURS MAY BE ADJUSTED BY THE WRITTEN                                                                                                                                            m. WHEEL - WASH OR SPRAY UNIT MAY BE REQUIRED DURING
                 DIRECTION OF THE ENGINEER DURING CONSTRUCTION.                                       EW16.         ALL EXISTING GRASSED AREAS DISTURBED DURING CONSTRUCTION SHALL                                          WET WEATHER.
                                                                                                                    BE TOP SOILED TO A MINIMUM DEPTH OF 100mm AND TURFED OR SEEDED
     EW5.        SITE PREPARATION:                                                                                  WITH A MINIMUM STRIKE RATE OF 80% PRIOR TO ANY 'ON MAINTENANCE'                           SE4.   SAFETY ISSUES MUST BE CONSIDERED AT ALL TIMES, INCORPORATE
                 a. STRIP TOPSOIL MIN 150 OR MORE AS REQUIRED TO REMOVE ALL                                         INSPECTION.                                                                                      TRAFFIC CONTROL DEVICES .
                      VEGETABLE MATTER TO THE BASE OF THE SUB GRADE.
                                                                                                      EW17.         ALL TEMPORARY STOCKPILES (IF APPLICABLE) TO HAVE 1:6 MAXIMUM SIDE                         SE5.   IT IS THE CONTRACTOR'S RESPONSIBILITY TO ENSURE THAT ALL
                 b.   FURTHER EXCAVATE IF REQUIRED TO BOX OUT TO MINIMUM PAVEMENT                                   BATTERS (GRASS SEEDED).                                                                          SEDIMENT AND EROSION CONTROL MEASURES HAVE BEEN
                      THICKNESS. REMOVE AND RE-COMPACT FILL AS PER GEOTECHNICAL                                                                                                                                      ADDRESSED AS STIPULATED IN THE ENVIRONMENTAL MANAGEMENT
                      REPORT NOTE ON THIS DRAWING.                                                            SEDIMENT & EROSION CONTROL PROGRAM                                                                     PLAN. ADDITIONAL OR DIFFERENT SEDIMENT & EROSION CONTROL
                                                                                                                    OBJECTIVE/TARGET                    THE CONTRACTOR MUST COMPLY WITH ALL STATUTORY                DEVICES MAY BE REQUIRED DURING CONSTRUCTION PHASE TO
                                                                                                                                                        REGULATIONS AND MAINTAIN THEM DURING EARTHWORKS/             COMPLY WITH THE ABOVE.
                 c.   COMPACT SUBGRADE TO A MIN RELATIVE DENSITY RATIO OF 98%                                                                           CONSTRUCTION. ALL PROVISIONS AND SPECIFICATIONS
                      STANDARD COMPACTION AS DEFINED IN AS 1289 IN THE TOP 200.                                                                         OUTLINED WITH THE APPROVED ENVIRONMENTAL
                                                                                                                                                        MANAGEMENT PLAN MUST BE ADHERED TO, ALONG WITH        SE6.   TEMPORARY STOCKPILES TO HAVE 1:6 SIDE BATTERS (MAXIMUM) AND
                                                                                                                                                        ALL EROSION AND SEDIMENT CONTROL MEASURES
                 d.   COMPACT AND PROOF ROLL ALL PREPARED SUBGRADE AREAS PRIOR TO                                                                       PRESCRIBED WITHIN THESE DRAWINGS BY THE                      BE SHAPED TO ENSURE RUN-OFF IS TREATED AND MANAGED TO THE
                      PLACING ANY FILLING. COMPACTION SHALL BE 100% COMPACTION AS                                                                       SITE ENGINEER                                                SATISFACTION OF THE SUPERINTENDENT. ALL EXPOSED STOCKPILE
                      MEASURED BY THE STANDARD METHOD DESCRIBED IN AS1289 UNO.                                      MANAGEMENT                          THE SITE FOREMAN IS TO IDENTIFY AND CHECK THE                SURFACES TO BE GRASS SEEDED. SEDIMENT FENCES AND CUT-OFF
                                                                                                                    STRATEGY                            DIRECTION OF STORMWATER FLOWS AS SHOWN ON PLAN.              DRAINS MAY BE REQUIRED.
                                                                                                                                                        PROVIDE BARRIERS AND OTHER MEASURES SHOWN ON
                 e.   EXCAVATE AND REPLACE WITH STRUCTURAL FILL ANY SOFT SPOTS OR                                                                       PLAN TO PREVENT STORMWATER FLOWS OVER
                      HEAVING SUBGRADE AREAS. STRUCTURAL FILL SHALL BE APPROVED                                                                         EMBANKMENTS, AND SEDIMENT INTO GULLY PITS
                      GRANULAR FILL (100mm MAXIMUM PARTICLE SIZE, MINIMUM SOAKED CBR
                                                                                                                    TASKS / ACTIONS                     ERECT SEDIMENTATION BARRIERS AS DETAILED.
                      15 PLACED IN LAYERS NOT EXCEEDING 200mm AND COMPACTED TO                                                                          STRATEGICALLY PLACE CHECK DAMS                               NOTE:
                      ACHIEVE NOT LESS THAN 98 % MAXIMUM RELATIVE DRY DENSITY                                                                           AROUND GULLY PITS
                                                                                                                                                                                                                     EROSION AND SEDIMENT CONTROL MEASURES ARE TO BE DESIGNED
                      (STANDARD), OR 75 % DRY DENSITY INDEX IN ACCORDANCE WITH AS 1289.                             PERFORMANCE                         THE SITE FOREMAN IS TO CHECK FOR EROSION AND                 AND PROVIDED IN ACCORDANCE WITH THE INTERNATIONAL EROSION
                      SITE FILLING MATERIAL AND COMPACTION UNDER THE PAVING AND                                     INDICATORS                          SEDIMENT FLOWS AT THE BASE OF EMBANKMENTS AFTER
                                                                                                                                                                                                                     CONTROL ASSOCIATION (AUSTRALASIA) 2018's "BEST PRACTICE
                                                                                                                                                        SIGNIFICANT RAINFALL AND SHOULD ASCERTAIN THE
                      BUILDING SHALL BE AS ABOVE.                                                                                                       WORKING EFFECTIVENESS OF CHECK DAMS DURING                   EROSION AND SEDIMENT CONTROL FOR BUILDING AND
                                                                                                                                                        THIS WET WEATHER                                             CONSTRUCTION SITE.
                                                                                                                    FREQUENCY /                         SITE FOREMAN TO MONITOR PERFORMANCE AFTER
                                                                                                                    DEADLINE                            EVERY HEAVY DOWNFALL

                                                                                                                    RESPONSIBILITY                      THE SITE FOREMAN IS RESPONSIBLE FOR ALL INSPECTIONS

                                                                                                                    REPORTING REVIEW                    SITE WORKMEN ARE TO ADVISE THE FOREMAN IF ANY
                                                                                                                                                        SEDIMENT & EROSION CONTROL DEVICES ARE FAILING

                                                                                                                    CORRECTIVE ACTIONS                  THE SITE FOREMAN IS TO REPORT AND ORDER THROUGH
                                                                                                                                                        SUPERVISOR, EXTRA BARRIER OR CHECK DAMS AS
                                                                                                                                                        REQUIRED

                                                                                                                                                                                                                                                                                 PROJECT:                               JOB NUMBER
REV DATE DESCRIPTION                                  BY     CHKD DRAWN
                                                                      I GDETAL
                                                                             IS                                                  SCALE                                                  APPROVED                                                                                 PROPOSED SUBDIVISION                        1856
 A    19-02-20   FOR APPROVAL                          MM      CL                                                                                                                                                                                                                AT NOOSA CIVIC, WALTER HAY DRIVE
                                                                     DATUM                AHD                                                                                                                                                                                                                       SHEET:    2   OF   10
                                                                                                                                                                                                                                                                                 FOR STOCKWELL PTY LTD
                                                                     DESIGN               MM                                                                                          .................                                                                                                             DRAWING NUMBER      REV
                                                                                                                                                                                                                                                                                 DRAWING TITLE:
                                                                     DRAWN                MM                                                                                     Director: CAMERON LANDRETH
                                                                     DESIGN CHECK                                                                                                         (RPEQ 19358)                p 07 5443 8285                                             EARTHWORKS NOTES                    EW02                   A
                                                                                          CL
                                                                                                   This drawing is not to be copied or amended without written permission from                                        e [email protected] w www.barlowshelley.com.au
                                                                     DATE               13-09-19   Barlow Shelley Consulting Engineers                                                                                a PO Box 899, Maroochydore,4558 ABN 89 215 591 077
Log in to download the original file

Attachment 2 - 1856-EW01_10.pdf · 3.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.