PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 26 MAY 2015
Preparation of a Preliminary Construction Management Plan
5. The works identified in this Decision Notice will be required to be carried out in accordance
with a Construction Management Plan endorsed by Council through an approval for
Operational Works. To ensure expedient assessment of any Operational Works
application, the applicant is advised to submit a preliminary Construction Management Plan
that addresses the requirements of the planning scheme. In particular, the preliminary
Construction Management Plan should address the following:
a. traffic management during all aspects of the construction phase including:
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction
ii. maintenance of safe pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased
iii. proposed fencing to the site during the construction phase of the development
b. maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures
c. works programme identifying key components of the works and their respective
durations
d. establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues
e. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
f. details on the location of external fill sites/sources, the haulage route, type of vehicle
to be utilised during filling operations and frequency of usage. NB any damage to the
existing road system as a result of haulage operations shall be fully repaired at the
applicant’s expense
g. it is acknowledged that the Construction Management Plan will be a draft document
requiring finalisation upon appointment of the Principal Contractor employed to
construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.
Building Works
6. Noise from building works shall comply with the following –
a. Limited to between 6:30am to 6:30pm Monday to Saturday.
b. All reasonable measures are taken to minimise noise emissions.
c. Not permitted on Sunday or public holidays.
Page 48 of 171
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.