Minor Change Existing Approval MCU21/0228.02 & OPW21/0364.02 [As Published]
e. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Stormwater Drainage
65. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
66. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (eg by blocking or interfering with natural overland flows).
67. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Erosion and Sediment Control
68. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination. These
measures must be designed, implemented and maintained in accordance with “Best Practice
Erosion and Sediment Control” published by the International Erosion Control Association
(Australasian Chapter) (IECA, 2008), to the extent that such measures and practices are also
consistent with the following:
a. Minimise Erosion
i. For areas of the site which drain to a sediment basin, implement drainage and
erosion control measures prior to rainfall which prevent or minimise rill erosion
and gully erosion
ii. For areas of the site which do not drain to a sediment basin, implement drainage
and erosion control measures prior to rainfall (including contingency measures)
which prevent or minimise erosion, including rain drop erosion, chemical erosion,
rill erosion and gully erosion
iii. Prior to the final inspection for the development, all site surfaces must be
effectively stabilised using methods which have achieved effective short-term
stabilisation and which will continue to achieve effective stabilisation in the
medium to long-term. For the purpose of this condition, an effectively stabilised
surface is defined as one that does not, or is not likely to result in visible evidence
of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead
to water contamination.
b. Manage concentrated stormwater flows
i. Prior to each rainfall event ensure concentrated stormwater flow paths are
provided with capacity in accordance with IECA (2008) Table 4.3.1 and are
structurally stable in all rainfall events for the following sources:
(a) From stormwater catchments upslope of the area of disturbance
which are either stable or external to the site, ensure stormwater is diverted
or managed either:
i. around the site or through the site without causing erosion and
without contaminating the flow; or
ii. if it is impractical to convey the flows around or through the site,
convey the flows into appropriately sized sediment basins without
causing erosion
(b) From all disturbed areas of the site to sediment basin(s) without causing
erosion
Page 10 of 18
Document Set ID: 24329699
Version: 3, Version Date: 24/11/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval MCU21/0228.02 & OPW21/0364.02 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 206 KB (small file)
- File type
No other editions are linked here.