GENERAL COMMITTEE MEETING                                                  12 NOVEMBER 2018


GENERAL COMMITTEE MEETING - LIVE RECORD MEETING NOTES
12 NOVEMBER 2018 – Crs. Frank Wilkie (Chair), Jess Glasgow, Ingrid Jackson, Joe
Jurisevic, Frank Pardon and Brian Stockwell, Tony Wellington


1   MCU18/0102 DEVELOPMENT APPLICATION FOR A MATERIAL CHANGE OF USE
    FOR VISITOR ACCOMMODATION TYPE 4 CONVENTIONAL (122 BEDS) AT 16 MARY
    STREET, NOOSAVILLE
    Committee Recommendation
    Moved:             Cr Stockwell
    Seconded:          Cr Jurisevic
    That Council note the report by the Coordinator Planning to the Planning & Environment
    Committee Meeting dated 6 November 2018 regarding Application No. MCU18/0102 for a
    Development Permit for Material Change of Use - Visitor Accommodation - Type 4
    Conventional (122 beds) situated at 14-16 Mary Street Noosaville and defer consideration
    of the matter to the Ordinary Meeting dated 15 November to allow staff to bring forward a
    further report with amended conditions of approval to include conditions which approve the
    height of the building as proposed by the applicant, allow operation of the internal pool and
    café area until 10pm at night, that condition the operation to install a sound monitoring
    system and 24hr onsite management to maintain statutory requirements in terms of noise
    nuisance and allow Council the opportunity to review compliance of that noise condition in
    12 months, and reduce the extent of acoustic fencing.
                                                                                         Carried.


2   NOOSA SPIT SHORELINE EROSION INVESTIGATION - SHORELINE EROSION
    MANAGEMENT PLAN
    Moved:           Cr Stockwell
    Seconded:        Cr Wellington
    That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore
    to the Services & Organisation Committee Meeting dated 6 November 2018 and support
    the completion of a Shoreline Erosion Management Plan for Noosa Spit and Noosa Main
    Beach subject to funding being provided in Budget Review 2.

    Amendment
    Moved:           Cr Pardon
    Seconded:        Cr Jurisevic
    That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore
    to the Services & Organisation Committee Meeting dated 6 November 2018 and support
    the urgent completion of a Shoreline Erosion Management Plan for Noosa Spit and Noosa
    Main Beach subject to funding being provided in Budget Review 2.
                                                                                     Carried.




                                                                                   Page 1 of 13
Log in to download the original file

2018-11-12 General Committee Meeting Notes(PDF, 642KB).pdf · 657 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 12 sections

Section 2

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                               12 NOVEMBER 2018


    Committee Recommendation
    Moved:         Cr Stockwell
    Seconded:      Cr Wellington
    That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore
    to the Services & Organisation Committee Meeting dated 6 November 2018 and support
    the urgent completion of a Shoreline Erosion Management Plan for Noosa Spit and Noosa
    Main Beach subject to funding being provided in Budget Review 2.
                                                                                     Carried.




3   REFUGEE WELCOME ZONE
    Committee Recommendation
    Moved:           Cr Wellington
    Seconded:        Cr Jackson
    That Council note the report by the Community Development Manager to the Services &
    Organisation Committee Meeting dated 6 November 2018 and agree to declare Noosa
    Shire as a Refugee Welcome Zone by signing The Refugee Council of Australia’s Refugee
    Welcome Zone Declaration.
                                                                                  Carried.




4   ANNUAL REPORT
    Committee Recommendation
    Moved:           Cr Wellington
    Seconded:        Cr Glasgow
    That Council note the report by the Director Executive Services to the Services &
    Organisation Committee Meeting dated 6 November 2018 and:
    A.   Adopt the ‘2017/18 Annual Report’ (provided at Attachment 1 to the report)
         incorporating the 2017/18 Audited Financial Statements; and
    B.   Authorise the Chief Executive Officer to make any required minor amendments to the
         document prior to publication.
                                                                                    Carried.




                                                                                Page 2 of 13

Section 3

 RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                                        12 NOVEMBER 2018


5                      FURTHER REPORT MCU18/0094 DEVELOPMENT APPLICATION FOR MATERIAL
                       CHANGE OF USE, MULTIPLE HOUSING TYPE 4 (4 DWELLING UNITS), 15 GARNET
                       STREET, COOROY
DOMENT INFORM AT ION




                       Committee Recommendation
                       Moved:           Cr Jurisevic
                       Seconded:        Cr Stockwell
                       That Council note the further report by the Development Planner to the General Committee
                       Meeting dated 12 November 2018 regarding Application No. MCU18/0094 for a
                       Development Permit for Material Change of Use for Multiple Housing - Type 4
                       Conventional. (4 Dwelling Units) situated at 15 Garnet St, Cooroy and approve the
                       application in accordance with following the conditions:
                       PLANNING
                       When Conditions must be Complied With
                       1.     Unless otherwise stated, all conditions of this Decision Notice must be complied with
                              prior to the use commencing, and then compliance maintained at all times while the
                              use continues.
                       Approved Plans
                       2.     Development undertaken in accordance with this approval must generally comply
                              with the approved plans of development. The approved plans are listed in the
                              following table unless otherwise amended by these conditions.
                        Plan No.   Rev.   Plan/Document Name                                        Date
                        A10        G      Ground – Site Plan, drawn by Morriarchi Architecture      29 October 2018

                        A11        F      Level 1 – Roof – Site Plan, drawn by Morriarchi           29 October 2018
                                          Architecture
                        A12        C      Townhouse Type A (3 bed) – Floor Plans, drawn by          3 July 2018
                                          Morriarchi Architecture
                        A13        C      Townhouse Type B (2 bed) – Floor Plans, drawn by          3 July 2018
                                          Morriarchi Architecture
                        A14        B      Landscape Plan, drawn by Morriarchi Architecture          29 October 2018
                        A20        F      Elevations, drawn by Morriarchi Architecture              30 October 2018
                        A30        F      Sections, drawn by Morriarchi Architecture                29 October 2018
                        A80        G      Perspective Images, drawn by Morriarchi Architecture      30 October 2018
                        A81        B      Finishes                                                  30 October 2018

                       Nature and Extent of Approved Use
                       3.     This approval is for 1 x 3 bedroom unit and 3 x 2 bedroom units. The TV/Study room
                              is not permitted to be fully enclosed for use as a bedroom.
                       Building Height
                       4.     The maximum height of the development must not exceed 8 metres above the
                              finished ground level and the natural ground level.



                                                                                                       Page 3 of 13

Section 4

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 12 NOVEMBER 2018


    Performance Bond
    5.    Security in the form of a cash bond or trading bank guarantee to the sum of $20,000
          must be submitted to Council, to secure performance of all conditions of this
          approval, prior to pre-start meeting. The cash bond or trading bank guarantee will be
          returned on performance of the conditions of approval less any costs incurred by
          Council in respect of enforcing performance of this permit. Council reserves the right
          to call upon the bond or guaranteed sum to effect compliance with conditions.
    Street Identification
    6.    The street address of the development must be clearly visible and discernible from
          the primary frontage of the site by the provision of a street number and, where
          appropriate, the building name.
    Building Appearance
    7.    All air conditioning units or other mechanical equipment must be located at ground
          level, or otherwise fully enclosed or screened such that they are not visible from the
          street frontages nor adjoining properties.
    Fencing and Walls
    8.    Any street fencing must be set back an average of 1 metre from the front property
          boundary. Any fencing on the front boundary must either:
          a.   not exceed a maximum height of 1.2m
          b.   be of open construction.
    9.    The area of land between the fence and the front property boundary must be densely
          landscaped to screen any fencing from the street.
    Clothes Drying Areas
    10.   Each dwelling unit must be provided with access to an outdoor clothes line which is
          screened from public view.
    Protection of Privacy
    11.   To ensure privacy is protected between adjoining properties, the windows located on
          the upper western building face of the building must either:
          a.   have a minimum window sill height or 1.5 metres above floor level;
          b.   be fitted with translucent glazing;
          c.   be fitted with a fixed external screen.
    12.   Any proposed Community Management Statement required for the development
          pursuant to the Body Corporate and Community Management Act 1997 must be
          submitted to Council for endorsement at the same time as submission of the Building
          Format Plan (or similar) to Council for compliance assessment.
    13.   All clauses and by-laws of the proposed Community Management Statement must
          accord with the requirements of this Decision Notice.
    Retention of mango tree
    14.   The existing mango tree located in the north eastern corner on the site must be
          retained.

                                                                                    Page 4 of 13

Section 5

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                  12 NOVEMBER 2018


    15.   An Arborist Report (or part thereof) prepared by a qualified person* and endorsed
          through an Operational Works approval must provide recommendations for the
          design of civil works, including retaining walls, to accommodate the retention of the
          Mango tree.
    16.   The Mango tree identified for retention in the conditions of this approval must be
          maintained in good health during construction and operational use for the expected
          life of the tree.
          *(Refer to Advisory Note)
    Landscaping Works
    17.   The development site must be landscaped. The works must be undertaken in
          accordance with an Operational Works approval and the Noosa Plan Planning
          Scheme Policy PSP 3 – Landscaping Plants and Guidelines and must include in
          particular:
          a.   The works shown on the approved Landscape Concept Plan using
               predominately local native species;
          b.   The provision of 6 x 100L local native street trees to the road frontages suitable
               for the location and sight lines.
          c.   Retention of the mango tree within the north eastern corner of the lot within a
               mulched garden setting.
    18.   All landscape works must be established and maintained in accordance with the
          approved design for the life of the development, and in a manner that ensures
          healthy, sustained and vigorous plant growth. All plant material must be allowed to
          grow to full form and be refurbished when its life expectancy is reached.
    19.   All landscape works must be maintained generally in accordance with the approved
          design for the life of the development.
    ENGINEERING
    External Works
    20.   A 2.0m wide concrete footpath must be provided within the road verge for the entire
          length of the frontage of the site to Wattle Street. The path must generally match with
          the existing grassed verge without causing a trip hazard. The works must be
          undertaken in accordance with an Operational Works approval and must
          include/address the following:
          a.   Be in compliance with IPWEAQ standard drawing SEQ R-065 Concrete
               Pathway Construction Details;
          b.   Be extended to smoothly tapered and join with the existing path along Garnet
               Street.
    Reinstatement Works
    21.   Any redundant driveway and/or kerb layback must be removed, and the kerb line and
          verge area reinstated and landscaped to match the existing kerb and/or verge
          treatments. Grassed verge areas to be reinstated must be provided with 100 mm
          topsoil and turf, and must be maintained by the developer until established.



                                                                                   Page 5 of 13

Section 6

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                  12 NOVEMBER 2018


    22.   Any redundant private pathway to the property must be removed, and verge area
          reinstated and landscaped to match the verge treatments.
    23.   Any damaged kerb and channel along the frontage of the site must be repaired to the
          reasonable satisfaction of Council’s representative.
    Site Access and Driveways
    24.   A sealed access driveway must be provided from Garnet Street to all parking and
          manoeuvring areas of the development. The works must be undertaken in
          accordance with an Operational Works approval and must include in particular:
          a.   Driveway crossovers in accordance with IPWEAQ standard drawings R-049
               and R-050 to grades prevent vehicles from scraping and/or bottoming whilst
               also allowing for compliant grades for the footpath and pedestrians movements
               along the footpath and the grassed verge without any step or trip hazard.
    Car Parking
    25.   Car parking must be provided within the site generally as shown on the approved
          plans. The works must be undertaken in accordance with an Operational Works
          approval and must be in compliance with the provisions of AS/NZS 2890.1-2004 with
          allowance for standard vehicle to enter and leave the site in a forward gear and with a
          minimum head clearance (headroom) at any point of 2.2m.
    26.   All car parking areas and access driveways must be maintained exclusively for
          vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
    Stormwater Drainage
    27.   The site must be provided with a stormwater drainage system connecting to a lawful
          point/s of discharge in Garnet Street and/or Wattle Street. The works must be
          undertaken in accordance with an Operational Works approval in compliance with the
          relevant sections of Queensland Urban Drainage Manual and supported by a detailed
          stormwater drainage design prepared and certified by a suitably qualified and
          experienced Registered Professional Civil Engineer (RPEQ).
    28.   The development of the site must not worsen existing drainage conditions on other
          properties by diverting stormwater runoff or cause additional stormwater ponding on
          any other property.
    29.   Stormwater runoff from the development must be disposed of on-site without causing
          scour or damage to the subject site or any adjoining property.
    Earthworks and Retaining Walls
    30.   All earthworks must be carried out in compliance with an Operational Works
          Development Permit.
    31.   All earthworks and associated batters/retaining walls must be contained entirely
          within the subject site unless written permission from the respective landowner(s) is
          provided to Council.
    32.   All earthworks must be undertaken in accordance with the provisions of Australian
          Standard AS3798: Guidelines on Earthworks for Commercial and Residential
          Developments, Council’s codes and relevant government regulations and guidelines.
          Certification must be provided by an RPEQ and submitted to Council prior to the
          issue of the Certificate of Classification for the building.

                                                                                   Page 6 of 13

Section 7

 RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                                            12 NOVEMBER 2018


                         33.   The development works must not adversely impact on the stability of the subject site,
                               any other property or private/ public structure and the long term health of the existing
                               mango tree as shown on the landscape plan A14 Rev B.
                         34.   Earthworks and development works carried out on site must not affect the structural
                               integrity of any of the existing fences or structures that border the site. Fences that
                               are affected shall be replaced prior to the Building Certifier issuing the Certificate of
                               Classification.
                         Telecommunication Services
                         35.   Unless otherwise stipulated by telecommunications legislation at the time of
                               construction, the development must be provided with all necessary conduits, pits and
                               pipes to accommodate the future connection of optic fibre technology
                               telecommunications.
                                                                                                          Carried.


6                        132007.2446.03 REQUEST TO CHANGE AN EXISTING APPROVAL FOR MATERIAL
                         CHANGE OF USE FOR VISITOR ACCOMMODATION TYPE 4 CONVENTIONAL
                         (HOSTEL ACCOMMODATION) AT 102 AND 106 PACIFIC AVENUE SUNSHINE BEACH
DOCUMENT INFORM AT ION




                         Committee Recommendation
                         Moved:             Cr Jurisevic
                         Seconded:          Cr Pardon
                         That Council note the report by the Coordinator Planning to the General Committee
                         Meeting dated 12 November 2018 regarding Application No. 132007.2446.03 to make a
                         change to an existing approval for Material Change of Use for Visitor Accommodation Type
                         4 Conventional (Hostel Accommodation) - additional 21 beds situated at 102 and 106
                         Pacific Ave, Sunshine Beach and:
                         A.    Approve the change.
                         B.    Include the following additional conditions:
                               When Conditions must be Complied With
                               64.   Unless otherwise stated, all conditions of this Decision Notice must be complied
                                     with prior to the use commencing, and then compliance maintained at all times
                                     while the use continues.
                               Approved Plans
                               65.   Development undertaken in accordance with this approval must generally
                                     comply with the approved plans of development. The approved plans are listed
                                     in the following table unless otherwise amended by these conditions.
                               Plan No.    Rev.    Plan/Document Name                                     Date
                               18101-01    P       Site Plan, by PJ concepts and design                   09.07.2018
                               18101-02    P       Landscape Plan, by PJ concepts and design              09.07.2018
                               18101-03    P       Floor Plan – Lot 106, by PJ concepts and design        09.07.2018
                               18101-04    P       Elevations –Sheet 1, by PJ concepts and design         09.07.2018
                                                   Noise barrier plan



                                                                                                           Page 7 of 13

Section 8

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                12 NOVEMBER 2018


        Nature and Extent of Approved Use
        66.   An additional 21 beds are approved for the Visitor Accommodation Type 4 –
              Conventional (visitor hostel). The total number of beds approved are 69 and
              one manager’s unit.
        67.   The approved accommodation units must be used for short term visitors only.
              The approved units must not be occupied by persons for the purpose of
              permanent accommodation.
        68.   Amplified music must not be audible at the boundaries of the site between
              10pm and 7am.
        Landscaping
        69.   The development site must be landscaped. The works must be undertaken in
              accordance with an Operational Works approval, the Planning Scheme Policy 3
              Landscaping Plants and Guidelines for Sunshine Beach and must include in
              particular:
              a.   the works generally shown on the approved site plan including:
                   i.     A minimum 1.0 metre wide landscaping strip along the northern side
                          boundary of the subject site, exclusive of the access driveway,
                          generally uncompromised by infrastructure items designed such
                          that vegetated screening will be provided within 3 years of the
                          plantings occurring.
                   ii.    A minimum 2.0 metre wide landscaping strip along the full extent of
                          the eastern boundary designed such that vegetated screening will
                          be provided within 3 years of the plantings occurring.
                   iii.   Vegetated screening of any electrical transformers, bin storage
                          areas and the like from the road frontage
                   iv.    Provision of 1 street tree within the road reserve for every 8 metres
                          of road frontage including landscaping to the crossover works
                   v.     Trees on the northern boundary must be retained to provide visual
                          screening of the development. Where civil works impact on the
                          capacity to retain the tree, the tree may be removed and replaced
                          with a tree of a minimum pot sized 100 litres.
        70.   All landscape works must be established and maintained in accordance with
              the approved design for the life of the development, and in a manner that
              ensures healthy, sustained and vigorous plant growth. All plant material must
              be allowed to grow to full form and be refurbished when its life expectancy is
              reached.
        Performance Bond
        71.   Security in the form of a cash bond or trading bank guarantee to the sum of
              $10,000 must be submitted to Council, to secure performance of all conditions
              of this approval, prior to the issue of a Development Permit for Operational
              Works. The cash bond or trading bank guarantee will be returned on
              performance of the conditions of approval less any costs incurred by Council in
              respect of enforcing performance of this permit. Council reserves the right to
              call upon the bond or guaranteed sum to effect compliance with conditions.

                                                                                 Page 8 of 13

Section 9

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                12 NOVEMBER 2018


        Water & Sewer Connections
        72.   An underground connection to reticulated water and sewerage must be
              provided to the development site in accordance with the standards and
              requirements of Northern SEQ Distributor–Retailer Authority (Unitywater).
        73.   A Certificate of Completion from the Northern SEQ Distributor–Retailer
              Authority (Unitywater) must be submitted to Council that certifies an
              underground connection to reticulated water and sewerage has been provided
              to the development site.
        Building Appearance
        74.   All air conditioning units or other mechanical equipment must be located at
              ground level, or otherwise fully enclosed or screened such that they are not
              visible from the street frontages nor adjoining properties.
        75.   All deck and balcony areas above ground floor must not be enclosed by
              permanent fixtures such as shutters, louvres, glass panelling or the like, except
              where required to satisfy any privacy condition of this Decision Notice.
        Advertising Devices
        76.   Advertising devices must comply with the requirements of the Advertising
              Devices Code.
        77.   Construction signage, including that on hoardings, shade cloth and cranes but
              not including statutory safety signage, shall not exceed a total of 4m2 to each of
              the site’s street frontages.
        Fencing and Walls
        78.   Any street fencing must be setback an average of 1 metre from the front
              property boundary. Any fencing on the front boundary must either:
              a.   not exceed a maximum height of 1.2m
              b.   be of open construction.
        79.   The area of land between the fence and the front property boundary must be
              densely landscaped to screen any fencing from the street.
        Clothes Drying Areas
        80.   Each rooming unit must be provided with access to an outdoor clothes line
              which is screened from public view.
        Protection of Privacy
        81.   To ensure privacy is protected between adjoining properties, any window/s,
              deck or the like that overlooks or has the potential to overlook the private open
              space or habitable room windows of neighbouring properties must either:
              a.   have a minimum window sill height or 1.5 metres above floor level
              b.   be fitted with translucent glazing
              c.   be fitted with a fixed external screen




                                                                                  Page 9 of 13

Section 10

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                12 NOVEMBER 2018


        Communal Recreation Areas
        82.   Communal recreation area/s must be provided as shown on the approved
              plans.
        Amalgamation of Lots
        83.   Lot 164 on RP 94566 and Lot 163 on RP 897370 must be amalgamated prior to
              the commencement of use.
        ENVIRONMENTAL HEALTH
        Amenity
        84.   The development must be undertaken and operated in a manner that causes
              no detrimental effect upon the amenity of the neighbourhood by reason of the
              creation of excessive noise, lighting, air-borne hazards, atmospheric pollutants
              (including dust or odours) nuisance or any other emissions in accordance with
              the nuisance provisions of the Environmental Protection Act 1994.
        Noise Nuisance
        85.   Noise emission from mechanical equipment shall comply with the following
              requirements:
              a.   Air-conditioning and Refrigeration
                   i.     7am to 10pm: Maximum background + 5dB(A)
                   ii.    10pm to 7am: Maximum background + 3dB(A)
              b.   Pumps
                   i.     7am to 7pm: Maximum background + 5dB(A)
                   ii.    7pm to 10pm: Maximum background + 3dB(A)
                   iii.   10pm to 7am: No audible noise.
        86.   Submission of written certification from a suitably qualified person confirming
              that the noise levels from all mechanical equipment comply when measured at
              either the residential boundary or outside the most exposed part of an affected
              building, whichever is the closest to the equipment.
              The assessment and certification is required immediately after installation of the
              equipment and prior to any occupation of the building, and in a format approved
              by Council. All equipment should be operating at the same time to test the
              overall noise level created.
        87.   Entertainers or speakers used to amplify noise must not be located in any of the
              outdoor recreational areas.
        88.   Prior to the use of the building situated at 106 Pacific Avenue for the purpose of
              visitor accommodation noise barrier fencing must be erected in accordance with
              the approved Noise barrier plan.
        89.   Between the hours of 9pm to midnight the night manager must have the
              reception phone with them. From midnight the phone must be diverted to a
              security team response number.



                                                                                 Page 10 of 13

Section 11

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                12 NOVEMBER 2018


        90.   The courtyard of the manager’s unit situated at 106 Pacific Avenue must not be
              used between the hours of 9.00pm and 6.00am.
        91.   The pool and associated deck area must not be used between the hours of
              9.00pm and 7.00am.
        Outdoor Lighting Devices
        92.   Lighting associated with the use must be designed, sited, installed and tested to
              comply with Table 2.1 & 2.2 of Australian Standard AS4282-1997 “Control of
              the obtrusive effects of outdoor lighting” using a control level of 1.
        93.   Certification must be submitted to Council from a qualified person which
              certifies that all outdoor lighting devices comply with the requirements of this
              Decision Notice at the time of commissioning.
              For the purpose of certifying outdoor lighting devices for the development, a
              qualified person is:
              a.   Registered Professional Engineer of Queensland;
              b.   an environmental or electrical design consultant with a minimum of 3
                   years current experience in the field of outdoor lighting.
        WASTE
        94.   The developer must provide waste storage and disposal facilities in accordance
              with Planning Scheme Policy No. 9 "Waste Management Multi-Dwellings and
              Commercial and Industrial Premises". The facilities must include an external
              impervious area correctly sized for all refuse and recycling containers and
              suitably screened from public places and neighbouring properties. A bin wash
              area is required with a cold-water tap, hose and drain outlet connected to
              sewer, via a bucket trap. The drain outlet must be designed to prevent storm
              water entry to the sewerage system. This can be achieved with a nib wall
              50mm high and up to 700mm x 700mm wide (max 0.5m2) , or alternatively the
              waste area can be roofed, or any other design approved by Council.
        95.   Refuse containers must be provided in accordance with the requirements of the
              Environmental Protection (Interim Waste) Regulation 1996 and (Waste
              Management) Regulation 2000, for the storage and collection of refuse.
        96.   Bins must be provided throughout the site to reduce littering. All bins provided
              must be for refuse and recycling and be decanted into the bulk bins by the site
              operators.
        ENGINEERING
        Site Access and Driveways
        97.   A sealed access driveway must be provided from Pacific Avenue to all parking
              and manoeuvring areas of the development. The new works proposed to
              access No 106 must be undertaken in accordance with an Operational Works
              approval and must include in particular:
              a.   a driveway crossover generally in accordance with Council’s Standard
                   Drawings RS-051 and the associated addendum




                                                                                Page 11 of 13

Section 12

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                               12 NOVEMBER 2018


               b.   the works must match neatly with existing road and verge/footpath
                    features. Additional works beyond the driveway may be required to
                    provide an acceptable transition to existing road and verge/footpath
                    profiles
         Car Parking
         98.   A minimum of an additional 2 car parking spaces must be provided and marked
               on the site. The works must include dimensions, crossfalls and gradients in
               accordance with Australian Standard AS2890: Parking Facilities for the relevant
               user class
         99.   All car parking areas and access driveways must be maintained exclusively for
               vehicle parking and manoeuvring and kept in a tidy and safe condition at all
               times.
         100. Directional signage must be provided to direct visitors and customers to the car
              parking spaces provided on site.
         Pedestrian and Bicycle Facilities
         101. Pedestrian and bicycle facilities must be provided for the development. The
              works must be undertaken in accordance with an Operational Works approval
              and must include in particular the replacement of the existing bitumen sealed
              path in the frontage of No. 106 Pacific Avenue with a concrete path and must
              extend to the existing driveway in the frontage of 108 Pacific Avenue. The new
              path must be the same width as the existing path.
         Stormwater Drainage
         102. Stormwater runoff from the development must be connected to the existing
              stormwater drainage systems within the sites.
         Damage to Services and Assets
         103. Any damage caused to existing services and assets as a result of the
              development works must be repaired at no cost to the asset owner at the
              following times:
               a.   where the damage would cause a hazard to pedestrian or vehicle safety,
                    immediately; or
               b.   where otherwise, upon completion of the works associated with the
                    development.
         Any repair work which proposes to alter the alignment or level of existing services
         and assets must first be referred to the relevant service authority for approval.
    C.   Note the report is provided in accordance with Section 63(5) of the Planning Act
         2016.
                                                                                 Carried.




                                                                               Page 12 of 13

Section 13

 RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                                    12 NOVEMBER 2018


7                        FINANCIAL PERFORMANCE REPORT - OCTOBER 2018
DOCUMENT INFORM AT ION




                         Committee Recommendation
                         Moved:             Cr Stockwell
                         Seconded:          Cr Glasgow
                         That Council note the report by the Manager Financial Services to the General Committee
                         Meeting dated 12 November 2018 outlining October 2018 year to date financial
                         performance against budget.
                                                                                                         Carried.




8                        BUDGET REVIEW 2 (BR2) FOR THE 2018/19 FINANCIAL YEAR
DOCUMENT INFORM AT ION




                         Committee Recommendation
                         Moved:             Cr Glasgow
                         Seconded:          Cr Pardon
                         That Council note the report by the Manager Financial Services to the General Committee
                         Meeting dated 12 November 2018 and approve the proposed changes to the budget for the
                         2018/19 financial year as outlined in the Revised Budget Financial Statements attached to
                         the report.
                                                                                                          Carried.




                                                                                                   Page 13 of 13

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.