2 David Low Way - Attachment 6 - UXO Assessment - OPEC
Attached to the e-mail Reconfiguration of a Lot (1 lot into 6) - RAL17/0501.
OPEC - 2 David Low Highway, Castaways Beach
Rev 02 – AFU – 10 Aug 2017
REDUCTION OF RISKS - MITIGATIONS/CONTROLS
Due to the relatively high likelihood of dangerous EO/UXO existing on the Site, the full suite of
mitigations is recommended including the following:
Conduct EO/UXO awareness/education for personnel/contractors working at the Site,
selected Client management staff and possibly other key stakeholders as well as implement
a ‘chance UXO find’ protocol/SWP (preventative control and mitigating control). This is an
important control even if areas have been UXO-remediated for the following reasons:
o UXO search/remediation processes are rarely 100% effective – a performance target
of 99.7% is generally accepted within the EO/UXO industry. It is important that those
using remediated sites understand that ‘chance finds’ of occasional EO/UXO could still
occur and be observant during their work.
o EO/UXO awareness/education is also a key control used reduce ‘perceptions of risk’ by
dispelling common myths and misunderstandings regarding EO/UXO.
o A proper EO/UXO Safe Working Procedure (‘Chance Find Procedure’) aims to minimise
unsafe practices in the event that EO/UXO are encountered and reduce the likelihood
that encounters will escalate to more serious consequences.
Conduct visual detector-supported inspection of the entire development footprint to
identify any surface of very shallow-buried EO items.
Undertake 100% UXO investigation/remediation work of all areas where ground-intrusive
work is planned (areas previously subjected to ground intrusive work may be able to be
excluded depending on the nature of any such previous works).
Review insurances and proposed contract clauses to ensure that these adequately address
EO/UXO risks. As discussed previously, legal and contractual issues surrounding remnant
EO/UXO are unclear and largely untested.
Review risk assessment as new data from research and field work comes to hand. Ongoing
re-evaluation of risks is a key aspect of an effective risk management system.
MITIGATED RISK RATINGS
Assuming the recommended mitigations/controls are adopted, the mitigated risk ratings remaining
after risk treatment (residual risk) are as shown in Table 4 (below). In nearly all cases, residual risks
are significantly reduced and normally within ‘tolerable’ levels (i.e. ‘As Low As Reasonably
Practicable’/ALARP):
Table 4 - Mitigated Risk Ratings (Mitigations/Controls Applied)
Risk Ratings & Scores
Risk Event Consequence Type Controls Probability Consequence Risk Score &
Term Term Term
UXO survey
11
H&S Awareness Rare Catastrophic
High
SWP
Note: When using conventional 5x5 Risk Assessment Matrices, it is almost impossible to
Explosion reduce the overall risk rating for UXO-related H&S events into the ‘green’ zone – even if
the probability is rare or almost impossible. This does not mean that the residual risks are
not tolerable but rather illustrates the difficulties that can arise when using relatively
simplistic risk decision tools. Other more sophisticated risk modelling tools may
demonstrate that risks are extremely low (negligible) however there will usually be some
residual risk of a fatality/serious injuries even if full remediation of the Site is undertaken.
For use only in relation to the specified project
© 2017 Copyright BOZ Technical Services Pty Ltd Page 19 of 22