5179Flood Report_REVISION_2_7Feb2021
Callaghan & Toth
2.0 FLOOD IMMUNITY
The Year 2100 1%AEP flood levels across the north-east corner of the site have been abstracted from a
flood study undertaken by Brisbane Stormwater Management Pty Ltd for the adjoining Erindale
Development in 2014. The relevant flood levels are 100.34 m AHD across the eastern (upstream)
boundary of the site and 99.94 m AHD across the northern (downstream) boundary of the site. Those
Year 2100 1%AEP flood levels are marked on Figures 3.2 and 3.3 hereafter, together with the inferred
Year 2100 1%AEP flood boundary between those two levels.
The proposed lots are seen, in comparison to the 0.5 metre contours on Figure 3.3, to be at least a metre
above the flood profile and will therefore be immune to 100 year flooding, even with a 20% impost on the
design rainfalls for future climate change.
The proposed stormwater detention facilities are also seen on Figure 3.3 to be outside the Year 2100 1%
AEP flood boundary and will therefore have no impact on the storage-routing capacity of the floodway.
5
2035 2 Pearsons Road – Flood Study – Revision 2 Feburary 2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.