PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 12 JULY 2016
Stormwater Quality
22. The detail design for the development must incorporate appropriate measures, as
recommended and certified by an RPEQ, to limit stormwater runoff from the
development in 1 year ARI events to the predevelopment 1 year ARI event.
23. A stormwater quality treatment system must be provided to treat all stormwater runoff
from the development to achieve a 90% reduction in gross pollutants, 80% reduction
in Total Suspended Solids, 60% Reduction in Total Phosphorous and 45% reduction
in Total Nitrogen compared to if no stormwater quality treatment was provided.
24. The Stormwater Quality Treatment System provided to the development must be
certified by a RPEQ that it has been modelled and designed in accordance with the
Water Sensitive Urban Design Technical Design Guidelines (2006), Water By Design
Music Modelling Guidelines (2010) (or the Water By Design Deemed to Comply
Solutions where relevant). Any bioretention basins to achieve the outcome must be
designed in accordance with the Water By Design Bioretention Technical Design
Guidelines (2014). The works must be undertaken in accordance with an operational
works approval.
25. Any water quality treatment devices must become an educational landscape feature
of the development and include signage stating what the water quality treatment
device is, the pollutants it removes, and the waters it will protect.
26. All stormwater quality treatment devices must be maintained in accordance with the
Water by Design (2009) - Maintaining Vegetated Stormwater Assets (Version 1).
Records of all maintenance activities undertaken must be kept and made available to
Council upon request.
27. Any proposed Community Management Statement required for the development
must include the Water by Design (2009) – Maintaining Vegetated Stormwater Assets
(Version 1) document and must include the full cost of maintaining the system in
accordance with that document.
Landscaping Works
28. The development site must be landscaped. The works must be undertaken in
accordance with an Operational Works approval and the Noosa Plan for that specific
area and must include in particular:
a. the works shown on the approved Landscape Concept plan 01 Rufous Street
Master Plan – Community Building.
b. provision of koala food trees to the western portion of the site in accordance
with The Noosa Plan Landscape Code
c. sufficient space and growing media to accommodate an advanced local native
canopy tree for every 4 carparks in accordance with the Noosa Plan Landscape
Code
d. all landscaping must be in accordance with Planning Scheme Policy 3
Landscaping Plants and Guidelines and the Noosa Plan Landscape Code
e. all plant species must be suitable for the local area, consist mainly of local
native species and non-local native species must not be invasive species.
f. vegetated screening of any electrical transformers, bin storage areas and the
like from the road frontage
g. provision of 1 street tree within the road reserve for every 8 metres of road
frontage.
Page 23 of 185
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.