TODCONSULTING
Preliminary assessment indicates extremely weathered rock at approx 2-
3m below general excavation levels, which will significantly reduce risk
of slip, and provide massive horizontal restraint to retaining walls.
The loose surface sands are very prone to erosion and slippage,
particularly where vegetation is removed or stormwater becomes
concentrated.
3.4 Construction Management Plan
The site is located at the northern end of a sealed access driveway off
Seaview Tce, with no off-site parking and set down areas for construction
equipment. The size of vehicles accessing the site is limited by the width
and layout of the common driveway.
The Contractor will face various challenges on this project due to the
limited access, however it is clear that local Builders have had sufficient
experience with these types of sites cg, at the adjacent homes in Seaview
Tce; the recent construction of Pat Rafter's house at 48 Seaview Tce; and
current construction along Park Rd, Noosa.
We suggest that the site is sufficiently large to accommodate all
construction vehicles and equipment/materials storage, providing the
Contractor plans his work carefully, and builds staged temporary access
ramp/platforms similar to our layout on 09578-P4.
During the initial piling stage of the project there will he very few
subcontractors (Piling Contractor and part-time Surveyor) on site and
therefore "Stage I Temporary Access Area" of about 700m2 indicated on
Drawing 09578-P4 should be adequate for all access, parking and storage.
Total number of cars on site would be less than five.
Once the contiguous piling is completed, screw piling will be completed
over the site and again there would be few other Subcontractors involved
in the works that time. (Piling Contractor and Part-time Surveyor)
By this stage the Contractor should have extended his temporary
access/parking/storage platform across to the northern area of the building,
"Stage 2 Temporary Access Area" indicated on 09578 - P4, greatly
increasing parking, access and storage for materials. Total number of cars
on site would not exceed 10. During this time there would still only be
about 4-5 different subcontractors on site:-
• Concretor/formworker
• Reinforcing fixing
• Plumber (part-time)
• Surveyor (part-time)
By the time the builder is constructing the floor slabs, we would expect
the number of subcontractors will increase up to approximately 10
occasionally, but the accessible area for parking and storage will be
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2008/0169 Response to information request - 71 Seaview Tce Sunshine BeachRelated documentApplication case desk ↗
About this file
- File size
- 31.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.