                                              Officer:          Jack Lewis
                                              Direct Telephone: (07) 5449 5294
                                              Response Address: PO Box 141, Tewantin QLD 4565
                                              Email:            [email protected]
                                              Our Reference:    2007/2062
                                              Your Reference:
24 December 2008

Des Crawford
3 Coronet Street
PEREGIAN BEACH QLD 4573



Dear Sir

                                 Amended Decision Notice
                                    Integrated Planning Act 1997

You are advised that this Amended Decision Notice supersedes Council's Decision Notice of 17
December 2008 which has been found to contain errors in relation to Condition 36 and Advice
Condition 2.
Details of the decision are as follows:

1        APPLICATION DETAILS

    Application No:                  2007/2062
    Street address:                  31 Corsair Crescent, Sunrise Beach
    Real property description:       Lot 219 RP 135364
    Planning Scheme:                 The Noosa Plan
2        DECISION DETAILS

The following type of approval has been issued:
        Development Permit for Material Change of Use - Multiple Housing Type 2 - Duplex
3        RELEVANT PERIOD OF APPROVAL

The relevant period for this Development Approval is identified in the Assessment Manager
conditions.

4        ASSESSMENT MANAGER CONDITIONS

Land Use

1.       Development undertaken in accordance with this approval must generally comply with the
         approved plans of development. The approved plans are listed in the following table and may
         be amended by these conditions: -
          Plan         /     Rev.   Plan / Document Name                          Date
          Document No.
          6262 Sheet 1              Site Plan – Marcoola Design Group             20 April 2008


                                                                                         Page 1 of 11
Full text of the other 10 pages

Page 2

                                                                                        2007/2062



     6262 Sheet 2               Floor Plan – Level 1 – Marcoola Design      20 April 2008
                                Group
     6262 Sheet 3               Floor Plan – Level 2 – Marcoola Design      20 April 2008
                                Group
     6262 Sheet 4               Floor Plan – Level 3 – Marcoola Design      20 April 2008
                                Group
     6262 Sheet 5               Elevation B – Marcoola Design Group         20 April 2008
     6262 Sheet 6               Elevation C & Elevation D – Marcoola        20 April 2008
                                Design Group
     SC-1705 A01                Site Drainage Layout         –    Empire    November 2008
                                Consulting Engineers

2.   The development must be undertaken and operated in a manner that causes no detrimental
     effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
     lighting nuisance or other emissions.
3.   The open space and setback areas are to be landscaped in accordance with Council’s Policy
     on Landscaping Guidelines and a properly prepared landscape plan. Such landscaping is to
     be completed prior to the premises being occupied and maintained at all times thereafter and
     shall include:-
     3.1    Native screening vegetation shall be provided between buildings as well as along the
            side and rear boundaries to protect the amenity of neighbouring residents.
     3.2    A minimum of 1 x 45 litre street tree shall be established on the frontage within the
            road reserve.
     3.3    A minimum of 1 x 100 litre tree shall be established on the frontage within the property.
     3.4    Remove the plant species erigeron karvinskianus from the proposed landscape plans
            and replace with a recommended plant species that is consistent with Planning
            Scheme Policy 3 – Landscape Plants & Guidelines.
     3.5    All plantings located within and at the edges of the soakage pit are to assist in the
            uptake of additional water and nutrients. Recommended plantings include;
            SHRUBS
             Code       Botanical Name                   Common Name           Size      No.

             Bae vir    Baeckea virgata                  Twiggy myrtle         140mm
             Cal pac    Callistemon pachyphyllus         bottlebrush           140mm
             Lep pol    Leptospermum polygalifolium      Wild may              140mm
             Mel nod    Melaleuca nodosa                                       140mm
             Pul myr    Pultenaea myrtoides                                    140mm

            GROUND COVERS AND TUFTING PLANTS

             Code       Botanical Name        Common Name        Size    No.

             Car app    Carex appressa                           GT      @ 300mm c
             Iso nod    Isolepsis nodosa                         GT      @ 300mm c
             Jun usi    Juncus usistatus                         GT      @ 300mm c
             Lom lon    Lomandra longifolia                      GT      @ 500mm c
             The tri    Themeda triandra                         GT      @ 300mm c

                                                                                      Page 2 of 11

Page 3

                                                                                        2007/2062



4.    All fencing shall be setback at least 1 metre from the front property boundary, with at least half
      of the fencing setback 2 metres. The area of land between the fence and the front property
      boundary shall be densely landscaped to screen any fencing from the street.
5.    Fencing along the rear boundary shall not exceed 2.0m above natural ground level.
6.    The development shall not exceed 8 metres above natural ground level and finished ground
      level.
7.    A verification survey of the building is to be carried out by a Licensed Surveyor and a
      certificate lodged with Council at completion of work confirming compliance with the maximum
      allowable building height as required by either the conditions of approval or the Planning
      Scheme.
8.    Any deck or balcony areas are not to be enclosed with shutters, glass panelling or the like,
      thus remaining as open structures.
9.    Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be
      submitted, to secure performance of all conditions of this approval, prior to the issue of a
      Development Permit for Operational Works. The cash bond or trading bank guarantee will be
      returned on performance of the conditions of approval less any costs incurred by Council in
      respect of enforcing performance of this permit.
10.   The requirements of this development approval are to be effected, prior to the use of the
      premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
      this approval to effect compliance with conditions.
11.   The Development Permit for a material change of use of premises lapses if the use has not
      happened by 16 December 2012, unless an application to extend the relevant period is
      approved by Council.
Land Development
Vehicle Access
12.   A vehicular access driveway to serve the development shall be constructed from the Corsair
      Crescent Street frontage of the site with a maximum width of 5.5m.
13.   The vehicular access driveway shall be constructed generally in accordance with drawing
      number 6262 Sheet 3 drawn by Marcoola Design Group dated 20/4/2008, except as modified
      herein.
14.   The driveway shall be designed and constructed to Council’s design standards and to grades
      that prevent vehicles from scraping and/or bottoming whilst also allowing pedestrians
      movements along the footpath without any step or level difference. Should any driveways be
      constructed to grades that do not comply with AS/NZS 2890.1-2004, Council will require that
      the driveway be removed and reconstructed to levels that do comply.
      Please note, a step between the driveway and the footpath shall be avoided, as it is preferred
      to have the footpath continue at a constant grade to minimise the potential for pedestrians to
      trip or fall.
15.   To ensure pedestrian safety between vehicles exiting the site and pedestrians on the footpath,
      the driveway and any associated fencing or vegetation near the driveway shall comply with the
      minimum sight line requirements as defined in AS 2890.1, section 3.2.4. The applicant shall
      demonstrate compliance by illustrating these sight lines on the plans submitted for both
      Operational Works approval and Building Works approval.
16.   All vehicles shall enter and leave the site in a forward direction.
Car Parking
17.   Carparking shall be provided within the site as shown on with drawing number 6262 Sheet 3
      drawn by Marcoola Design Group dated 20/4/2008, except as modified herein.
                                                                                      Page 3 of 11

Page 4

                                                                                      2007/2062



18.   A minimum of 4 covered carpark spaces shall be provided on site.
19.   The carparking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004
      for user class 1A with allowance for vehicles to enter and leave the site in a forward gear and
      with a minimum head clearance (headroom) at any point of 2.2m.
20.   All carparking shall be kept and maintained in a condition fit for use.
21.   A sign shall also be provided to indicate that the proposed turning area is a “Turning Area
      Only” and that “No Parking is Permitted”.
Frontage Works
22.   Footpath improvements such as topsoiling, grassing, and tree planting are required to the
      Corsair Crescent Street frontage of the site in accordance with Planning Scheme Policy
      PSP03 Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.
23.   A new 1.5m wide concrete path shall be constructed along the Corsair Street frontage of the
      site in accordance with Council’s design standards and to an alignment that protects any
      significant vegetation or any underground services.
24.   All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel
      and landscaping such as trees and grasses in accordance with Council’s Standard
      specifications prior to commencement of the use permitted by this permit.
Roof Water & Stormwater Drainage
25.   Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank that
      is installed to ensure water from the rainwater storage system or tank is used for external uses
      (such as watering gardens, irrigation, ornamental ponds, water features, topping-up swimming
      pools, outdoor cleaning, etc) and for internal (ground floor) use in washing machine cold taps
      and toilet cisterns. All rainwater tanks are to be designed and installed in accordance with the
      Queensland Development Code (QDC) current at the time of building approval, and shall be
      part of the plumbing application for approval. The location and capacity of the tanks shall be
      clearly shown on the plans submitted for Building Works and Operational Works approval and
      any overflow shall be directed to the road frontage in Corsair Crescent or the stormwater
      drainage system located at the rear of the site or an onsite infiltration system.
26.   All stormwater drainage (including roof water overflow from the rainwater storage system)
      shall be collected and discharged so there is no net increase in stormwater runoff from the
      site. Stormwater drainage permitted to drain from the site shall be discharged to:
      26.1    Council’s existing drainage structure at the rear of the site. Or
      26.2    Council’s kerb & channel street drainage system in Corsair Crescent. Or
      26.3    An onsite infiltration system.
      Construction of drainage infrastructure shall generally be in accordance with drawing number
      SC-1705 A01 drawn by Empire Engineering dated November 2008. The infiltration system
      shall be wholly contained within the site and surface discharge shall not cause scour or
      damage to adjoining properties or adversely affect Council’s sewer main.
      Plans of the drainage design shall be prepared by a Registered Professional Civil Engineer
      and submitted to Council prior to obtaining a Development Permit for Operational Works. The
      maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
      drainage system at any one location is 25 litres/second.
      A Development Permit for Building Works shall not be granted until a Development Permit for
      Operational Works has been issued in regard to the drainage scheme.
27.   All site stormwater drainage shall be by means of a gravity system.


                                                                                    Page 4 of 11

Page 5

                                                                                       2007/2062



Sewer Mains
28.   The site shall be connected to Council’s existing sewerage reticulation systems and be
      constructed in accordance with Council’s standards and requirements at no cost to Council.
29.   The existing sewer main that is located in the adjoining property at the rear of the site and the
      ‘zone of influence’ (taken as the area within a 45-degree angle measured from the invert of the
      sewer main to the finished surface level) shall be accurately located and determined by a
      licensed Surveyor and shown on all plans submitted for Operational Works approval.
Town Water Supply
30.   The site shall be connected to Council’s existing town water supply and be constructed in
      accordance with Council’s standards and requirements at no cost to Council.
31.   Each individual water connection to the water reticulation system shall extend to the property
      boundary and be metered. All fees for the supply of water meters shall be paid to the Council.
32.   All water meters must be located outside the property boundary and in an easily assessable
      location to facilitate unhindered reading by Council and/or Council’s contracted water meter
      readers, and not behind fences or locked gates. In this regard approval of the water meter
      configuration and location must be obtained from Council’s Water & Sewerage Capital Works
      Manager prior to lodgement and approval of hydraulic drawings.
33.   The development shall be served by a single Body Corporate water meter to measure the total
      water consumption (including fire hose reels, but excluding fire hydrants and fire sprinkler
      systems), and individual water meters to each tenement capable of being separately rated.
Site Stability
34.   A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
      determine the soil classification, establish whether any measures are required to protect the
      stability of adjoining buildings and/or structures and/or land, and make recommendations on
      the type of foundation system(s) best suited for the proposed development. The
      recommendations of this report shall be incorporated into the design and construction of the
      proposed development.
Erosion and Sediment Control
35.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to
      be submitted to the Council for approval prior to obtaining a Development Permit for
      Operational Works.
Contributions Towards Council Infrastructure
36.   Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
      upgrading various infrastructure at the rates applicable at the time of payment. An estimate
      only of the contribution amounts under the current Council policies and requirements is
      outlined in the table below:

       Contribution Required For:                                                     Amount:
       PSP12 – Public Open Space Contributions (Park)                                 $3,171

       PSP16 – Sewerage Headworks Contributions                                       $1,907

       PSP17 – Water Supply Headworks Contributions                                   $4,492

       PSP20 – Pathway Trunk Network Contributions                                    $1,425


                                                                                     Page 5 of 11

Page 6

                                                                                       2007/2062




        TOTAL Contribution Amount =                                                   $10,995
        Please note, that these amounts are all subject to variations in the Consumer Price Index, All
        Groups Brisbane from September 2008 until the date of payment.

       All contributions must be paid prior to the issue of a Development Permit for Operational
       Works.
       Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
       contributions not be paid at the due time, Council shall call upon the trading bank guarantee in
       full.

       Processing of bonds for security where specific Council approval has been given for the
       bonding of contributions will incur an administration fee in accordance with Council’s Land
       Development Commercial & Regulatory Fees at the time of lodgement.
       In the event that the Development Permit for Material Change of Use of Premises lapses or is
       cancelled, the paid contributions and will be returned.
General
37.    Any damage caused to any public utility during the course of construction shall be repaired to
       Council’s standards and at no cost to Council.
38.    Any alteration of any public utility or other facilities necessitated by the development of the
       land or associated construction works external to the site shall be at no cost to Council.
39.    The transportation of all materials to and from the site shall be undertaken in a manner such
       that no particle matter escapes onto a public road. All vehicles carrying materials either to or
       from the site shall be covered to prevent materials including dust being windblown from the
       vehicle.
       Approval of works shall not be granted until all As Constructed information has been supplied
       and accepted by Council.
Building Services
40.    The development must be undertaken and operated in a manner that causes no detrimental
       effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
       lighting nuisance or other emissions.

5      REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:

 Referral Trigger            Referral Status     Referral Agency        Referral Address

 Nil

6      APPROVED PLANS/DOCUMENTS

The approved plans and / or documents for this development approval are listed in the following
table:
 Plan / Document No.       Rev.    Plan / Document Name                       Date
 6262 Sheet 1                      Site Plan – Marcoola Design Group          20 April 2008
 6262 Sheet 2                      Floor Plan – Level 1 – Marcoola Design     20 April 2008
                                   Group



                                                                                     Page 6 of 11

Page 7

                                                                                      2007/2062



 6262 Sheet 3                    Floor Plan – Level 2 – Marcoola Design     20 April 2008
                                 Group
 6262 Sheet 4                    Floor Plan – Level 3 – Marcoola Design     20 April 2008
                                 Group
 6262 Sheet 5                    Elevation B – Marcoola Design Group        20 April 2008
 6262 Sheet 6                    Elevation C & Elevation D – Marcoola       20 April 2008
                                 Design Group
 SC-1705 A01                     Site Drainage Layout         –    Empire   November 2008
                                 Consulting Engineers

7    ADVISORY NOTES

The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1.   The applicant is advised that development contributions and infrastructure charges applicable
     to this development approval have been based on the following Uses Class/ Uses and
     applicable quantities:-

                 Existing Development                             Approved Development
       Existing Use Class                             Approved Use Class
                               Existing Quantity                                 Approved Quantity
              / Use                                         / Use
                                                      Multiple Housing -
      Detached House          Vacant Land                                        2 x 3 Bedroom Units
                                                      Type 2 – Duplex

2.   The applicant is informed that approval of this development application will trigger an
     Infrastructure Charge in accordance with the Coastal Major Road Network Infrastructure
     Charges Plan for the estimated amount of $4,051 and is subject to variations in the Consumer
     Price Index, All Groups Brisbane from September 2008 until the date of payment. An
     Infrastructure Charge Notice will be issued in accordance with Chapter 5 of the Integrated
     Planning Act 1997.
3.   The applicant is informed that payment via credit card transaction will not be an acceptable
     method of payment for development contributions conditioned in this permit or for
     infrastructure charge notices issued separately.
4.   The applicant is advised that a Compliance Permit for all plumbing and drainage works within
     the boundaries of the development site must be obtained from Council’s Plumbing Services
     Section prior to obtaining a Development Permit for Building Works.
5.   Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
     the cost of operational works exceeds $80,000, then a portable long service leave levy is
     required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
     the approved form issued by the Building and Construction Industry (Portable Long Service
     Leave) Authority that confirms that the requirements of the Act have been satisfied. A statutory
     declaration outlining the cost of the operational works must be submitted to Council with the
     lodgement of any application for operational works over the site.
6.   The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
     Local Law No. 12, prevents a builder or building contractor carrying out building work on a
     building site in a way that makes or causes audible noise to be made from the building work:-
     6.1    On a Sunday or public holiday, at any time; or
     6.2    On a Saturday or a business day, before 7.00am or after 6.30pm.
     A maximum penalty of $1,500 applies to an offence under this legislation.
                                                                                    Page 7 of 11

Page 8

                                                                                         2007/2062



Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8     PROPERTY NOTES
Not applicable

9     PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable

10    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required           Subject of the required Development Permit
 Development Permit for Building Works         All Building Works

 Development     Permit    for   Operational   Access and/or Carparking, Stormwater Drainage,
 Works                                         Frontage Works, Erosion & Sediment Control &
                                               Landscaping

11    SELF ASSESSABLE CODES
The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Advertising Devices Code

12    SUBMISSIONS
Not applicable

13    REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable

14    RIGHTS OF APPEAL

You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.
During the appeal period, you as the applicant may make written representations to Council about
the conditions contained within the development approval. If Council agrees or part agrees with the
representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice”
may be given. Taking this step will defer your appeal period, which will continue after Council makes
its decision. (Refer to sections 3.5.17 and 3.5.18 of the Integrated Planning Act 1997).



                                                                                      Page 8 of 11

Page 9

                                                                                    2007/2062



15     OTHER DETAILS
Please note that an Infrastructure Charge in accordance with the Coastal Major Road Network
Infrastructure Charges Plan has been triggered by the approval of this development application. An
Infrastructure Charge Notice is attached in compliance with Chapter 5 of the Integrated Planning Act
1997.
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.

Yours faithfully,




Denis Wallace
PLANNING OFFICER




                                                                                  Page 9 of 11

Page 10

                                                                                                      2007/2062



                                                        Appeal Rights
                                                    INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




The following is an extract from the Integrated
                                                                    (6) If an application involves assessment against a
Planning Act (Chapter 4).                                      concurrence agency code, appeal rights for submitters
Division 8 - Appeals to court relating to                      for the application are not available against the part of
development applications                                       the approval that represents the concurrence agency’s
                                                               response for the code.
Appeals by applicants
                                                               Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application
may appeal to the court against any of the following-          4.1.29.(1) An advice agency may, within the limits of
                                                               its jurisdiction, appeal to the court about the giving of a
(a) the refusal, or the refusal in part, of a development      development approval for a development application
      application;                                             if-
(b) a matter stated in a development approval,                 (a) the development application involves impact
      including any condition applying to the                      assessment; and
      development, and the identification of a code
      under section 3.1.6;1                                    (b) the advice agency told the applicant and the
                                                                   assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a             application as a submission for an appeal.
      development permit was applied for;
                                                                  (2) The appeal must be started within 20 business
(d) the length of a relevant period;                           days after the day the decision notice or negotiated
(e) a deemed refusal.                                          decision notice is given to the advice agency as a
    (2) An appeal under subsection (1)(a) to (d) must          submitter.
be started within 20 business days (the “applicant’s           Appeals for matters arising after approval given
appeal period”) after the day the decision notice or           (co-respondents)
negotiated decision notice is given to the applicant.          4.1.30.(1) For a development approval given for a
    (3) An appeal under subsection (1)(e) may be               development application, a person to whom any of the
started at any time after the last day a decision on the       following notices have been given may appeal to the
matter should have been made.                                  court against the decision in the notice-
Appeals by submitters                                          (a) a notice giving a decision on a request for
4.1.28.(1) A submitter for a development application               extension of the relevant period for an approval;
may appeal to the court about-                                 (b) a notice giving a decision on a request to make a
(a) the giving of a development approval, including                minor change to an approval.
      any conditions (or lack of conditions) or other              (2) The appeal must be started within 20 business
      provisions of the approval; or                           days after the day the notice of the decision is given to
(b) the length of a relevant period for the approval.          the person.
    (2) The appeal must be started within 20 business                (3) Subsection (1)(a) does not apply if the
days (the “submitters appeal period”) after the day            approval resulted from a development application
the decision notice or negotiated decision notice is           (superseded planning scheme) that was assessed as
given to the submitter.                                        if it were an application under a superseded planning
                                                               scheme.
    (3) If a person withdraws a submission before the
application is decided, the person may not appeal the             (4) Also, a person who has made a request
decision.                                                      mentioned in subsection (1) may appeal to the court
                                                               against a deemed refusal of the request.
    (4) If an application involves both impact
assessment and code assessment, appeal rights for                 (5) An appeal under subsection (4) may be started
submitters are available only for the part of the              at any time after the last day the decision on the
application involving impact assessment.                       matter should have been made.
    (5) If an application is processed under section           Division 9 - Appeals to court about other matters
6.1.28(2), appeal rights for submitters for the                Appeals for matters arising after approval given
application are available only for the aspects of the          (no co-respondents)
development that would have required public
notification under the repealed Act.                           4.1.31.(1) A person to whom any of the following
                                                               notices have been given may appeal to the court
                                                               against the decision in the notice-
                                                               (a) a notice giving a decision on a request to change
                                                                   or cancel a condition of a development approval.
1
     Section 3.1.6 (Preliminary approval may override
    local planning instrument)
                                                                                                  Page 10 of 11

Page 11

                                                                                                   2007/2062

(b) a notice under section 6.1.442 giving a decision to     (d) the length of a period mentioned in section 3.5.21
    change or cancel a condition of a development                 relevant period;
    approval.                                               (e) a deemed refusal.
    (2) The appeal must be started within 20                    (2) An appeal under subsection (1)(a) to (d) must
business days after the day the notice of the decision      be started within 20 business days (the “applicant’s
is given to the person.                                     appeal period”) after the day the decision notice or
   (3) Also, a person who has made a request                negotiated decision notice is given to the applicant.
mentioned in subsection (1)(a) may appeal to the                (3) An appeal under subsection (1)(e) may be
court against a deemed refusal of the request.              started at any time after the last day a decision on the
    (4) An appeal under subsection (3) may be               matter should have been made.
started at any time after the last day the decision on      The Registrar for the Building and Development
the matter should have been made.                           Tribunal may be contacted at the website
Appeals against decisions to change approval                http://www.localgovernment.qld.gov.au/
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a
                                                            For Infrastructure Charges Only
decision made on an application to change the               4.1.36 Appeals about particular infrastructure
conditions attached to an approval given under              charges
section 2.19(3)or section 4.4 of the repealed Act may       (1) This section applies to a person who has been
appeal to the court against-                                given, and is dissatisfied with, an infrastructure
(a) the decision; or                                        charges notice or a regulated State infrastructure
(b) a deemed refusal of the application.                    charges notice.
    (2) An appeal under subsection (1)(a) must be           (2) The person may appeal to the court against the
started within 20 business days after the day notice of     notice.
the decision is to be given to the person.                  (3) The appeal must be started within 20 business
    (3) An appeal under subsection (1)(b) may be            days after-
started at any time after the last day a decision on the    (a) if the notice is given because of a development
matter should have been made.                                    approval or master plan approval-the day the
Appeals against local laws                                       applicant is given notice of the decision about the
                                                                 approval; or
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions            (b)    otherwise-the day the notice is given to the
applied under a local law about the use of premises or             person.
the erection of a building or other structure permitted     (4) An appeal under this section may only be about-
by the planning scheme may appeal to the court              (a) whether a charge in the notice is so
against the decision or the conditions applied.                  unreasonable that no reasonable relevant local
    (2) The appeal must be started within 20 business            government, State infrastructure provider or
days after the day notice of the decision is given to the        coordinating agency could have imposed it; or
applicant.                                                  (b) an error in the calculation of the charge.
For Building Works Only                                     (5) To remove any doubt, it is declared that an
Rights of appeal conferred by Section 4.2.9 of the          appeal under this section can not be about the
Integrated Planning Act 1997 as follows:                    methodology used to establish the charge in the
                                                            relevant infrastructure charges schedule or regulated
Division 3 – Appeals to tribunals relating to
                                                            State infrastructure charges schedule.
development applications
Appeals by applicants
4.2.9(1) An applicant for a development application
may appeal to the Building and Development Tribunal
against any of the following-
(a) the refusal, or the refusal in part, of a development
    application;
(b) a matter stated in a development approval,
    including any condition applying to the
    development, and the identification of a code
    under section 3.1.6;3
(c) the decision to give a preliminary approval when a
    development permit was applied for;


2
   Section 6.1.44 (Conditions may be changed or
  cancelled by assessment manager or concurrence
  agency in certain circumstances)
3
   Section 3.1.6 (Preliminary approval may override
  local planning instrument)
                                                                                               Page 11 of 11

Used in these records

About this file

File size
73 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Amended Decision Notice - 010.2007.00002062.001 [As Published].pdf · 73 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.