safely located and freely accessible with an onsite water volume of not
water supply is provided for fire less than 5,000 litres; and
fighting purposes, which is in 2.​           a water supply outlet pipe
addition to day to day water supply. 50 millimetres in diameter and
                                    fitted with a standard fire brigade
                                    fitting connected to the water
                                    supply (other than where the water
                                    supply is in a swimming pool or
                                    dam).

                                    Editor’s Note — Water supply capacity for
                                    firefighting purposes is in addition to water
                                    supply capacity for household use.

Flood Hazards                      AO16.1 Where the development is Not applicable - the site is not
PO16 Development is designed located in the Flood Hazard Area as mapped in the Flood Hazard
and sited to ensure risk to people shown on Flood Hazard Overlay Area.
and property from flooding is Map in Schedule 2, the finished
avoided or minimised.              floor level of habitable rooms is at
                                   least 300 millimetres above the
                                   Defined flood event (DFE).


                                    OR


                                    AO16.2 Where the DFE has not Not applicable - the site is not
                                    been modelled for the area, the mapped in the Flood Hazard
                                    finished floor level of habitable Area.
                                    rooms is at least 500 millimetres
                                    above the highest recorded flood.


                                    Editor's Note—The QDC mandatory
                                    provisions MP3.5 also apply to the
                                    construction of buildings in flood
                                    hazard areas.

PO17 Underground car parking No acceptable outcome provided.                        Not applicable - not proposed.
areas are designed to drain and
function safely during a flood event
and power failure.


Editor's note—Basements should
have flood immunity above the
1%AEP defined flood event with
alternative means to mechanical
pumping used to achieve such
immunity.

Major Electricity Infrastructure AO18.1 Development including any Not applicable - the site is not
& Substations                    sensitive land uses is at least:   mapped as containing major
PO18 Development is sufficiently 1.​      50     metres      from a electricity infrastructure or



                                                                                                               20
Log in to download the original file

Town Planning Assessment Report.pdf · 8.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.