Mitti St, Noosa Heads                                                                SLR Ref: SLR Memo 23 09 19.docx
Hydraulic Investigation                                                                      Date: 23 September 2019
Channel Widening Option




Figure 3     Peak Flood Hazard – 1% AEP Flood Event




The results of the analysis, as shown in the Figures above, are as follows:
     •     The peak flood depths beyond the channel are less than 500 mm.
     •     The impacts of the proposed works are less than 20 mm external to the subject site.
     •     The peak flood hazard beyond the channel; is less than 0.4 m²/s.




                                                      Page 4

Used in these records

About this file

File size
3.1 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 4 - Option 1 Hydraulic Advice.pdf · 3.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.