SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 12 FEBRUARY 2019
Page 111 of 130
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 12 FEBRUARY 2019
OPERATIONAL PLAN 2018-19 PROGRESS REPORT
THE NOOSA COMMUNITY
No. Project Responsibility Update Status
1 Adoption of Cultural Plan and development of a 2019 Director Community Services Final Draft of Cultural Plan and 2019 Action Plan approved and adopted in Completed o
Action Plan December 2018.
2 Adoption of Community Health and Wellbeing Plan and Director Community Services Community consultation plan being developed for consultation in early 2019. On track Qo
development of a 2019/20 Action Plan
3 Begin construction of an iconic playground at Cooroy Infrastructure Planning, Design and Detailed design is nearing completion. Procurement stage commencing. On track Qo
following community consultation Delivery Manager
4 Complete Noosaville Library refurbishment Libraries & Galleries Manager Library staff and collection relocated. Devolution of temporary locations Completed Qo
completed. Noosaville Library re-opened on 26 November 2018.
5 Implementation of Sport and Active Recreation 2018/19 Director Community Services Implementation Plan to be reported on every 3 years of operation — review not On track Gg
Action Plan required until 2021.
6 Complete construction of Park Road Boardwalk Project Infrastructure Planning, Design and Construction is complete. The Project has now transitioned to maintenance Completed @
Delivery Manager phase. Capital Works Executive to consider the future of the temporary path
in the new year.
Page 111 of 130See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.