07/2431 - Operational Works - Landscaping [As Published]
INTEGRATED PLANNING ACT 1997 Part A, Version 3.0, 3 September 2007
11. Does the application involve land other than State-owned {and (i.e. privately owned land) and require owner's consent?
[2] No
[J Yes - Complete Table K and submit, with the application, written documentation of all owner's consent
Mandatory attachments and supporting information
42, What are the other parts of IDAS Application Form 1 submitted with this application, and the other mandatory attachments and
supporting information accompanying this application, not identified in those other form parts?
(eg, Pov off 1 omers. consent eee of (eg. Gener! halt ee Sheetal Date weeccment manor
resource allocation/entitlement, plans, drawings, reports} Report)
1 Part E 26-Nov-2007 | mail
2 Checklist 26-Nov-2007 | mail
3 Landscape Plan - LGGG850 LA01 rev C 26-Nov-2007 | mail
4 Landscape Plan - LGGG850 LA02 rev B 26-Nov-2007 | mail
5 Landscape Details - LGGG850 LA03 rev B 26-Nov-2007 | mail
@ Portable Long Service Leave (PLSL) levy for building and construction work
13. ls payment of a Portable Long Service Leave (PLSL) levy required for building and construction work before a development permit for
the application can be given?
[2] No
(7 Yes
13(a). Indicate the reason PLSL is not applicable
(1 The apptication is not for building and construction work under the Building and Construction Industry (Portable Long
Service Leave) Act 1991, section 3AA (e.g. the application is only for a change of use or for the following types of work carried
out solely for farming purposes: land clearing, site preparation, earthworks, fences, fodder harvesting, clearing of encroaching
vegetation, clearing of regrowth, thinning vegetation or controlling weeds or pests); or
[2] Allcosts, that relate to the work both directly and indirectly, are less than $80,000, inclusive of GST; or
(The work is being carried out under an owner-builder permit issued under the Queensland Building Services Authority
Act 1991- Complete and submit a QLeave Notification and Payment Form (no payment required if owner-builder permit number
stated). The receipted form must be sighted by the assessment manager before a development permit can be given
@ oFrice use onty
L
Date Received 2rfu Jor Reference Numbers | o7/ 273 j
FOR COMPLETION BY ASSESSMENT MANAGER
Is a QLeave Notification and Payment Form required for this application?
LJ No
L] Yes - Complete Table M
NOTIFICATION OF ENGAGEMENT OF PRIVATE CERTIFIER
To Council
| have been engaged as the private certifier for the building work referred to in this application
Oate of
Accreditation number Name BSA Certification number Building classification
engagement
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (07_2431 - Operational Works - Landscaping [As Published].pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.