ORDINARY MEETING MINUTES 17 DECEMBER 2020
62. Operating stormwater harvesting tanks must be provided for the development. The
tanks must be provided in accordance with approved plans and must include
capacity, catchment, distribution and reuse as detailed in Section 4.2.2 and Section
5 of the approved Stormwater Quality Management Plan version 0, prepared by
Callahan and Toth and dated August 2019.
Construction Management Plan
63. A preliminary Construction Management Plan must be submitted with the
Operational Works application and must address the following:
a. traffic management during all aspects of the construction phase including:
i. a Traffic Management Control Plan in accordance with the Manual of
Uniform Traffic Control Devices (MUTCD) detailing all temporary
signage and traffic control measures prior to construction;
ii. maintenance of safe pedestrian access for the areas affected by the
works during and after daily construction has ceased;
iii. proposed fencing to the site during the construction phase of the
development;
iv. approval of the Traffic Management Control Plan by the Department of
Transport and Main Roads (DTMR) for any works on State controlled
roads; and
v. provision for worker car parking.
b. maintenance and protection of water quality and existing drainage lines
through the construction site, through the implementation of appropriate
erosion and sediment control measures.
c. works programme identifying key components of the works and their
respective durations.
d. establishment of a communication protocol with the general public, adjoining
owners, emergency services and local businesses to advise of agreed
construction times, impacts on traffic, services and other relevant issues.
e. a post out to the local residents and businesses prior to the pre-start meeting
advising of the site contact details and the potential for off-site impacts during
the developments construction. The post out must:
i. include a copy of the architectural approved plans;
ii. include plans that show any changes to the road network;
iii. be distributed to all businesses and residences in the area bounded
by:
Opal Street;
Kauri Street;
Elm Street; and
Pearl Street.
Written confirmation of the post out must be submitted to Council a
minimum of 5 days prior to the pre-start meeting.
f. identification of complaint management procedures including:
i. contact details for the on-site manager;
ii. dispute resolution procedures.
Page 19 of 25