Council archive · source document
Decision Letter - Change to an Existing Approval [As Published] · 132005.390.02
Officer: Jack Lewis
Direct Telephone: (07) 5449 5183
Response Address: Locked Bag 72
Sunshine Coast Mail Centre QLD 4560
Email: [email protected]
Our Reference: 2005/390
1 April 2010
Vasterby Pty Ltd
PO Box 1349
NOOSA HEADS QLD 4567
Dear Sir or Madam
Change to an Existing Approval
Sustainable Planning Act 2009
I refer to your request to make a change to an existing approval. On 29 March 2010 Council decided
your requested changes.
Details of the decision with the consolidated conditions are as follows:
1 APPLICATION DETAILS
Application No: 2005/390
Street address: 22 Hill Street, Sunshine Beach
Real property description: Lot 491 RP 48112
Planning Scheme: The Noosa Plan
2 DECISION DETAILS
Council on 19 May 2006 decided to issue the following type of approval:-
Development Permit for Material Change of Use – Duplex dwelling
In relation to your request to extend the relevant period for the above development approval, Council
on 29 March 2010 decided to:
A. Agree to extend the Relevant Period.
B. Approve to change condition 19.
C. Issue a Change to an Existing Approval.
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
Page 1 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 15 pages
Page 2
2005/390
4 ASSESSMENT MANAGER CONDITIONS
Land Use
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are numbered V.05 DA.01 D, DA.02 D,
DA.03 C, DA.04 C, DA.05 C, DA.06 C, DA.07 C, DA.08 C, DA.09 C, DA.10 D, DA.11 D, DA.12
D, and DA.13 C prepared by Bark Design Architects and dated March 2006 and as may be
amended by these conditions.
2. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
3. The open space and setback areas are to be landscaped in accordance with Council’s Policy
on Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably
qualified Landscape Architect or Horticulturalist. Such landscaping is to be completed prior to
the premises being occupied and maintained at all times thereafter and shall include:-
3.1. The provision of screening vegetation to reach a height of over 3 metres within the
planting beds adjacent to both swimming pools;
3.2. The provision of 1 x 100 Litre native canopy species within the rear of the property to
replace the Fig species removed.
3.3. The provision of 45 Litre screening species along the side and rear property boundaries
where they have been dedicated for soft landscaping purposes.
4. Amended plans shall be submitted prior to the issuing of the Operational Works Development
Permit detailing the provision of 20% soft landscaping in accordance with The Noosa Plan. In
this regard no soft landscaping shall be located directly over the basement carpark, and
therefore the terrace areas located either at the front and rear of the property will be required
to be reduced in size.
5. All fencing shall be setback at least 1 metre from the front property boundary, with at least half
of the fencing setback 2 metres. The area of land between the fence and the front property
boundary shall be densely landscaped to screen any fencing from the street and shall include
the provision of 3 x 100 Litre species located to the east of the driveway and 1 x 100 Litre
species located to the west of the driveway. These species are to be in accordance with the
existing plantings within Pat Mullins Park.
6. The front fencing shall incorporate a mixture of materials including timber battening.
7. All fencing shall not exceed a height of 2 metres as measured from natural ground level. In
this regard the side fencing located adjacent to the Drying Areas of both units shall be reduced
in height.
8. Existing trees within road reserve and Pat Mullins Park are to be retained. The submitted
landscape plans shall detail the proposed methods of protection for this vegetation.
9. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
10. Mechanical plant and equipment including air-conditioning units are:-
10.1. where located at ground level, screened by fencing 1.5 metres in height or by dense
vegetation of at least 1.5 metres in width incorporating grouped trees and shrubs; or
10.2. visually integrated into the line and plane of the building and roof design and do not
project beyond the height or width of the building when viewed from the street and
adjoining properties.
Page 2 of 16
Page 3
2005/390
11. Any deck, balcony or terrace areas are not to be enclosed with shutters, glass panelling or the
like, thus remaining as open structures.
12. The balustrade of Apartment 1’s upper level rear deck shall be constructed of transparent
materials to reduce it’s visual impact upon the adjoining properties.
13. No gate shall be constructed across vehicle accessway to ensure the visitors car space is
open and accessible.
14. The proposed development shall have all kitchen, laundry and bathroom fittings that comply
with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation Rating
System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
Dishwashers and washing machines are excluded from this requirement.
15. A verification survey of the building is to be carried out by a Licensed Surveyor and a
certificate lodged with Council at completion of work confirming compliance with the maximum
allowable building height and fence height as required by the Planning Scheme and the
conditions of this approval.
16. Security in the form of a cash bond or trading bank guarantee to the sum of $10 000 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for Operational Works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
17. The requirements of this development approval are to be effected, prior to the use of the
premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
this approval to effect compliance with conditions.
18. The developer must obtain all of the other Development Permits referred to in the Decision
Notice, prior to obtaining a Development Permit for Building Works.
19. The Development Permit for a material change of use of premises lapses if the use has not
happened by 19 May 2014, unless an application to extend the currency is approved by
Council.
Land Development
Vehicle Access
20. A vehicular access driveway to serve the development shall be constructed from Hill Street
generally in accordance with drawing Nos 0511-02B and 0511-03A prepared by Earl
Covington And Associates dated 04/06.
21. The driveway shall be designed and constructed to Council’s design standards and to grades
that prevent vehicles from scraping and/or bottoming whilst also allowing pedestrians
movements along the footpath without any level difference. Should any driveways be
constructed to grades that do not comply with AS/NZS 2890.1-2004, Council will require that
the driveway be removed and reconstructed to levels that do comply.
Please note, a step between the driveway and the footpath shall be avoided, as it is preferred
to have the footpath continue at a constant grade to minimise the potential for pedestrians to
trip or fall.
22. The driveway shall be designed to ensure that stormwater does not pond in front of Nos 18 &
20 Hill Street.
23. All vehicles shall enter and leave the site in a forward direction.
Page 3 of 16
Page 4
2005/390
Carparking
24. Carparking shall be provided within the site generally as shown on drawing number DA.02D
dated 23.03.06 prepared by Bark Design, except as modified herein.
25. The carparking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004
for user class 1A with allowance for vehicles to enter and leave the site in a forward gear and
with a minimum head clearance (headroom) at any point of 2.2m.
26. All carparking shall be kept and maintained in a condition fit for use.
Park Contributions
27. A Park contribution of $1,296 towards the acquisition of additional parkland or the
improvement of existing parkland and facilities in the locality shall be paid to the Council prior
to obtaining a Development Permit for Operational Works in accordance with Council’s
Planning Scheme Policy PSP24 Park Requirements for Development Applications. This
amount will be subject to variations in the Consumer Price Index, All Groups Brisbane from
March 2006 until the date of payment.
Frontage Works
28. Footpath improvements such as topsoiling, grassing, and tree planting are required to the Hill
Street frontage of the site in accordance with Planning Scheme Policy PSP1 Landscaping
Guidelines. Grass shall be couch, free of weeds.
29. All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel,
footpath paving and landscaping such as trees and grasses in accordance with Council’s
Standard specifications prior to commencement of the use permitted by this permit.
Pathway Contributions
30. A pathway contribution of $292 towards external major pathways, in accordance with Planning
Scheme Policy PSP41 Pathway Trunk Network Contributions, shall be paid to the Council
prior to obtaining a Development Permit for Operational Works. This amount will be subject to
variations in the Consumer Price Index, All Groups Brisbane from March 2006 until the date of
payment.
Stormwater Drainage
31. All stormwater drainage shall be collected on site and discharged so there is no net increase
in stormwater runoff from the site. Stormwater drainage permitted to drain from the site shall
be discharged to Council’s kerb & channel street drainage system in Ross Crescent. Plans of
the drainage design shall be prepared by a Registered Professional Civil Engineer and
submitted to Council prior to obtaining a Development Permit for Operational Works.
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
drainage system at any one location is 25 litres/second.
32. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank
(minimum storage 3000 litres per dwelling/unit) that is installed to ensure water from the tank
can be used for external uses (such as watering gardens, irrigation, ornamental ponds, water
features, topping-up swimming pools, outdoor cleaning, etc) and for use in flushing of toilets
internal to the dwelling. All rainwater tanks are to be designed and installed in accordance
with the Queensland Development Code (QDC), Part 25 – Rainwater Tanks, and shall be part
of the plumbing application in conjunction with the building approval. The location and
capacity of the tanks shall be clearly shown on the plans submitted for Building Works
approval and any overflow shall be directed to the road frontage.
Page 4 of 16
Page 5
2005/390
33. An on-site infiltration system shall be provided to collect stormwater runoff from the access
driveway within the site. The on-site infiltration system shall have sufficient capacity to cater
for a 1 in 100 year storm event. The design of the on-site infiltration system shall be certified
by a qualified Geotechnical Engineer with regard to the capacity of the soils to cater for the
runoff.
34. No trees are to be removed in Hill Street, Ross Crescent or “Pat Mullins Park” during the
construction of the stormwater drainage system.
35. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
36. The site shall be connected to Council’s existing sewerage reticulation systems and be
constructed in accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
37. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
38. Each water connection to the water reticulation system shall extend to the property boundary
and be metered. Where multiple units are served by a single service, multiple water meters to
each individual unit shall be installed. All fees for the supply of water meters shall be paid to
the Council.
Service Easements (Stormwater)
39. A private easement for the Drainage of Water shall be created within “Pat Mullins Park” (Lot 9
MCH837249), to benefit the subject site. The easement is to be centrally located over the
pipework and a minimum of 1.5 metres wide or to be of sufficient width to ensure all
associated pits and pipes are wholly contained within the easement.
In addition to this the Applicant’s Solicitor shall give Council’s Solicitor an appropriate
undertaking in writing that the Title Deed and the easement documents will be lodged at the
Land Titles Office and any additional Titles Office forms or requisitions requiring the consent of
Council will be attended to promptly.
A duly executed copy of the easement shall be submitted to Council for perusal prior to the
use commencing.
Any changes required by Council’s Solicitor must be corrected immediately.
Headworks Contributions
40. Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28
and PSP30 on Water Supply Headworks Contributions and Sewerage Headworks
Contributions respectively and at the rates applicable at the time of payment. An estimate
only of the contribution rates under the current policies is outlined below. These amounts will
adjusted in line with changes to the Consumer Price Index, All Groups Brisbane from March
2006 until the date of payment.
Water Supply $1,944
Sewerage $1,613
TOTAL $3,557
All headworks contributions must be paid prior to the issue of a Development Permit for
Operational Works.
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
headworks contributions not be paid at the due time, Council shall call upon the trading bank
guarantee in full.
Page 5 of 16
Page 6
2005/390
In the event that the Development Permit for Material Change of Use of Premises lapses or is
cancelled, the contribution or trading bank guarantee will be returned
Earthworks & Site Stability
41. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences or structures that border the development site. Fences that are affected shall be
replaced prior to the Building Certifier issuing the Certificate of Classification. In this regard
any fences to be replaced shall be clearly shown on the plans submitted for Operational
Works approval.
42. A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
determine the soil classification, establish whether any measures are required to protect the
stability of adjoining buildings and/or structures, and make recommendations on the type of
foundation system(s) best suited for the proposed development. The recommendations of this
report are to be incorporated into the design and construction of the proposed development.
Erosion and Sediment Control
43. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General
44. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works, which shall be submitted in conjunction with an
application for a Development Permit for Operational Works.
45. Digital detailed design drawings and calculations shall be submitted with any application for a
Development Permit for Operational Works in respect of roadworks and stormwater drainage
works. To avoid conflict with underground pipes or services, all existing and proposed
services required by the development shall be shown on the plans.
46. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
47. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
48. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
Environmental Health
49. The developer must provide a suitably external screened imperviously paved area large
enough for all refuse and recycling containers.
50. Swimming pool or spa pumps are to be contained in an acoustically treated enclosure or
located in a manner which prevents a noise nuisance beyond the subject land in accordance
with the nuisance provisions of the Environmental Protection Regulation 1998. On the spot
fines apply for such offences.
51. Noise emission from air conditioning and swimming pool equipment shall comply with the
following requirements:
Page 6 of 16
Page 7
2005/390
51.1. The equipment shall be installed and located in a manner which prevents noise
nuisance beyond the subject land in accordance with the nuisance provisions of the
Environmental Protection Regulation 1998 and Council’s Local Law No. 12 - Control of
Nuisances. Infringement Notices (on-the-spot fines) may apply for offences.
51.2. Submission of written certification from a suitably qualified person confirming that the
noise levels comply when measured at the nearest residential boundary. This is
required immediately after installation of the equipment and prior to any occupation of
the building, and in a format approved by Council.
51.3. A person must not use equipment on any day if it makes or causes noise to be made:-
51.3.1. Before 7am or after 10pm: More than the lower of either –
40 d(B)A
3 d(B)A above the background noise level
51.3.2. From 7am to 7pm: More than the lower of either –
50 d(B)A
5 d(B)A above the background noise level
51.3.3. From 7pm to 10pm: More than 3 d(B)A above the background noise level.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Unexploded ordnance Concurrence Environmental GPO Box 2771, Brisbane
Protection Agency Qld 4001
A copy of any referral agency conditions is attached.
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
Plan / Document No. Rev. Plan / Document Name Date
V.05 DA.01 D Site Plan March 2006
DA.02 D Basement Plan March 2006
DA.03 C Ground Floor Plan March 2006
DA.04 C First Floor Plan March 2006
DA.05 C Roof Plan March 2006
DA.06 C North Elevation March 2006
DA.07 C East Elevation March 2006
DA.08 C South Elevation March 2006
DA.09 C, West Elevation March 2006
Page 7 of 16
Page 8
2005/390
DA.10 D Section A March 2006
DA.11 D Section B March 2006
DA.12 D Section C March 2006
DA.13 C Section D March 2006
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. The applicant is informed that payment via credit card transaction will not be an acceptable
method of payment for development contributions conditioned in this permit or for
infrastructure charge notices issued separately.
2. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
Local Law No. 12, prevents a builder or building contractor carrying out building work on a
building site in a way that makes or causes audible noise to be made from the building work:-
2.1. On a Sunday or public holiday, at any time; or
2.2. On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
3. In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
cement, concrete, builder’s waste or rubbish shall not be permitted to enter or be placed
where it could reasonably be expected to move into a roadside gutter, stormwater drain or a
watercourse. On the spot fines apply for such offences.
4. We advise ‘interested parties’ i.e. ‘developer’, ‘owner’, ‘tenant’ to consider their responsibilities
under the Disability Discrimination Act (DDA) in regard to the installation of disabled access
and the provision of disabled facilities, and that access to this building and the provision of
sanitary facilities may need to comply with the requirements of Section D Part D3 and Section
F Clause F2.4 of the Building Code of Australia.
5. Fencing to the swimming pools must comply with the Queensland Building Act 1975 Part 3 (as
amended) and Part 5 of Standard Building Regulation 1993 in all respects. Direct access from
the dwelling to the pool enclosure is not permitted.
6. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
the cost of operational works exceeds $80,000, then a portable long service leave levy is
required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
the approved form issued by the Building and Construction Industry (Portable Long Service
Leave) Authority that confirms that the requirements of the Act have been satisfied. A statutory
declaration outlining the cost of the operational works must be submitted to Council with the
lodgement of any application for operational works over the site.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
Page 8 of 16
Page 9
2005/390
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not applicable
9 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Building Works All building works
Development Permit for Operational Access and/or carparking, stormwater drainage,
Works frontage works, excavation of materials to fill another
site and landscaping
Preliminary Approval for Building Works Assessable against the Planning Scheme for Building
Removal or Demolition
10 SUBMISSIONS
There was 1 properly made submission about the application. In accordance with Sustainable
Planning Act 2009, the name and address of the principal submitter for each properly made
submission is provided and attached.
11 RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Sustainable Planning Act 2009 is attached.
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
Yours faithfully,
Denis Wallace
Senior Development Planner
Decision Notice History
19 May 2006 Original Decision Notice.
29 March 2010 Approved Change to
Condition 19 to extend
relevant period
Page 9 of 16
Page 10
2005/390
Referral Agency Conditions
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
Page 10 of 16
Page 11
2005/390 Page 11 of 16 [OCR of page images] 2005/390 IDAS C-6 Concurrence agency response Integrated Planning Act 1997 ss3 3 16 and 3 3 18 Applicant: Vasterby Pty Ltd C/- Dillon Folker Stephens, Town Planners PO Box 605 MAROOCHYDORE QLD 4558 Application no.: 2005/390 Date received by EPA: 30 March 2005 Surisdiction: Environmental Protection Act 1994 Role: Concurrence Description: Material Change of Use 22 Hill Street, SUNSHINE BEACH Lotno:491 Registered Plan no . RP48112 1 Type of development = =~—- Matenal change of use o Reconfiguration of a Lot where: o the existing use of the land 1s, or if the Jand 1s vacant land with no existing use the most o 2 recent use of the land was, for a nottfiable actrvity under the Environmental Protection Act 1994 the proposed use of the land 1s for child care, educational, recreational, residential or simular purposes and the existing use of the land 1s, or 1f the land 1s vacant land with no existing use the most recent use of the land was, for an industnal activity the land 1s on the Environmental Management Register or Contaminated Land Register under the Environmental Protection Act 1994. the land 1s wholly or partly withm an area for which an Area Management Advice for industrial activity or natural mmeralisation has been issued and the proposed use of the land 1s for child care, educational, recreational, residential or similar purposes the land ts wholly or partly in an area for which an Area Management Advice for unexploded ordnance (UXO) has been issued Response to development application The Environmental Protection Agency (EPA), actmg as a concurrence agency under the Integrated Planning Act 1997, provides the followmg response to the application detailed above - oOnoo0og8 3 conditions must attach to any approval of the development any approval must be for part only of the development any approval must be a prchmunary approval only there are no concurrence agency requirements the application must be refused Reasons for including condition(s) or refusal The site (the subyect lot/s) 1s part of an area of land within which the Department of Defence (Defence) has assessed a ‘substantial’ risk of residual UXO contamunation exists Defence advises that the current usage of land with UXO contammation potential, either ‘substantial’ or ‘slight’, may continue without specific need for UXO search or remediation. VER 2 Page 11 of 16
Page 12
2005/390 Page 12 of 16 [OCR of page images] 2005/390 IDAS C-6 However, Defence also advises that development or land use rezonmg proposals for land within a ‘substantial’ zone should only proceed following the conduct of UXO investigation and clearance acuvities. Defence mamtains a hist of commercial UXO mvestigation and remedial search contractors that it accredits to carry out this work Defence also recommends that owners or occupters of potentially affected land and workers and contractors employed on the land need to be aware of the procedure 1f a suspect object 1s found. As the EPA has no record of the site bemg further investigated or remediated, it 1s considered that there remains a possibilty of UXO bemg found on it 4 Conditions The following concurrence agency conditions are to be attached to any approval 4.1 Pnor to the commencement of any development-related excavation, earthworks or sot! disturbance, that part of the site to be so worked 1s to be subjected to investigation and, where necessary, appropriate remedial action. 4.2 Any person employed to work on any part of the site where Condition 4 1 has not been satisfied 1s to be forewarned in writing by the applicant This warning ts to explain that information available to the EPA indicates a potential for residual UXO exists on the site and work, particularly that nvolving excavation, earthworks or soil disturbance, should proceed with due caution. It 1s to state the procedure to be followed by any person finding an object suspected of beg explosive ordnance or component thereof Do not disturb the object. Take action, where appropriate, to prevent it being disturbed by another person Note its approximate dimensions and general appearance. Note the route to its location Advise the Police as soon as possible 43 Following investigation and any remedial action taken to satisfy Condition 4 1 above, the applicant 1s to submit a report, prepared 1n accordance with current guidelines, to the EPA for assessment. The EPA 1s to subsequently advise the Noosa Council of 1ts assessment m regard to Condition 4 1 being satisfied 44 No gravel, rock, sand or soil is to be removed from the site without written EPA approval 4.5 The apphcant is to advise the owner and any occupicr of the site of the above responsibilities 5 Additional comments or advice Applicants may contact the EPA’s Contaminated Land Unut on (07) 3224 5644 or visit the Defence website www defence gov au/army/uxo for the details of current UXO mvestigation and remedial search contractors The EPA accepts reports based on investigative and remedial work carried out by these contractors Investigation and remedial action to satisfy Condition 4 1 typically mvolves sampling/search programs with detection equipment unless the use of such equipment is: VER 2 Page 12 of 16
Page 13
2005/390 Page 13 of 16 [OCR of page images] 2005/390 IDAS C-6 © considered unwarranted by a UXO contractor due to the extent of any prior excavation or earthworks or, conversely, of any fillmg proposed as part of the development program, or © prevented or made impracticable by the presence of a structure, stockpile, natural barner or metal waste. In the latter case, alternative action may be appropnate to minimuse the risk in the first mstance For example, where the nsk of exposure to any UXO that may exist 1s reduced by the presence of a structure or natural barrier, issuance of the standard UXO wamung (see Condition 4.2) may suffice while the structure, stockpile or barner remains in place Where a structure is to be removed or teduced as part of the development program, protective precautions, commensurate with any greater tisk to which workers might then be exposed, may need to be considered Progressive assessment will be necessary where such circumstances exist. Uniess, at the completion of prelummary works, there 1s evidence then available to the UXO contractor that any residual nsk 1s neghgyble, the use of detection equipment will typically be required to confirm the site’s status Where investigation, along with any subsequent remedial action and assessment, 15 to be implemented by stages to satisfy Condition 4 1 and 4.3, a preliminary investigation report should be submitted by the applicant to the EPA along with a management plan for the proposed work Staged investi gation/remedhation 1s most likely to be applicable where development of smaller, built-on lots (which can present circumstances such as those discussed above) or broadhectare sites is proposed In such cases, the EPA’s assessment of the report and advice to Council in regard to approval of the development will be dependent on agreement with the management plan Where Condition 4 1 1s to be satisfied by a whole lot or broadhectare development stage being subjected to mvestigahon and any necessary remedial action, the EPA, based on the subsequent investigation/remediation report’s findings and recommendation/s, may reassess the lot, or that portion comprising the development stage, as bemg remediated or not needmg remediation, and advise the applicant and Council accordingly. Otherwise, any balance of land that has not been further imvestigated will retam the nsk assessment made by Defence. This 1s unless evidence obtained from the investigated part/s can be used to refute Defence’s assessment in regard to all or part of the balance. In the latter case, the EPA may reassess all of the balance or the applicable part/s as being unaffected by UXO. 6 Additioval information This concurrence response applies only to contammated land issues and does not remove the need to obtain any further approval for this development which may be required by this or other legislation, State and/or Commonwealth. Applicants are advised to check with all relevant statutory authorities. Applicants should also comply with all relevant legislation. The EPA has not provided a notification to native ttle parties for this application The State’s Native Title Work Procedures indicate that the responsibility for assessment of native title issues for an IDAS application rests with the Assessment Manager It 1s recommended that the Assessment Manager determmes whether native title notification 1s required for this application. *End of response* IDAS C-6 CLM VER2 Page 13 of 16
Page 14
2005/390
List of Submitters
SUSTAINABLE PLANNING ACT 2009, IDAS DEVELOPMENT
APPLICATION
P & PE Mullins 20 Hill Street SUNSHINE BEACH QLD
4567
Page 14 of 16
Page 15
2005/390
Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
The following is an extract from the Integrated (6) If an application involves assessment against a
Planning Act (Chapter 4). concurrence agency code, appeal rights for submitters
for the application are not available against the part of
Division 8 - Appeals to court relating to the approval that represents the concurrence agency’s
development applications response for the code.
Appeals by applicants Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application 4.1.29.(1) An advice agency may, within the limits of its
may appeal to the court against any of the following- jurisdiction, appeal to the court about the giving of a
(a) the refusal, or the refusal in part, of a development development approval for a development application if-
application; (a) the development application involves impact
(b) a matter stated in a development approval, including assessment; and
any condition applying to the development, and the (b) the advice agency told the applicant and the
identification of a code under section 3.1.6;1 assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a application as a submission for an appeal.
development permit was applied for; (2) The appeal must be started within 20 business
(d) the length of a relevant period; days after the day the decision notice or negotiated
decision notice is given to the advice agency as a
(e) a deemed refusal. submitter.
(2) An appeal under subsection (1)(a) to (d) must be Appeals for matters arising after approval given
started within 20 business days (the “applicant’s appeal
(co-respondents)
period”) after the day the decision notice or negotiated
decision notice is given to the applicant. 4.1.30.(1) For a development approval given for a
development application, a person to whom any of the
(3) An appeal under subsection (1)(e) may be started
following notices have been given may appeal to the
at any time after the last day a decision on the matter
court against the decision in the notice-
should have been made.
(a) a notice giving a decision on a request for extension
Appeals by submitters
of the relevanrt period for an approval;
4.1.28.(1) A submitter for a development application may
(b) a notice giving a decision on a request to make a
appeal to the court about-
minor change to an approval.
(a) the giving of a development approval, including any
(2) The appeal must be started within 20 business
conditions (or lack of conditions) or other provisions
days after the day the notice of the decision is given to
of the approval; or
the person.
(b) the length of a relevant period for the approval.
(3) Subsection (1)(a) does not apply if the approval
(2) The appeal must be started within 20 business resulted from a development application (superseded
days (the “submitters appeal period”) after the day the planning scheme) that was assessed as if it were an
decision notice or negotiated decision notice is given to application under a superseded planning scheme.
the submitter.
(4) Also, a person who has made a request
(3) If a person withdraws a submission before the mentioned in subsection (1) may appeal to the court
application is decided, the person may not appeal the against a deemed refusal of the request.
decision.
(5) An appeal under subsection (4) may be started at
(4) If an application involves both impact assessment any time after the last day the decision on the matter
and code assessment, appeal rights for submitters are should have been made.
available only for the part of the application involving
impact assessment. Division 9 - Appeals to court about other matters
(5) If an application is processed under section Appeals for matters arising after approval given
6.1.28(2), appeal rights for submitters for the application (no co-respondents)
are available only for the aspects of the development that 4.1.31.(1) A person to whom any of the following notices
would have required public notification under the have been given may appeal to the court against the
repealed Act. decision in the notice-
(a) a notice giving a decision on a request to change or
cancel a condition of a development approval.
1
Section 3.1.6 (Preliminary approval may override local
planning instrument)
Page 15 of 16
Page 16
2005/390
(b) a notice under section 6.1.442 giving a decision to (c) the decision to give a preliminary approval when a
change or cancel a condition of a development development permit was applied for;
approval. (d) the length of a period mentioned in section 3.5.21
(2) The appeal must be started within 20 business relevant period;
days after the day the notice of the decision is (e) a deemed refusal.
given to the person.
(2) An appeal under subsection (1)(a) to (d) must be
(3) Also, a person who has made a request started within 20 business days (the “applicant’s appeal
mentioned in subsection (1)(a) may appeal to the period”) after the day the decision notice or negotiated
court against a deemed refusal of the request. decision notice is given to the applicant.
(4) An appeal under subsection (3) may be started at (3) An appeal under subsection (1)(e) may be started
any time after the last day the decision on the at any time after the last day a decision on the matter
matter should have been made. should have been made.
Appeals against decisions to change approval conditions The Registrar for the Building and Development
under the repealed Act Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a decision http://www.localgovernment.qld.gov.au/
made on an application to change the conditions
attached to an approval given under section 2.19(3)or For Infrastructure Charges Only
section 4.4 of the repealed Act may appeal to the court 4.1.36 Appeals about particular infrastructure
against- charges
(a) the decision; or (1) This section applies to a person who has been
(b) a deemed refusal of the application. given, and is dissatisfied with, an infrastructure charges
notice or a regulated State infrastructure charges notice.
(2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of (2) The person may appeal to the court against the
the decision is to be given to the person. notice.
(3) An appeal under subsection (1)(b) may be started (3) The appeal must be started within 20 business days
at any time after the last day a decision on the matter after-
should have been made. (a) if the notice is given because of a development
Appeals against local laws approval or master plan approval-the day the
applicant is given notice of the decision about the
4.1.33B.(1) An applicant who is dissatisfied with a
approval; or
decision of a local government or the conditions applied
under a local law about the use of premises or the (b) otherwise-the day the notice is given to the person.
erection of a building or other structure permitted by the (4) An appeal under this section may only be about-
planning scheme may appeal to the court against the
(a) whether a charge in the notice is so unreasonable
decision or the conditions applied. that no reasonable relevant local government, State
(2) The appeal must be started within 20 business infrastructure provider or coordinating agency could
days after the day notice of the decision is given to the have imposed it; or
applicant.
(b) an error in the calculation of the charge.
For Building Works Only (5) To remove any doubt, it is declared that an appeal
Rights of appeal conferred by Section 4.2.9 of the under this section can not be about the methodology
Integrated Planning Act 1997 as follows: used to establish the charge in the relevant infrastructure
Division 3 – Appeals to tribunals relating to charges schedule or regulated State infrastructure
development applications charges schedule.
Appeals by applicants
4.2.9(1) An applicant for a development application may
appeal to the Building and Development Tribunal against
any of the following-
(a) the refusal, or the refusal in part, of a development
application;
(b) a matter stated in a development approval, including
any condition applying to the development, and the
identification of a code under section 3.1.6;3
2
Section 6.1.44 (Conditions may be changed or
cancelled by assessment manager or concurrence
agency in certain circumstances)
3
Section 3.1.6 (Preliminary approval may override local
planning instrument)
Page 16 of 16
Used in these records
Decision Letter - Change to an Existing Approval [As Published]Related documentApplication case desk ↗
About this file
- File size
- 299 KB (small file)
- File type
No other editions are linked here.