DELEGATED REPORT
PLANNING ASSESSMENT BRANCH

REQUEST FOR NEGOTIATED DECISION NOTICE

Application no:	OPW15/0199             Date: 30/12/2015
	
Project Manager:	Monkeith Kadhum - Development Engineer
	

APPLICATION DETAILS
Application Number:	OPW15/0199
Applicant:	Sunshine Beach Constructions ATF The Tahiti Discretionary Trust
Representations Received Date:	
Original Approval Type:	Development Permit for Operational Work Engineering Works – Earthworks,  Stormwater Drainage Works, Roadworks and Landscaping.
Number of Submissions for Original Application:	Non
PROPERTY DETAILS
Property Address:	6 Crank St SUNSHINE BEACH  QLD  4567
RP Description:	Lot 431 RP 48112
Land Area:	514.0000 Square Metres

BACKGROUND:

A Preliminary Approval for Operational Work Engineering Works - Drainage Works, Landscaping, Stormwater & Earthworks was issued on 23 Nov 2015.

A preliminarily approval and not a development permit was issue solely due to the lack of payment of the required Performance Bond ($10,000).  The preliminarily approval included only one condition and related advisory notes, as follow:

Condition:
Prior to the issue of a Development Permit for Operational Works, payment of the Performance Bond as described in Condition 7 of the higher order Development Permit for Material Change of Use, Council Reference MCU15/0068 dated 6 October 2015, must be made to Council.

Advisory Notes:
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
It must be noted that a Preliminary Approval for Operational Works does NOT permit commencement of any works.  Further representation to change the Preliminary Approval to a Development Permit may be made within the appeal period (normally 20 business days unless the appeal period is suspended).  After the appeal period expires, the Preliminary Approval cannot be changed to a Development Permit, and a fresh development application for Operational Works will be required to be made, addressing the requirements of the Preliminary Approval.
A Development Permit for Operational Works has not been issued because payment of the Performance Bond as described in Condition 7 of the higher order Development Permit for Material Change of Use, Council Reference MCU15/0068 dated 6 October 2015, has not been made.  Council may favourably consider changing the Preliminary Approval to a Development Permit via the Negotiated Decision process, if the applicant has made payment of the Performance Bond.

REPRESENTATION:

The applicant made representation to the development approval conditions received by Council on 4 December 2015.  The representation confirms that the required bond in a bank guarantee form for $10,000 (Council’s Ref BAGS5006398) has been submitted to Council in compliance with Condition 7 of the higher order approval MCU15/0068 and requesting the issue of a Development Permit approval.

ASSESSMENT:

The applicant has now complied with the condition of the preliminary approval and required bond payment. As such a Development Permit can now be issued.

Recommendation

It is recommended that a Negotiated Decision Notice for a Development Permit for Operational Works be issued with all relevant items and the required conditions.

RECOMMENDATION

AGREE to the representations submitted in relation to Application No. OPW15/0199, situated at 6 Crank St SUNSHINE BEACH QLD  4567 , and issue a Negotiated Decision Notice in accordance with the following:-

A.	Change the approval type to the following: A Development Permit for Operational Work Engineering Works – Earthworks, Stormwater Drainage Works, Roadworks and Landscaping

B.	Include the required items for a decision notice and the relevant and necessary conditions for the Development Permit as provided in the Attachment: Document – “Report Conditions” in T1

Monkeith Kadhum

30/12/2015

[Attachment: image1.png (image text)]
 
 
 

 
 
 

a
mm

  

NOOSA
COUNCIL

Used in these records

About this file

File size
52 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

OPW15_0199 - Negotiated Report.docx · 52 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.