Delegated Report - Code - Planning MCU23 0109 · MCU23/0109
Author Development Planner, Tara Norley Development Assessment APPLICATION DETAILS Application No. MCU23/0109, OPW23/0123 & RAL23/0017 Applicant Davrus P/L TTE Proposal Material Change of Use - Multiple dwelling (10 small dwellings), Reconfiguring a Lot (Community Title) Operational Works (Road work, Stormwater, Drainage Work, Earthworks and Landscaping). Properly Made Date Information Request Date 4 October 2023 Information Response Date 21 March 2024 Decision Due Date 14 May 2024 Report Reviewed & Finalised By Nadine Gorton 20.05.2024 PROPERTY DETAILS Property Address 20 Kauri St, Cooroy RP Description Lot 1 RP 203032 Land Area 2030m² Existing Use of Land Dwelling house STATUTORY DETAILS SEQRP Designation Urban Footprint Zone Medium Density Residential Precinct Not Applicable Local Plan Area Cooroy Overlays Nil Assessment Type Code PROPOSAL The application seeks approval for: Material Change of Use - Multiple dwelling (10 small dwellings), Reconfiguring a Lot (Community Title) Operational Works (Road work, Stormwater, Drainage Work, Earthworks and Landscaping). The proposal includes 10 two bedroom small dwellings, being a maximum of 100m2 each. Each dwelling is provided with one undercover car park, with two uncovered visitor carparks also provided on site. Each dwelling is provided with private open space areas at ground level, with Units 3 to 7 also having upper level verandas. The locality and proposal plan are included below. Figure 1 – Locality Figure 2 – Subject Site Figure 3 – Site Plan Figure 4 – Floor Plans – Units 1,2, 8, 9 & 10 (lower and upper) Figure 4 – Floor Plans – Units 3 - 7 Figure 5 – Renders site details Site Description The subject site is a rectangular 2028m2 lot with a 22m frontage to Kauri Street. The site slopes from the east to the west, falling to the south west corner. The site contains scattered existing planted vegetation. Surrounding Land Uses The site is located within a predominantly residential area consisting of a mix of dwelling houses and multiple dwellings, however does adjoin a child care centre to the south and a Council reserve to the west. assessment Instruments for Statutory Assessment Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development: State Planning Policy; South East Queensland Regional Plan; Planning Regulation 2017; and Noosa Plan 2020 (25 September 2020). Noosa Plan 2020 The following codes from the Noosa Plan 2020 are applicable to this development: Medium Density Residential Zone Code; Cooroy Local Plan Code; Dual Occupancy and Multiple Dwelling Code; Works Codes; Reconfiguring a Lot Code. The subject site is located in Cooroy and is zoned Medium Density Residential. The proposed use is identified as a consistent use within the zone and is required to follow a code assessable application process. The application has been found to generally comply with all applicable statutory instruments. The pertinent issues arising out of the assessment are discussed below: Criteria Planning Scheme Proposal Complies Building height storeys metres 2 storeys max 8 metres 2 storeys 8 metres Site cover 45% max (912.5m2) 45% (914m2) Plot ratio 0.5:1 max. (1014m2 GFA) 0.49:1 (990m2 GFA) Boundary setbacks Ground Floor Frontage Side (north) Side (south) Rear 6 metres min 1.5 metres min 1.5 metres min 6 metres min 6 metres 1.3 metres 2.6 metres 2 metres X X Upper Floor Frontage Side (north) Side (south) Rear 6 metres min 2.0 metres min 2.0 metres min 6 metres min 8.8 metres 2.5 metres 2.6 metres 4.7 metres X Length of wall 15 metres max Building 3 – 19.5m Building 4 – 17.5m Though both buildings include walls that are offset by more than 600mm and as such not measure as one wall. Roof Form Pitch Eaves Min 5 degrees Min 600mm to 75% Up to 17 degrees 100% Landscaped open space Soft landscaping Landscaping Setbacks Min 35% (709m²) Min 60% of total (426m2) 6m frontage 35% (713m²) 85% (606m²) 6m frontage Private Open Space 20m² min All >20m² Carparking 10 covered resident min 3 visitor min 10 covered 2 uncovered spaces 2 motorbike spaces X Setbacks Acceptable Outcome AO12.1 of the Medium Density Residential Zone Code states: AO12.1 Buildings and structures meet the following minimum boundary setbacks: for frontages — 6 metres for side boundaries— 1.5 metres setback up to 4.5 metres height; 2 metres setback between 4.5 metres and 7.5 metres height; and 2.5 metres where above 7.5 metres height for the rear boundary - 6 metres The applicant is proposing a minimum setback of 1.3m to the northern side boundary and 2m to the rear boundary, and as such does not comply with AO12.1 of the Medium Density Residential Zone Code. The proposal is therefore required to comply with corresponding Performance Outcome PO12 of the Medium Density Residential Zone Code, which states: PO12 Buildings and structures are designed and sited to: provide a high level of amenity to users of the subject site and adjoining premises, including provision of visual and acoustic privacy; not unreasonably obstruct views or cause overlooking of private open space or habitable areas of adjoining premises; provide adequate distance from adjoining land uses; preserve existing vegetation that will help buffer development; allow for space and landscaping to be provided between buildings including adequate area at ground level for landscaping with trees, shrubs, outdoor living and utilities; be consistent with the predominant character of the surrounding area; and protect the natural character and avoid adverse impacts on ecologically important areas such as national parks, waterways and wetlands. Side Setback The northern side boundary encroachment relates to the eaves of the ground floor patio roofs only (refer to Figure 6), and as such is very minor in nature and will not compromise the visual or acoustic privacy, or unreasonable obstruct views or cause overlooking of the adjoining lot to the north. In addition, the setback provides an adequate distance from the dwelling to the north. The proposal therefore complies with PO12 of the Medium Density Residential Zone Code. Figure 6: Portions of the dwellings within the 1.5m northern setback Rear Setback The proposed rear setback includes 2m to the ground floor patio roof and approximately 4.8m to both the ground floor and upper level building (refer to Figure 7). Figure 7: Portions of the dwellings within the 6m setback from rear boundary The subject site adjoins a reserve to the rear, and as such the reduced setback will not impact on amenity or privacy of residents to the rear, whilst the covered ground floor terrace area will provide increased amenity to the residents of Building 4. The setback will not impact on the character of the area, and will be consistent with existing development adjoining the reserve, which is setback a minimum of 1.7m from the boundary (refer to Figure 8). Figure 8: Existing development adjoining the reserve Council’s Senior Environment Officer has reviewed the application material and confirmed that large trees within the adjoining Council Environmental Park are to be protected during construction and reviewed prior to the commencement of use. Where remediation is required (tree removal or trimming of branches) these works will be undertaken by the developer. Conditions are included in the recommendation regarding the retention of vegetation in the reserve. As such, the proposal will preserve existing vegetation that will help buffer development to the west, whilst protecting the natural character and ecological values of the reserve. The proposal therefore complies with PO12 of the Medium Density Residential Zone Code. Carparking Acceptable Outcome AO13 of the Dual Occupancy and Multiple Dwelling Code requires carparking to be provided at a rate of one covered space for each two bedroom dwelling, and one visitor space per four dwellings. As such, the proposal is required to provide 10 resident spaces and 3 visitor spaces. The proposal includes 10 resident and 2 visitor spaces, and therefore is required to comply with corresponding Performance Outcome PO13 of the Dual Occupancy and Multiple Dwelling Code, which states ‘sufficient on-site car parking is provided to accommodate the number and type of vehicles likely to be generated by the residential use without impacting on the safety or amenity of the adjoining streets’. Council is typically not supportive of a shortfall in carparking for multiple dwelling proposals, however the proposal is a predominantly compliant development (eg plot ratio, site cover, landscaping etc), providing for 10 small dwellings within the Cooroy Local Plan Area, providing increased housing choice in the area. Additionally, the applicant has proposed two motorcycle spaces on site in lieu of the third visitor car park, in accordance with Acceptable Outcome AO6.2 of the Driveways and Parking Code which states, where appropriate, motorcycle spaces can be provided on site in lieu of required car parking spaces, excluding industry activities, at the following rates: 2 motorcycle spaces provided for 0.5 car parking space; or 4 motorcycles spaces provided per 1 car parking space; and up to a maximum of 4 car parking spaces. It is noted that the Driveways and Parking Code does not require motorcycle spaces to be provided for residential uses, however the Overall Outcome 2 (c) of the Code states ‘the use of motor scooters and motorcycles are promoted as an alternative to cars within urban areas, with appropriate parking provided for such vehicles’. As such, the proposal for 10 resident spaces, 2 visitor spaces and additional motorbike parking is considered to be sufficient for the proposal. However, a plan amendment is included in the recommendation requiring the provision of a minimum of four motorcycle spaces (rather than the proposed two), or alternatively, for a third visitor space to be provided on site. Adjoining Uses – Child Care Centres The subject site adjoins a child care centres to the south and north west (refer to Figure 9). Figure 9: Adjoining Child Care Centres (shown in yellow) The southern elevation of all four buildings include small, higher set windows on the upper level, each with a sill height less than 1.7m (refer to Figure 10). These windows may provide opportunities for overlooking into the Child Care Centre to the south. A condition is included in the recommendation requiring any overlooking (should it occur) to be mitigated. Figure 10: Southern Elevations The western elevation of Building 4 includes large windows in the bedrooms of each of the units on the upper level (refer to Figure 11). These windows may provide opportunities for overlooking into the Child Care Centre to the north west. A condition is included in the recommendation requiring any overlooking (should it occur) to be mitigated. Figure 11: Western elevation of Building 4 cONSULTATION Referral Agencies Not Applicable Internal Council Referrals The application was forwarded to the following internal Council officers for review and/or comment: Development Engineer, Development Assessment: The subject site naturally grades towards the south-west primarily into an Environmental Reserve owned by the State of Queensland (with Council as trustee) and partially into a child day-care centre. A residential battleaxe block exists to the north of the subject site. The subject site reserves sheet flow from the site to the north. The site is provided with a driveway crossover that generally complies with Council’s standard drawing RS-051. The carparks provided on site are functional and considered generally in accordance with AS2890. The development includes a balance of cut (up to ~1.4m) along the northern property boundary and fill (up to ~0.7m) along the southern property boundary. The proposed earthworks have been designed by a suitably qualified person (RPEQ). The development includes a series of on-site reuse water tanks, detention tanks and bioretention basin. The development provides 28kL of the required 30kL on-site reuse storage. Council’s external stormwater consultant advised Council that the shortfall may be considered acceptable provided a water balance model is provided demonstrating that 80% of the reuse demand is met. A condition has been included. The detention tanks are provided and sized to ensure pre- and post-development flows do not create a non-worsening downstream during events up to, and including, the Q100. The on-site stormwater infrastructure is fitted with gross pollutant field inlet baskets and a bioretention basin to address stormwater quality. The management plan has been designed by a suitably qualified person (RPEQ). Sufficient information has been provided demonstrating that the receiving waters are protected as part of the development. The verge fronting the subject site contains an existing pedestrian footpath. The applicant is proposing to reconstruct ~<1.0m of footpath either side of the driveway crossover to achieve a smooth transition between the crossover and existing footpath. The ~<2.0m of reconstructed footpath will become Council’s asset. It is recommended that a standard maintenance bond for the municipal works and a 12-month maintenance period be conditioned, noting that an ‘As-Con’ package and ADAC data is not considered necessary in this instance. Engineering believes the development generally meets the relevant provisions of The Noosa Plan 2020 and recommends the following conditions. Senior Environment Officer, Development Assessment: Landscape plans have utilised an assortment of predominately native plant species throughout the development. Large trees have been provided where possible within each units back yard, along the southern boundary and Kauri Street frontage. A bioretention basin has been provided in the south west corner of the site between the fence and unit 10. Large trees are not permitted within these devices. Due to the topography of the property this is the logical location of this device. 1 Large tree within the north western corner of the day care centre is required to be reviewed during the construction works in accordance with the arborist report. Large trees within the Council Environmental Park are to be protected during construction and reviewed prior to the commencement of use. Where remediation is required (tree removal or trimming of branches) these works will be undertaken by the developer conclusion & reasons for decision The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval. The report is provided in accordance with Section 63(5) of the Planning Act 2016. RECOMMENDATION With regard to Application No MCU23/0109 for a Material Change of Use - Multiple dwelling (10 small dwellings), RAL23/0017 for Reconfiguring a Lot (Community Title) and OPW23/0123 for Operational Works (Road work, Stormwater, Drainage Work, Earthworks and Landscaping) situated at 20 Kauri St Cooroy Qld 4563 and described as Lot 1 RP 203032, it is recommended the application be approved in accordance with the following details for the Decision Notice: application details Application No: MCU23/0109 Street address: 20 Kauri St Cooroy Qld 4563 Real property description: Lot 1 RP 203032 Planning Scheme: Noosa Plan 2020 (25 September 2020) Decision details Council decided to issue the following type of approval: Development Permit for a Material Change of Use - Multiple dwelling (10 small dwellings), Development Permit for Reconfiguring a Lot (Community Title) Development Permit for Operational Works (Road work, Stormwater, Drainage Work, Earthworks and Landscaping). CURRENCY PERIOD of approval The currency period for this development approval is stated in the conditions below. assessment manager conditions MCU23/0109 - Material Change of Use - Multiple dwelling (10 small dwellings) Planning When Conditions must be Complied With Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues. Currency Period This development approval lapses if the use has not happened by 14 May 2030, unless an application to extend the currency period is approved by Council. Approved Plans Development authorised by this approval must be undertaken generally in accordance with the Approved Plans listed in the tables below. The plans must be amended to incorporate the amendments listed within the table below and resubmitted to Council prior to the issue of any Development Permit for Building Works* Plan No. Rev. Plan/Document Name Date 202304 DA.08 A Upper Floor prepared by Black Wood 03.08.2023 202304 DA.09 A Roof Plan prepared by Black Wood 03.08.2023 202304 DA.10 A Site Elevations & Sections prepared by Black Wood 03.08.2023 202304 DA.12 A Building 1/2 – Roof & Elevations prepared by Black Wood 03.08.2023 202304 DA.13 A Building 1/2 – Sections prepared by Black Wood 03.08.2023 202304 DA.15 A Building 3/4 – Roof & Elevations prepared by Black Wood 03.08.2023 202304 DA.16 A Building 3/4 – Elevations & Sections prepared by Black Wood 03.08.2023 The following plans require amendment. Plan No. Rev. Plan/Document Name Date 202304 DA.07 A Ground Floor prepared by Black Wood 03.08.2023 202304 DA.11 A Building 1/2 - Ground & Level 1 prepared by Black Wood 03.08.2023 202304 DA.14 A Building 3/4 - Ground & Level 1 prepared by Black Wood 03.08.2023 ED 23153 OPW - 02 A Landscape Plan Operational Works prepared by Element Design 30.06.2023 ED 23153 OPW - 03 A Landscape Plan Operational Works prepared by Element Design 30.06.2023 Amendments Provide a minimum of four motorbike parking spaces on site, or alternatively, provide a third visitor car park in lieu of motorcycle spaces. *(Refer to Advisory Note) Building Height The maximum height of the development must not exceed 8 metres above the ground level. Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which certifies that the buildings do not exceed the maximum height requirement of this Decision Notice. Performance Bond Security in the form of a cash bond or trading bank guarantee to the sum of $60,000 must be submitted to Council, to secure performance of all conditions of this approval prior to pre-start meeting. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions. Water & Sewer Connections An underground connection to reticulated water and sewerage must be provided to the premises in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater). A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to the premises. Building Appearance External design features, materials and finishes must be as shown on the Approved Plans, with no inclusions or alterations made without approval in writing by Council. External finishes of the building must be a mix of lightweight and textured external finishes, with masonry areas incorporating a variety of textured finishes to break up the surface. All deck and balcony areas must not be enclosed with shutters, louvres, glass panelling or the like thus remaining as open structures, except where required to satisfy any privacy condition of this Decision Notice. All balustrades to decks and balcony areas must be open or transparent. All air conditioning units or other mechanical equipment must be fully enclosed or screened such that they are not visible from the street frontages nor adjoining properties. Waste storage areas, clothes drying areas and external storage areas must be screened from view of the street. Fencing and Walls Any street fencing must not exceed 1.8 metres in height, be set back an average of 1 metre and articulated to provide visual interest by stepping the design. Any fencing on the front boundary must either: not exceed a maximum height of 1.2 metres be of open construction. The area of land between the fence and the front property boundary must be densely landscaped to screen any fencing from the street. Protection of Privacy To ensure privacy is protected between adjoining properties, any windows on upper level of the western building face of Building 4; and on the upper level of the southern building face of all buildings that result in overlooking of the childcare centres located to the south and north-west must either: have a minimum window sill height or 1.7 metres above floor level; or be fitted with translucent glazing; or be fitted with a fixed external screen. Landscaping Works The development site must be landscaped. The works must be undertaken in accordance with Operational Works approval OPW23/0123, PSP 2 - Landscape and the Noosa Plan 2020 for that specific area and must include in particular: the works shown on the Approved Plans vegetated screening of any electrical transformers, bin storage areas and the like from the road frontage All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached. Waste Management A Waste Management Plan must be prepared that details the type and quantity of waste material that is likely to be generated by the development; where and how the waste will be stored, disposed of and procedures for handling the waste. The Waste Management Plan must be submitted and approved by Council prior to the issue of a Development Permit for Building Works. Community Management Statement Any proposed Community Management Statement required for the development pursuant to the Body Corporate and Community Management Act 1997 must be submitted to Council for endorsement at the same time as submission of the Building Format Plan (or similar) to Council for compliance assessment. All clauses and by-laws of the proposed Community Management Statement must accord with the requirements of this Decision Notice and, in particular, must include the following additional clauses: The dwelling units are not permitted to be used for short term accommodation, unless where identified as accepted development by the Noosa Plan or where there is a Development Permit for Material Change of Use for Short Term Accommodation in effect. Short term accommodation means the use of the premises for providing accommodation of less than 3 consecutive months to tourists or travellers. Engineering External Works Kauri Street must be upgraded for the length of its frontage to the subject site. The works must be undertaken in accordance with the conditions of this approval and Operational Works approval OPW23/0123, be generally in accordance with SCG Consulting’s Driveway & Access Plan (OW4.1, Rev. B) dated 7 March 2024 and must include in particular: construction of a transitional pedestrian footpath in accordance with the conditions of this Decision Notice; and removal of the existing property access and reinstatement of the kerb, footpath and verge area to match the balance of the site frontage, including the provision of topsoil and turf where the existing verge is grassed. Site Access and Driveways A sealed access driveway must be provided from Kauri Street to all parking and manoeuvring areas of the development. The works must be undertaken in accordance with the conditions of this approval and Operational Works approval OPW23/0123, and be generally in accordance with SCG Consulting’s Driveway & Access Plan (OW4.1, Rev. B) dated 7 March 2024 and Driveway Details (OW4.3) dated June 2023 and must include in particular: a driveway crossover in accordance with Council’s standard drawing RS-051. Car Parking A minimum of ten (10) covered and two (2) uncovered car parking spaces and either an additional uncovered carpark space or four (4) motorbike spaces must be provided and marked on the site. The works must be undertaken in accordance with the conditions of this approval and Operational Works approval OPW23/0123, be generally in accordance with SCG Consulting’s Driveway & Access Plan (OW4.1, Rev. B) dated 7 March 2024 and must include in particular: Three visitor spaces or two visitor car parking and four motorbike spaces within the total, which are clearly marked for that purpose and accessible at all times for visitor use; and dimensions, crossfalls and gradients in accordance with Australian Standard AS2890: Parking Facilities. Pedestrian and Bicycle Facilities Pedestrian and bicycle facilities must be provided for the development. The works must be undertaken in accordance with the conditions of this approval and Operational Works approval OPW23/0123, be generally in accordance with SCG Consulting’s Driveway & Access Plan (OW4.1, Rev. B) dated 7 March 2024 and must include in particular: a transitional concrete footpath adjacent to each side driveway crossover. Stormwater Drainage The site must be provided with a stormwater drainage system connecting to a lawful point of discharge. The works must be undertaken in accordance with the conditions of this approval and Operational Works approval OPW23/0123, be generally in accordance with SCG Consulting’s Stormwater Management Plan (SW1.1, Rev. B) dated 7 March 2024. A minimum of 10 business days prior to arrange the prestart meeting, provide, and have accepted by Council, a water balance model for the proposed roofwater storage tanks which justifies the proposed size of the tanks; for example, by demonstrating that 80% of the reuse demand can be met with the proposed configuration. As part of the model, include plans showing the areas to be irrigated by each tank and state reuse demand assumptions for all categories of fixtures. Services Underground reticulated electricity and telecommunication services must be provided to each lot/unit in accordance with the conditions of this approval and the standards and requirements of the relevant service provider. Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications. Certification must be submitted to Council from all relevant service providers (Energex, NBN and Unitywater) which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction. Easements Unless otherwise agreed in writing by the relevant service provider, any public or third party infrastructure located on the subject site must be placed within an easement registered against the title of the property. All easements must be designed in accordance with the planning scheme and granted at no cost to the Grantee. Where the Grantee is Council or a service authority, the easement documentation must be in accordance with the Grantee’s standard easement terms. Draft easement documentation must be submitted to Council for endorsement. All works must be kept clear of any existing or proposed easements on the subject land, unless agreed otherwise in writing by the Grantee. Earthworks and Retaining Walls All earthworks and associated retaining structures/batters, both above and below ground, both temporary and permanent, must be undertaken in accordance with the conditions of this approval and Operational Works approval OPW23/0123, be generally in accordance with SCG Consulting’s Bulk Earthworks Plan (OW3.1) dated June 2023 and contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council. Where the development involves excavation or filling over, or adjacent to, drainage, water supply or sewerage infrastructure, all access chamber surface levels must be adjusted to provide a freeboard of 100mm above the finished ground surface level. All retaining walls must be designed and constructed in accordance with the planning scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade safety fence. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. RAL23/0017 - Reconfiguring a Lot (Community Title) When Conditions Must Be Complied With Unless otherwise stated, all works required by the conditions of this Decision must be completed prior to submission of the subdivision plan to Council for compliance assessment. Currency Period This development approval lapses if the requirements of the conditions have not been completed and an application for plan seal is not lodged with Council by 14 May 2030, unless an application to extend the currency period is approved by Council. Approved Plans Development authorised by this approval must be undertaken generally in accordance with the Approved Plans listed in the tables below. Plan No. Rev. Plan/Document Name Date 202304 DA.05 A Property Plan prepared by Black Wood 08.08.2023 All lot numbering on the subdivision plan to be submitted to Council for compliance assessment must remain as shown on the Approved Plans. Water & Sewer Connections An underground connection to reticulated water and sewerage must be provided to each lot in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater). A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to each lot. Services Underground reticulated electricity and telecommunication services must be provided to each lot in accordance with an approval for Operational Works and the standards and requirements of the relevant service provider. Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications. Certification must be submitted to Council from all relevant service providers (Energex, NBN) which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction. Community Management Statement Any proposed Community Management Statement required for the development pursuant to the Body Corporate and Community Management Act 1997 must be submitted to Council for endorsement at the same time as submission of the subdivision plan to Council for compliance assessment. All clauses and by-laws of the proposed Community Management Statement must accord with the requirements of this Decision Notice. Prior to Council sealing the plan of survey, all works described within this Decision Notice must be completed and accepted by a Council representative. OPW23/0123 - Operational Works (Road work, Stormwater, Drainage Work, Earthworks and Landscaping). APPROVED PLANS Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. The plans must be amended to incorporate the amendments listed within the table below and resubmitted to Council prior to the issue of any Development Permit for Building Works* Plan No. Rev. Plan/Document Name Date OW3.1 . Bulk Earthworks Plan prepared by SCG Consulting June 2023 OW4.1 B Driveway & Access Plan prepared by SCG Consulting 07.03.2024 OW4.2 B Driveway Levels prepared by SCG Consulting 07.03.2024 OW4.3 . Driveway Details prepared by SCG Consulting June 2023 SW1.1 B Stormwater Management Plan prepared by SCG Consulting 07.03.2024 SW1.2 A Retention / Detention Tank Details prepared by SCG Consulting 07.03.2024 SW1.3 A Stormwater Details prepared by SCG Consulting 07.03.2024 ED 23153 OPW - 01 A Landscape Plan Operational Works prepared by Element Design 30.06.2023 ED 23153 OPW - 04 A Plant Schedule & Specification Sheet prepared by Element Design 30.06.2023 ED 23153 OPW - 05 A Landscape Plan Details Sheet prepared by Element Design 30.06.2023 - - Australian Tree Contractors & Arboricultural Consultants Managing Trees in the Urban Environment prepared by Kurt Brown 10.09.2024 The following plans require amendment. Plan No. Rev. Plan/Document Name Date ED 23153 OPW - 02 A Landscape Plan Operational Works prepared by Element Design 30.06.2023 ED 23153 OPW - 03 A Landscape Plan Operational Works prepared by Element Design 30.06.2023 Amendments Provide a minimum of four motorbike parking spaces on site, or alternatively, provide a third visitor car park in lieu of motorcycle spaces. *(Refer to Advisory Note) CURRENCY PERIOD The Currency Period for this development approval lapses if the development has not substantially started by 14 May 2026, unless an application to extend the currency period is approved by Council. SITE SPECIFIC CONDITIONS Bonds A site control and/or compliance bond of $20,000 is to be submitted to Council prior to the pre-start meeting. The pre-start meeting will only be held once Council's Construction Engineering Officer has confirmation that the bond monies have been received by Council. The bond will be refunded less any costs incurred by Council in ensuring compliance with these conditions or any additional inspections incurred for substandard work or work undertaken not in accordance with this permit. Bonds must: have approval of the bond calculations and amount from Council prior to lodgement. be lodged with Council and accompanied by the Bond Administration Fee/s. be requested for release by writing to Council, when relevant approval requirements have been met. Engineering PRIOR TO COMMENCEMENT OF WORKS Engineering All necessary approvals from external service providers (e.g., Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council. A condition report including photographs of the frontage of the site must be completed and submitted to council at the prestart meeting / prior to any works commencing. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting. Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties for the following aspects of the works: Civil engineering works; Landscape works; Erosion and sediment control works; and Other relevant parties. A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following: Traffic Management during all aspects of the construct phase including: A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction; Maintenance of safe vehicle and pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased; Proposed fencing to the site during the construction phase of the development; Adequate parking arrangements for construction workers; and No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off. Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures; Works programme identifying key components of the works and their respective durations; Establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic and services and other relevant issues; Include a post out to the local residents and businesses advising of the proposed development, the expected time frames and the site contact details; Include signage in prominent locations on the boundaries of the site advising of the proposed development, the expected time frames and the site contact details; identification of complaint management procedures including: contact details for the on-site manager; dispute resolution procedures; and For haulage operations involving significant volumes of fill material or excavated material being transported onto or off the site: details on the location of external fill sites/sources, the haulage route, type of vehicle to be utilised during filling operations and frequency of usage. NB any damage to the existing road system as a result of haulage operations shall be fully repaired at the applicant’s expense. Prior to the commencement of municipal works associated with this development, Council requires the provision of a bank guarantee, or a cash bond, of not less than 10% (minimum of $1,500) of the value of the municipal works. Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. DURING CONSTRUCTION Engineering The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers. All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice; All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines; and The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site. Works within Road Reserve/Reinstatement Safe vehicle and pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles. Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council. Pathways All pathways must be constructed in accordance with the following requirements: All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065; Provision must be made for disabled access at all kerb crossings associated with pathways, in accordance with Council's current standards; All paths must have a slip resistant surface; Expansion and contraction joints must provide a flush finish. Installation of joints by saw cutting is preferred to ensure a smooth ride for cyclists; and The required work includes any modifications to ensure the footpath finishes flush with all existing service covers and the like, or alternatively these services are raised or altered, so as not to create a pedestrian safety hazard. Pathways must: terminate in a manner that ensures smooth transition to existing surfaces for public safety; and be designed and constructed to comply with the Disability Discrimination Act (DDA), Access to Premises Standard, Austroads and relevant sections of AS1428 Design for access and mobility. Site Access and Driveways Driveway crossovers must be constructed in accordance with council’s Standard Drawing RS-051 and any associated addendum. Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. The following must be complied with during the construction of the required crossover/driveway: The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete; The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties; Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway; Where there is an existing pedestrian path, a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path; and The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works. Earthworks and Retaining Walls All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development, with geotechnical testing undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing the Plan of Survey. Fall protection must be provided to retaining walls that are over 1m high. Slope and batters are a maximum grade of: 1 in 6 where in proximity to waterbodies; 1 in 4 for grassed areas; 1 in 3 for planted areas; and 1 in 2 for combined structural engineering and planting solutions. Stormwater Drainage Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets. Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (e.g., by blocking or interfering with natural overland flows). Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3. Erosion and Sediment Control Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties. The sediment and erosion control design and measures have NOT been approved, it is the site's Supervising Engineer who is responsible for ensuring that the sediment and erosion control measures have: Been duly designed by an RPEQ or CPESC and constructed in accordance with "best practise" methods; Been revised by an RPEQ or CPESC to address the issues raised by changes in the projected construction schedule and/or methods; Been revised to address predicted rainfall events; and Achieve the desired environmental outcomes. Council may request further controls to be installed should the implemented measures be found inefficient. The erosion and sediment control measures must be designed, installed and maintained in accordance with the supervising engineer instructions and the current best practice standards * (Refer to Advisory Note). The developer must ensure non-essential exposure of soil is prevented by restricting the extent of disturbance and minimising the duration of soil exposure to adverse weather conditions and effectively turf, cover or stabilise any disturbed area without delay and prior to rainfall occurring. The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways. Prior to the completion of the development and commencement of use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY Certification Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit. On Maintenance All municipal works must be accepted ‘On Maintenance’ by Council in accordance with Council’s relevant Planning Scheme Policy prior to plan sealing. To achieve ‘On Maintenance’, the supervising RPEQ must submit to Council: certification that all works have been undertaken and completed in accordance with the requirements of this Permit; as Constructed details in accordance with Council’s Planning Scheme Policy; and maintenance and operational manuals for all proprietary or site specific devices. Off Maintenance Prior to requesting an Off Maintenance inspection, the developer must provide a written request for the Off Maintenance inspection. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged where: a Council inspection reveals works do not comply with approval requirements; or submitted certification falsely states works comply with approval requirements. A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection. Landscaping DURING CONSTRUCTION Retention of Existing Trees and Vegetation All trees and vegetation identified for retention must be protected in accordance with AS 4970, Protection of trees on development sites. A qualified person * must be engaged for the duration of the works to: Ensure works are carried out in accordance with the approved Arborist Report Oversee installation of all tree protection fencing prior to commencement of any works onsite (including any clearing). Supervise tree protection within the development site, frontages, and Environmental Park (western boundary) prior to, during and following construction in accordance with AS 4970, Protection of trees on development sites. Oversee approved tree removal in proximity to retained trees. Undertake a risk assessment of all trees within striking distance of the development works and site and carry out hazard removal and amenity pruning in accordance with AS 4373, Pruning of amenity trees. *(Refer to Advisory Note) All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice. The relevant conditions of the higher order Material Change of Use approval viz. Insert MCU23/0109 to which this approval relates. All relevant Council Planning Scheme Policies, standard drawings, standard specifications and guidelines. The latest version of Water Sensitive Urban Design Technical Design Guidelines for South East Queensland (Healthy Waterways) for all water quality devices to be constructed on site. Vegetation Clearing MINOR VEGETATION REMOVAL Prior to felling or pruning, all trees are to be checked for wildlife (i.e. koalas, possums, birds etc.) If wildlife is present, the tree vegetation must not be felled or pruned until the wildlife has left vegetation or has been relocated by a qualified fauna spotter catcher. *(Refer to Advisory Note)FAUNA - FOR VERY MINOR VEGETATION REMOVAL All tree and vegetation removal works must be undertaken by a qualified person*. *(Refer to Advisory Note) Landscaping Works Landscape works must be supervised, undertaken and certified by qualified persons*. All works must be completed in accordance with this Decision Notice. (* Refer to Advisory Note) Where damage occurs to any Council asset as a result of the development works, it must be repaired immediately where it creates a hazard that presents risk to person or property. Other damage must be repaired prior to completion of works. Street trees must: Meet AS2303 Tree stock for landscape use. Be located in accordance with engineering requirements for safe vehicle and pedestrian sight lines. FOLLOWING CONSTRUCTION Supervision/Certification Prior to commencement of use the following (prepared by respective qualified persons* and certifying compliance with approvals) must be submitted to Council: Landscaping certification confirming all works have been constructed in accordance with conditions of approval. NATSPEC certification (Specifying Trees: a guide to assessment of tree quality addressing each specimen). (* Refer to Advisory Note) reference documents Nil. referral agencies Not applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: Infrastructure Charges All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges Aboriginal Cultural Heritage Act 2003 There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act). The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage. You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act. Equitable Access and Facilities The plans for the proposed building work have NOT been assessed for compliance with the requirements of the National Construction Code - Building Code of Australia (Volume 1) as they relate to people with disabilities. Your attention is also directed to the fact that in addition to the requirements of the National Construction Code as they relate to people with disabilities, one or more of the following may impact on the proposed building work: the Disability Discrimination Act 1992 (Commonwealth); the Anti-Discrimination Act 1991 (Queensland); and the Disability (Access to Premises – Buildings) Standards. Development Compliance Inspection Prior to the commencement of the use, please contact Council's Development Assessment Branch to arrange a Development Compliance Inspection. Resubmission of Amended Plans Required The conditions of this Decision Notice require resubmission of plans to Council with amendments. Please address the amended plans to Council’s Development Assessment Branch with the Reference No. MCU23/0109. The plans must be amended to incorporate the amendments listed within the table below and resubmitted to Council prior to the issue of any Development Permit for Building Works. Sustainability Council encourages sustainable and energy efficient building design for all development, including the use of sustainable building materials, energy efficient fittings, solar hot water, photovoltaic systems (including the use of inverter/charges), solar panels, water saving devices and rainwater harvesting. Building and Construction Industry (Portable Long Service Leave) Levy The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid. Community Title Scheme - Private Infrastructure All private infrastructure for the development must be designed to meet the planning scheme requirements unless otherwise agreed by the relevant authority. General Advisory Notes As this driveway is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction. It is recommended that professional advice be sought for the construction of the driveway to ensure that the driveway is constructed in accordance with standard drawings RS-051. Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. Prestart, On and Off Maintenance Inspections Request Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5 business days’ notice of preferred inspection time. If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise. Environmental Advisory Notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. Erosion and Sediment Control Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional Engineer of Queensland (RPEQ). As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the plan sealing inspection: Methods of stabilisation are: appropriate for slopes and slope lengths; and are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and Stormwater runoff from the site is not currently and is not likely to result in visible evidence of sedimentation or erosion or lead to water contamination. Retention of Existing Trees The existing trees on adjoining properties must be retained and protected during construction wherever achievable. To avoid doubt, this advisory note is not intended to exclude the operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following construction of the development which is the subject of this development approval. Removal of Existing Trees and Vegetation Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as well as optimum weed seed sterilisation. Qualified Person Qualified Person, for the purpose of: Supervising landscape works and preparing a landscape certification, is considered to be a landscape architect, landscape designer or horticulturist with a minimum of three years current experience in the field of landscape design. Undertaking landscape construction and establishment works is considered to be a person with five years current experience in commercial landscape construction projects. Undertaking, supervising tree works and preparing arboriculture certification, is considered to be a person with a minimum three years current experience in tree protection, hazard identification/mitigation and Specifying Trees – a guide to assessment of tree quality (NATSPEC) assessment and either: International Society of Arboriculture (ISA) certification; or A Diploma of Arboriculture. Managing Fauna protection is considered to be a certified Fauna Spotter Catcher. Landscape Works The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges Register where: An inspection revealed that any constructed rehabilitation/landscape works do not comply with the conditions of the Decision Notice, Approved Plans and or Approved Documents Certification is submitted to Council falsely stating that works comply with the approved plans, documents and or conditions of the Decision Notice. property notes Not applicable. VARIATION approval details Not applicable. further development permits required Type of Development Permit Required Subject of the required Development Permit Development Permit for Building Works All building work. submissions Not applicable. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given. OTHER DETAILS If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices. [word/footer1.xml] Page 4 of 6 [word/header1.xml] 3 [word/header2.xml] DEVELOPMENT ASSESSMENT DELEGATED REPORT [Attachment: image13.png (image text)] tree —+4 11 Alvannogisam | ' QI tere is Bi Awvomnos ican SSS OO EE [Attachment: image15.png (image text)] fn Re Posy 38 i iy, q Ties, 4 aasr 1489 [Attachment: image16.png (image text)] ILDING FOU! UNIT 10 CARPORT BUILDING THREE} [BUILDING TWO) [BUILDING ON CARPORT [Attachment: image17.png (image text)] IS» xR a [Attachment: image3.png (image text)] [UNIT 4] | [unir 3| ‘CARPORT et u [Attachment: image4.png (image text)] 1,020 70 1,070 Laundry 2.230 490 1,085 7 7 | \ \ | | | \ I “T a INING LING (A: 9.32 m? A: 43.95 m? Oy 4 90 so) si0 p 1010 4 710 | [Attachment: image5.png (image text)] E /BATHR'M- Zo me 95.26 Im } oN BED2 JA: 13.95 m [Attachment: image6.png (image text)] 2,800 sy oO 5 de aa eS oy d¢de 734 CarSpace F345 18.79 mt? 3.410 0p 1.690. 1,020 [Attachment: image7.png (image text)] il { \ DECK 1 | As12.88 m? 7 oN f J = Wee E L | e x LIVING U I ALI ALm? PEN KITCHEN 2 214.36 me bese] F cll Pay wir ¢ 2 \ ie JA: 3.81. S = z TU TTT a au BED2 als L. - i [a: 14.13 mi Soke ; °
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU23 0109Related documentApplication case desk ↗
About this file
- File size
- 6.4 MB (large file)
- File type
- DOCX
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.