GENERAL COMMITTEE MEETING AGENDA 16 APRIL 2018
2. Proposed Carryovers - Capital Expenditure Projects
There are a total of 50 BR3 submissions for capital projects as a result of either cost savings or
overruns, variations to scope, timing delays, rescheduling to reflect delivery over two financial
years as well as emergent works. The budget review proposes an overall increase in expenditure
of $2.4 million, with the capital program therefore increasing overall from $28.6 million to $30.9
million.
The budget review includes a revised delivery schedule for a number of grant-funded capital
programs including the Noosaville Library Refurbishment and the Bridge Renewal Program. This
rescheduling changes the timing of grant claims and has resulted in a delay of some capital
revenue to 2018/19, with the 2017/18 budget decreasing by $334,349.
The following table summarises the proposed movement for the 2017/18 capital expenditure
budget:
Capital Works Amount
Original Budget $24,055,500
Total BR1 Carryovers $6,934,213
Total BR2 Capital Expenditure Submissions -$2,409,775
Total Current Budget $28,579,938
Total BR3 Capital Expenditure Submissions $2,359,490
Proposed Revised Capital Expenditure Budget $30,939,428
The following table summarises the proposed revised 2017/18 capital budget by program, with the
full list contained in Attachment 2.
Program Original BR1 BR2 BR3 Total
Budget
Capital Works $20,319,500 $6,475,340 -$2,450,179 $2,086,490 $26,431,151
Bridges $1,500,000 -$750,650 -$230,850 $518,500
Coastal Canals and Waterways $12,000 $154,000 $236,500 -$229,812 $172,688
Commercial Land & Property $2,000,000 $1,119,628 $113,983 $3,233,611
Community Facilities $65,000 $281,991 $1,045,180 -$64,716 $1,327,455
Corporate Buildings $195,000 $49,821 -$90,000 -$303 $154,518
Environmental Assets, Bushland $2,117,187 $2,117,187
Reserves, Tracks and Trails
Gravel Road Network $800,000 $62,485 -$250,000 $250,000 $862,485
Holiday Parks $1,050,000 $10,500 -$198,696 $861,804
Parks & Playgrounds $360,000 $34,450 $212,875 $6,558 $613,883
Pathways & Enabling Facilities $7,180,000 $181,509 -$5,110,460 $1,884,817 $4,135,866
Public Transport Infrastructure $600,000 $137,647 $77,353 $815,000
Sealed Roads Network $3,510,000 -$286,933 -$254,000 $254,348 $3,223,415
Sports Ground and Facilities $53,500 $12,000 $32,000 $97,500
Stormwater Drainage $80,000 $69,619 $2,972,570 -$313,000 $2,809,189
Streetscapes and Road Corridors $123,659 $123,659
Transport and Infrastructure $2,800,000 $2,407,779 -$462,194 $504,808 $5,250,393
Management
Waste Management $114,000 $114,000
Other Capital $3,736,000 $458,873 $40,404 $273,000 $4,508,277
Asset Management $570,000 $8,741 $578,741
Page 49 of 122
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.