ECM_22343520_v1_Geotechnical Investigation · 132000.200173.1
PROPOSED RENOVATIONS
2 ARAKOON CRESCENT, SUNSHINE BEACH
6.0 GEOTECHNICAL RECOMMENDATIONS
6.1 Earthworks
Excavations for the lower level and new garage are anticipated to range up to about 2 m deep. Isolated
relatively deep excavations may be required for underground services and footings or other specific
elements. Filling less than 1 m high is anticipated to form final levels, with filling to the east of the residence
limited to landscaping only, which should not exceed 0.5 m high.
The advice give herein should be treated as preliminary to aid in project planning, and Tectonic must review
detailed design drawings for the residence prior to construction.
6.1.1 Site Preparation and Trafficability
Following clearing of existing vegetation, any tree stumps and large roots should be ‘grubbed out’. Any
organic rich topsoil or uncontrolled fill should then be stripped away from at grade or building subgrades and
set aside. Similarly, all footings and remaining structural elements from the existing residence should be
removed and ‘grubbed out.’ Based on the ASI boreholes and site observations, stripping depths to remove
existing unsuitable upper soils should be relatively shallow however, deeper areas of unsuitable materials
may be present across the site, particularly related to the existing structures (e.g. retaining wall backfill,
service trenches, footing excavations). Topsoil materials must not be used in structural fill; however, may be
placed across landscaping areas.
It should be noted that compaction of such relatively ‘clean’ sands as structural fill requires the addition of
substantial volumes of water (‘flooding’) combined with the use of vibratory compaction equipment (typically
a vibrating plate). Care must be taken with the use of vibratory equipment (e.g. compactors or sheet piling)
to ensure that there are no adverse impacts on surrounding structures. The impacts from ground vibration
must be closely monitored and managed during construction. It would be prudent to conduct a dilapidation
survey of neighbouring structures prior to commencement of construction; and furthermore it is
recommended that a suitably qualified and experienced civil/structural RPEQ is engaged to provide a
vibration management plan for the proposed construction works. Our preliminary recommendation would be
that allowance is made for equipment and works such that the peak particle velocity does not exceed
10 mm/s, where measured at the property boundary.
The exposed natural subgrade following excavations will likely be in a loose condition and must be
compacted by several passes of a vibrating plate or minimum 4 tonne vibrating smooth drum roller, in
conjunction with surface application of ample water, to achieve the required compaction.
Due to the potential for development of poor trafficability during construction, placement of a minimum
150 mm thick granular working platform may be required across laydown areas. Specific platform design
would be required prior to mobilisation and trafficking of any heavy mobile plant on the site (e.g. mobile
cranes, concrete pumps or piling rigs).
Due to the highly permeable nature of the sands at this site, stormwater is expected to rapidly infiltrate the
ground, making un-sealed surface drainage ineffective for the control of flows. Any sealed areas should be
graded to ensure free drainage of stormwater away from construction areas, and to a control point(s).
6.1.2 Excavations
Excavations through the soils should be achievable using conventional earthmoving plant (e.g. small or
larger excavators with toothed buckets). Temporary unsurchaged cuts in the very loose to loose sand could
be formed at 1V:2H, and at 1V:1.5H in medium dense (or denser) sand, for batters up to 3 m in height. Flatter
batters or temporary retention may be required if groundwater seepage is encountered or if sloughing of dry
sand occurs at the batter surface. Deeper cuts, if required, will require temporary shoring, unless assessed
and approved by Tectonic during construction.
Permanent cuts or fills greater than 1 m must be retained. Permanent cut and fill batters up to 1 m high shall
not exceed 1V:2.5H. Any permanent soil and fill batters will require erosion protection (e.g. revegetation or
surface protection). Similarly, improvements to the vegetation (i.e. with endemic native species) on the
natural high dune face downslope of the residence would aid in restricting the development initial surficial
failures.
24 February 2023
Report No. 22484-001-Rev0 14
Document Set ID: 22343520
Version: 1, Version Date: 16/03/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.