Information Request Response_190521

of 9
        15. Provide plans that demonstrate that vehicles (B99 as described in AS/NZS2890.1:2004) can
            enter the site and access the spaces in a forward gear, manoeuvre on site and exit the site
            in a forward gear. The manoeuvre must be carried out in a total of 3 movements and
            consider that the adjacent space is occupied. It is noted that the proposed security gate will
            impact on the proposed visitor space and the proposed turning area.”

Applicant’s Response:
As a result of the proposed amendments to the design an amended parking layout is now proposed.
The supporting documents from Empire Engineering provide a response to this item based on the
amended parking layout.

Council Issue - Stormwater

        “The submitted material does not include sufficient detail to fully assess the stormwater impacts
        of the proposed development.

        Information Required:
        16. Provide an updated stormwater management plan prepared by an Registered Professional
            Engineer of Queensland that includes but is not be limited to:
            • a preliminary stormwater design for the proposed development which includes the
                detention system described in the submitted stormwater management plan;
            • measures to convey existing overland flows through the site without redirecting flows
                on to any adjoining property”.

Applicant’s Response:
Please refer to the attached Engineering Response to Information Request and Stormwater Management
Plan, prepared by Empire Engineering. These documents include a response to this item in full.

Lodgement of this response with Council brings the Information Request stage for the application to an
end and the Decision Stage now commences.

Should you have any questions with respect to the above, please do not hesitate to contact me direct.

Yours faithfully
PROJECT URBAN




Mick Sheppard
Director
Email: [email protected]

Log in to download the original (Information Request Response_190521.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.