                        •    The location and contact details of veterinary clinics and wildlife carers are to
                             be kept in an accessible location on Site in the event that an animal is injured
                             on or in the vicinity of the Site and no FSC is present (for example, during
                             construction). Advice must be sought from the FSC or a wildlife carer prior to
                             disturbing the animal.
                         • Invasive and introduced fauna are to be managed ethically by the FSC. This
                             may include taking the animal to the nearest veterinary clinic for euthanasia.
                         • Detailed records of fauna interactions and incidents will be maintained by the
                             FSC and will be included in the Post-Clearance Report.
                    After works:
                         • Installation of nest boxes is required to compensate for the loss of hollows.
                             Nesting boxes are to be installed at a ratio of 2:1 (two [2] boxes per hollow
                             removed or a minimum of ten [10] boxes; further details are provided in
                             Section 5.6).
Performance         1. Zero disturbance must occur outside the permitted impact area.
Indicators          2. Mortality and disturbance of fauna should be prevented.
Responsible         RACV is held accountable for:
Personnel                • Ensuring a suitably qualified FSC is present for all vegetation clearing.
                    The Project Manager is responsible for:
                         • Working with the FSC to manage any animal welfare issues identified (e.g.,
                             active nests).
                         • Ensuring all personnel are reminded of their responsibility to uphold animal
                             welfare by preventing and / or minimizing the risk of distress, injury, illness,
                             orphanage, predation, or death of fauna.
                         • Ensuring all personnel understand that fauna is not to be handled by anyone
                             except the licensed FSC (or advice must be sought if no FSC is on Site
                             following clearing).
                         • Ensuring that clearing works cease temporarily if an animal is injured, to allow
                             the FSC time to assess the level of injury and determine the next steps
                             required.
                    The Clearing Contractor is responsible for:
                         • Communicating clearly and effectively with the FSC, by use of radio, hand
                             signals or other agreed upon methods.
                         • Working carefully and under the assumption that fauna or their habitat may be
                             concealed within vegetation.
                         • Working with the FSC to manage any animal welfare issues identified.
                         • Ceasing vegetation clearing while the FSC is managing fauna. The contractor
                             may seek advice from the FSC on which works may continue to be
                             undertaken, if any.
                    The FSC / Ecologist is responsible for:
                         • Capturing and relocating fauna. Unimpeded passage must be available for
                             any fauna not captured to allow for safe self-dispersal away from Site.
                         • Maintaining detailed records of fauna interactions and fauna habitats cleared,
                             and preparing reports.
Reporting and       The FSC / Ecologist is to provide RACV with a Post-Clearance Report which details
Auditing            fauna management actions and outcomes.
Corrective Action   In the event that practices are inconsistent with the strategies outlined in this FMP, the
                    contractor should take the corrective steps and report non-compliance to the relevant
                    personnel.
                    In the event of a fauna-vehicle collision, existing measures to increase driver
                    awareness, and lessen risk of collision will be reviewed.




FAUNA MANAGEMENT PLAN | 142 Noosa Drive, Noosa Heads                                                      19

Used in these records

About this file

File size
4.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Approved Document Fauan Management Plan OPW25-0206.pdf · 4.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.