Appendix B - Biome Consulting Response
Attached to the e-mail MCU17/0551 - Information Response - 20 Trading Post Rd Cooroy.
Our Ref: BC-17152 Your Ref: MCU17/0551 6 February 2018 Noosa Council PO Box 141 TEWANTIN QLD 4565 Dear Sir/Madam, RE: DEVELOPMENT APPLICATION MCU17/0551 PROPOSED SUBDIVISION DEVELOPMENT INFORMATION REQUEST RESPONSE 19 & 20 TRADING POST ROAD, COOROY Please find below relevant responses to Information Request Items 4, 5, 6 and 7 raised by the Noosa Council within the Information Request issued on 13 December 2017. The following documents make up the supporting information to respond to the Information Request and have been included as attachments to this letter: A. Stormwater Management Design Drawings – BIOME Consulting B. Stormwater Management Plan (SWMP) – Calibre Consulting; and C. Engineering Services Layout – Pinnacle Engineering Group If you would like clarification of any of the information included within this Information Request response, please contact the undersigned. Yours faithfully BRAD COMLEY MSc, BAppSc MEngPrac, NER, RPEQ Attachment A: Stormwater Design Drawings – BIOME Consulting Attachment B: Stormwater Management Plan (SWMP) – Calibre Consulting Attachment C: Engineering Services Layout – Pinnacle Engineering Group
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 14 pages
Page 2
INFORMATION REQUEST RESPONSE
DEVELOPMENT APPLICATION MCU17/0551
19 & 20 Trading Post Road, COOROY
Request Item 4.
Issue:
Previous applications have demonstrated that 75 m2 of filter media needed to be allocated for
bioretention systems to achieve water quality reduction targets as required by the Water Sensitive
Design Code of the Noosa Plan and State Planning Policy for the overall development. This filter
media areas was based of impervious areas detailed in Appendix F of the provided stormwater
management plan
4 Demonstrate that the road, ground and roof areas proposed in the application is consistent
with the impervious and pervious areas detailed in Appendix F of the Stormwater
Management Plan to achieve pollutant reduction targets consistent with the State Planning
Policy
Response
The road, ground and roof areas of the developed site and the impervious fractions of each surface
type have been independently estimated by BIOME Consulting. Table 1 summarises the sub-
catchment characteristics.
Table 1 MUSIC Sub-Catchment Areas
Area Total Impervious
Catchment ID Land Use
(ha) (%)
Urban Residential - Road 0.163 70
Urban Residential - Roof 0.241 100
D3
Urban Residential - Ground Level 0.122 50
Total (ha) 0.526 -
The sub-catchment delineation is presented in Figure 1 and DWG-210 – Attachment A. It was
assumed that a typical lot will have a roof area comprising 75% of the total lot, based upon aerial
photography (Google Earth, 31 August 2017) showing existing lot and roof areas within earlier stages
of the development.
The sub-catchment areas defined by BIOME Consulting are consistent with those shown within the
submitted Stormwater Management Plan (SWMP) authored by Calibre Consulting, with only minor
variations between the areas and assumed impervious fractions.
To confirm that the previously determined bioretention filter area (75 m 2) will meet with the minimum
mean annual load-based reductions, a catchment model was executed using MUSIC v6. In
accordance with the State Planning Policy for Healthy Waters and the Queensland Water Quality
Guidelines (2009), the target pollutant reductions are 80% for Total Suspended Sediment (TSS); 60%
for Total Phosphorus (TP), 45% for Total Nitrogen (TN), and 90% for Gross Pollutants (GP).
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Page 1
PO Box 3469, Australia Fair
Southport QLD 4215
Page 3
Figure 1 MUSIC Sub-catchments
Model Parameters
Rainfall and evapotranspiration data for the catchment has been obtained from the Bureau of
Meteorology (BOM) Cooroy Composite rainfall station (40059) and is included within Table 2 below.
Table 2 Meteorological and Rainfall Runoff Data Reporting
Station Cooroy Composite 40059
Period 1/01/1973 to 31/12/1983 (11 years)
Time Step 6 minute
Mean Annual Rainfall (mm) 1,600
Evapotranspiration (mm) 1,629
The developed site has been modelled as having an urban residential land use with the internal
catchment split into roof, road reserve and ground level source nodes as shown above in Table 1.
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Page 2
PO Box 3469, Australia Fair
Southport QLD 4215
Page 4
The pollutant export and runoff parameters adopted for each sub catchment were as prescribed
within Table 3.8 and Table 3.7 of the Water by Design MUSIC v6 Modelling Guidelines (2010) for an
urban residential catchment. Table 3 summarises the bioretention node parameters.
Table 3 Bioretention Parameters
Parameter Bioretention D3
2
Surface area (m ) 75
Extended detention depth (m) 0.2
2
Filter area (m ) 75
Unlined filter media perimeter (m) 0.01
Saturated hydraulic conductivity (mm/hr) 200
Filter depth (m) 0.4
TN content of filter media (mg/kg) 400*
Proportion of organic material in filter (%) <5
Orthophosphate content of filter media (mg/kg) 30*
Is the base lined? Yes
Effectiveness of plant TN removal Effective
Overflow weir width (m) Surface Area/10
Exfiltration rate (mm/hr) 0.00
Underdrain present? Yes
Submerged zone with carbon present? No
Confirmation that K and C* remain default? Yes
Sediment Forebay Required (>2.5 ha contributing catchment) Yes
*As per Healthy Land and Water Recommendations for MUSICv6 modelling
Modelling Results
Results of the MUSIC v6 modelling for the treatment train effectiveness are summarised in Table 4,
and show that the 80%, 60%, 45% and 90% reduction targets for TSS, TP, TN and gross pollutants
respectively were achieved for the rainfall data set simulated. A screen capture of the modelling
results is included as Figure 2.
Table 4 Treatment Train Effectiveness
Inflows Outflows Reduction Reduction Water Quality
Pollutant
(kg/yr) (kg/yr) (kg/yr) Achieved (%) Objective (%)
TSS 1,110 166 944 85.1 80.0
TP 2.29 0.52 1.77 77.3 60.0
TN 13.9 6.33 7.57 54.5 45.0
GP 157 0 157 100 90.0
NOTE: All simulations have been run with pollutant export estimation set to “stochastic generation”.
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Page 3
PO Box 3469, Australia Fair
Southport QLD 4215
Page 5
Figure 2 Screen Capture of MUSIC Modelling Results
It is therefore expected that the bioretention filter area previously determined by Calibre Consulting
(75 m2) will be sufficient to meet the required pollutant removal targets in accordance with the State
Planning Policy for Healthy Waters and the Queensland Water Quality Guidelines (2009).
Request Item 5.
The provided stormwater management plan was provided for previous stages of the Palm Lakes
development and does not address design, construction or maintenance aspects of the current
proposed stage.
5 Provide an addendum or duplicate the Stormwater Management Plan to encompass the
design, construction and operation aspects of the area outlined within the Stormwater
Management Plan as D3 so that it can be appropriately referenced. The addendum/duplicate
must demonstrate how Specific Outcome O10 of the Water Sensitive Design Code of the
Noosa Plan is met.
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Page 4
PO Box 3469, Australia Fair
Southport QLD 4215
Page 6
Response
Based upon the level of detail provided in the SWMP previously submitted for assessment, it has not
been deemed necessary to provide an addendum or duplicate Stormwater Management Plan in order
to detail aspects of Sub-catchment D3. Stormwater management designs and associated
construction requirements are instead detailed within drawings DWG-300 to DWG-330 – Attachment
A. These drawings demonstrate that:
the bioretention bed sized by Calibre Consulting, and its associated setbacks and
maintenance requirements will be able to be contained within the designated space; and
maintenance provisions for the bioretention are in accordance with the Water by Design
Bioretention Technical Design Guidelines (2014), including a 2.5 m wide concrete access
with a maximum grade of 1:4.
MUSIC modelling has also shown that 100% of gross pollutants entering the bioretention bed are
removed from discharged flows.
Request Item 6.
The provided stormwater management plan only addresses the area needed for water quality
management and does not address any stormwater detention requirements necessary for flood or
frequent flow management.
6 Demonstrate that Specific Outcome O1 of the Water Sensitive Design Code of the Noosa
Plan, as well as Appendix 2, Table B of the State Planning Policy, in terms of changes to flow
are met.
Response
The previously submitted SWMP by Calibre Consulting manages stormwater detention on a whole of
site basis with some catchment areas detained and others undetained. The area subject to the
current development proposal has been included within the quantity management plan (Attachment
B) as follows:
The site area has been included within the pre-development Catchment D2 as shown on
Drawing B14158.W-SK100 and as such the flows reported within Table 3-1 include flows from
the pre-development catchment area; and
The site area has been included within the post-development Catchment D3 as shown on
Drawing B14158.W-SK101 and as such the flows reported within Table 3-5 include flows from
the post-development catchment area.
Based on the SP-RAFTS Layout Summary no detention has been included for the development area
(Sub-catchment D3). Sub-catchment D3 will discharge unmitigated flows at Discharge Location B
(shown on Calibre Consulting Drawing No. B14158.W-SK101 E – Appendix B and Pinnacle Drawing
No. PEG0360-DA-SK01 A – Appendix C).
Table 3-9 of the submitted SWMP shows that the Central Basin is expected to mitigate the peak flow
at Discharge Location B for all storm events considered up to the 0.01 AEP, without the need for
detention of Sub-catchment D3.
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Page 5
PO Box 3469, Australia Fair
Southport QLD 4215
Page 7
Request Item 7.
The provided plan of development does not allocate any area to demonstrate that the required water
quality treatment devices can be appropriately integrated into the development.
7 Provide a preliminary stormwater management plan to demonstrate that there is adequate
space for the required water quality treatment systems as well as depth of fall for pipework
and batters for any bioretention basins. Demonstrate that the preliminary Stormwater
Management Plan is consistent with Specific Outcome O8 of the Water Sensitive Design
Code of the Noosa Plan
Response
It was deemed that an additional stormwater management plan is not required, based on the level of
detail already provided in the submitted SWMP authored by Calibre Consulting. Drawings DWG-300
to DWG-330 within Attachment A indicate that all infrastructure associated with the required
bioretention is able to be contained within the designated footprint.
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Page 6
PO Box 3469, Australia Fair
Southport QLD 4215
Page 8
Attachment A
Stormwater Design Drawings – BIOME Consulting
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Attachment A
PO Box 3469, Australia Fair
Southport QLD 4215
Page 9
VERSION: A
DATE : 22.02.18
STORMWATER MANAGEMENT DESIGN DRAWINGS
Proposed Resort Development
20 Trading Post Road, Cooroy
for
Palm Lake Resort
Project No: BC-17152
February 2018
SCHEDULE OF DRAWINGS
Drawing No. Drawing Title
DWG-100 LOCALITY AND DRAWING INDEX PLAN
DWG-210 MUSIC CATCHMENT PLAN
DWG-310 BASIN D3 LAYOUT AND CROSS SECTION
DWG-320 BASIN D3 - INLET AND OUTLET DETAILS
DWG-330 BASIN D3 - FILTER MEDIUM AND UNDERDRAINAGE DETAILS
BIOME Consulting Pty Ltd
Unit 30201, Southport Central Tower 3,
9 Lawson St, Southport QLD 4215
PO Box 3469, Australia Fair, Southport
Site Location O 07 5532 7779
M 0415 935 222
E [email protected]
W www.BIOMEconsulting.com.au
ABN 86 166 087 476
Page 10
0
23
9
22
7
22
8
22
6
22
5
22
4
22
1
22
2
22
0
22
9
3
21
22
8
21
5
21
7
21
6
21
73
N
TIO
EN
T
DE
58
AD
RO
59
ST
PO
NG
DI
1
RA T
DATE PROJECT APPROVED FOR AND ON BEHALF OF BIOME CONSULTING COPYRIGHT ORIGINAL SCALE BEFORE REDUCTION
PTY LTD ACN 166 087 476
PROPOSED RESORT DEVELOPMENT Designs and information presented on these
22.02.18 RPEQ No. : drawings are copyright and the property of
BIOME Consulting Pty Ltd and are not to be
reproduced or used without permission from
DRAWING TITLE
VER. DESCRIPTION APPR. DATE BIOME Consulting Pty Ltd.
PROJECT No. :
MUSIC CATCHMENT PLAN A ORIGINAL ISSUE 22.02.18
Drawings are only to be used for the purpose of
BC-17152 CLIENT
which they were intended and BIOME Consulting
will not accept liability for any unauthorised use
or for any purpose by a third party for which they
CERTIFIED BY
DRAWING No. :
PALM LAKE RESORT were not intended.
Unless the checked section of the document are BIOME Consulting Pty Ltd
ADDRESS: signed and approved the drawings are
PO Box 3469, Australia Fair, Southport
DWG-210 20 TRADING POST ROAD, COOROY
uncontrolled and issued for information purposes
only. Drawings have been prepared of
M 0415 935 222
assessment purposed only and are not for
construction purposes.
REVISION No. : E [email protected]
DRAFTED BY : DESIGNED BY : CHECKED BY: PAPER SIZE : SCALE :
A TP / AC BC A3 1:750
ABN 86 166 087 476
Page 11
9
22
DATE PROJECT APPROVED FOR AND ON BEHALF OF BIOME CONSULTING COPYRIGHT ORIGINAL SCALE BEFORE REDUCTION
PTY LTD ACN 166 087 476
PROPOSED RESORT DEVELOPMENT Designs and information presented on these
22.02.18 RPEQ No. : drawings are copyright and the property of
BIOME Consulting Pty Ltd and are not to be
reproduced or used without permission from
DRAWING TITLE
VER. DESCRIPTION APPR. DATE BIOME Consulting Pty Ltd.
PROJECT No. :
BASIN D3 LAYOUT AND CROSS SECTION A ORIGINAL ISSUE 22.02.18
Drawings are only to be used for the purpose of
BC-17152 CLIENT
which they were intended and BIOME Consulting
will not accept liability for any unauthorised use
or for any purpose by a third party for which they
CERTIFIED BY
DRAWING No. :
PALM LAKE RESORT were not intended.
Unless the checked section of the document are BIOME Consulting Pty Ltd
ADDRESS: signed and approved the drawings are
PO Box 3469, Australia Fair, Southport
DWG-310 20 TRADING POST ROAD, COOROY
uncontrolled and issued for information purposes
only. Drawings have been prepared of
M 0415 935 222
assessment purposed only and are not for
construction purposes.
REVISION No. : E [email protected]
DRAFTED BY : DESIGNED BY : CHECKED BY: PAPER SIZE : SCALE :
A TP / AC BC A3 1:50, 1:150
ABN 86 166 087 476
Page 12
DATE PROJECT APPROVED FOR AND ON BEHALF OF BIOME CONSULTING COPYRIGHT ORIGINAL SCALE BEFORE REDUCTION
PTY LTD ACN 166 087 476
PROPOSED RESORT DEVELOPMENT Designs and information presented on these
22.02.18 RPEQ No. : drawings are copyright and the property of
BIOME Consulting Pty Ltd and are not to be
reproduced or used without permission from
DRAWING TITLE
VER. DESCRIPTION APPR. DATE BIOME Consulting Pty Ltd.
PROJECT No. :
BASIN D3 - INLET AND OUTLET DETAILS A ORIGINAL ISSUE 22.02.18
Drawings are only to be used for the purpose of
BC-17152 CLIENT
which they were intended and BIOME Consulting
will not accept liability for any unauthorised use
or for any purpose by a third party for which they
CERTIFIED BY
DRAWING No. :
PALM LAKE RESORT were not intended.
Unless the checked section of the document are BIOME Consulting Pty Ltd
ADDRESS: signed and approved the drawings are
PO Box 3469, Australia Fair, Southport
DWG-320 20 TRADING POST ROAD, COOROY
uncontrolled and issued for information purposes
only. Drawings have been prepared of
M 0415 935 222
assessment purposed only and are not for
construction purposes.
REVISION No. : E [email protected]
DRAFTED BY : DESIGNED BY : CHECKED BY: PAPER SIZE : SCALE :
A TP / KP AC BC A3 1:25,1:100
ABN 86 166 087 476
Page 13
DATE PROJECT APPROVED FOR AND ON BEHALF OF BIOME CONSULTING COPYRIGHT ORIGINAL SCALE BEFORE REDUCTION
PTY LTD ACN 166 087 476
PROPOSED RESORT DEVELOPMENT Designs and information presented on these
22.02.18 RPEQ No. : drawings are copyright and the property of
BIOME Consulting Pty Ltd and are not to be
reproduced or used without permission from
DRAWING TITLE
VER. DESCRIPTION APPR. DATE BIOME Consulting Pty Ltd.
PROJECT No. :
BASIN D3 - FILTER MEDIUM & UNDERDRAINAGE DETAILS A ORIGINAL ISSUE 22.02.18
Drawings are only to be used for the purpose of
BC-17152 CLIENT
which they were intended and BIOME Consulting
will not accept liability for any unauthorised use
or for any purpose by a third party for which they
CERTIFIED BY
DRAWING No. :
PALM LAKE RESORT were not intended.
Unless the checked section of the document are BIOME Consulting Pty Ltd
ADDRESS: signed and approved the drawings are
PO Box 3469, Australia Fair, Southport
DWG-330 20 TRADING POST ROAD, COOROY
uncontrolled and issued for information purposes
only. Drawings have been prepared of
M 0415 935 222
assessment purposed only and are not for
construction purposes.
REVISION No. : E [email protected]
DRAFTED BY : DESIGNED BY : CHECKED BY: PAPER SIZE : SCALE :
A TP / KP AC BC A3 N.T.S
ABN 86 166 087 476
Page 14
Attachment B
Stormwater Management Plan (SWMP) – Calibre Consulting
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Attachment B
PO Box 3469, Australia Fair
Southport QLD 4215
Page 15
Attachment C
Engineering Services Layout – Pinnacle Engineering Group
BIOME Consulting Pty Ltd
M: 0415 935 222 E: [email protected] ABN: 86 166 087 476 Attachment C
PO Box 3469, Australia Fair
Southport QLD 4215