12332_Council_Information Response_081118
Attached to the e-mail Response to Info Request (Letter, DA Form 1, Owners Consent, carpark plan, masterplan, pickup dropoff plan) - MCU18/0097.
Odyssey Consulting Group Gold Coast
ABN 35 612 263 975
Suite 5 Corporate House
155 Varsity Parade
Varsity Lakes Q 4227
PO Box 4579 Robina Town Centre
Queensland Australia 4230
Telephone: +61 7 5575 7744
Facsimile: +61 7 5641 7992
Email: [email protected]
05 November 2018 www.odcconsulting.com.au
Odyssey Consulting Group Brisbane
ABN 39 165 718 230
Billy Glover 9a/19 Lang Parade
Milton Q 4064
Assistant Development Planner Telephone: +61 7 3720 8800
Noosa Council Facsimile: +61 7 5641 7992
Email: [email protected]
PO Box 141
TEWANTIN Q 4565 Odyssey Consulting Group Rockhampton
6A/34 East Street
Rockhampton Q 4701
Our Ref: K4277-0005 Telephone: +61 7 4922 5019
Your Ref: MCU18/0097 Facsimile: +61 7 5580 9133
Email: [email protected]
BY EMAIL: [email protected]
To Whom it May Concern
RE: INFORMATION REQUEST – LOT 30 SP170751 – 115 EUMINDI NOOSA ROAD, NOOSAVILLE
We refer to the above matter and in particular your correspondence dated 16 July 2018 requesting further information,
we hereby provide the following response.
ITEM 9
Issue
The location of the bioretention basin in the front setback area reduces the ability of the development to provide a
vegetated screening of the car park area when viewed from the major road networks.
Information Required
Provide a revised car park layout that relocates the bioretention basin and provides vegetation screening of the
development when viewed from the major road networks, Walter Hay Drive and Eumundi Noosa Road.
Response:
The bio retention basin set back is currently 2m off the boundary. The current location was seen as the best option as it
followed the natural contours negating the need for unnecessary earthworks and tree removal.
ITEM 11
Issue
The MUSIC model demonstrated in the Stormwater Report shows that all runoff will flow via pervious paving prior to
entering bioretention basins. However, the detail design plans demonstrate that only a small portion of the runoff will
flow via pervious paving areas prior to entering the bioretention basins, and therefore is inconsistent with the MUSIC
model. Additionally, the Water By Design Music Modelling Guidelines states that porous paving and associated
drainage layer and filter media must be free draining (i.e. does not hold water after rainfall), the information provided
does not demonstrate this is the situation on this site.
Information Required
Provide a MUSIC model, that is consistent with the detail design plans in terms of the low flow and high flow bypass to
achieve the required pollutant reduction targets.