GENERAL COMMITTEE MEETING AGENDA 16 NOVEMBER 2015
REPORT
Recurrent Revenue (Year to date benchmark 33%)
Council has received 46% ($40.5 million) of its recurrent revenue budget of $87.3 million as at
the end of October 2015 with only minor recurrent revenue changes expected in the September
quarter budget review. Commentary on each recurrent revenue type is provided below:
Rates and Levies – $30.2m (50%) of the annual budget of $60.5m has been recorded.
Fees and Charges – Fees and charges earned ($2.9m) totals 60% of the full year budget.
Annual licences, permits and dog registrations have been issued contributing to the positive
year to date budget position. A number of fee lines are tracking above YTD budget and will
be monitored to determine if the trend will hold.
Interest Received – Currently 4.9% above forecast levels due to higher cash balances than
conservatively estimated for the budget. With speculation over further reductions in interest
rates, the budget will need to be monitored.
Dividend and Tax – Dividends and the payment of tax equivalent from Unitywater are in line
with budget forecasts.
Other Revenue – Generally in accordance with budget forecasts.
Grants and Subsidies – Overall receipts for operational grants are in accordance with
budgeted levels, with additional revenue recognised in the September quarter budget review
(with matching expenditure).
Figure 2: Recurrent Revenue Position by Type (Excluding Rates)
$3.5
$3.0
YTD Budget ($m)
$2.5
YTD Actual ($m)
$2.0
$1.5
$1.0
$0.5
$0.0
Other
Fees
Grants
Dividend
Tax
Interest
Recurrent Expenditure (Year to date benchmark 33%)
Operating expenditure is currently 32% of the full year budget spend. There were moderate
adjustments as part of the budget review, but without impact on the forecast operating result.
Detailed commentary for significant items appears below.
Employee Costs – Actuals of $8.9m against the YTD budget of $9.1m and equates to 32% of
the full year budget. Minor adjustments were included as part of the September quarter
budget review.
Materials and Services – 32% of budget ($12.4m) has been expended compared to the
budget of $13.9m. Materials, contract services and legal fees have significant variances lower
than YTD forecasts and will be monitored.
Page 13 of 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.