APPLICATION DETAILS
Application No.	OPW19/0092
Applicant	Paul Byers
Proposal	Operational Works - Vehicle Crossover
Properly Made Date	12 April 2019
Information Request Date	Not Required
Information Response Date	N/A
Decision Due Date	18 June 2019
Report Completed Date	21 May 2019
Number of Submissions	Not Applicable

PROPERTY DETAILS
Property Address	12 Mainsails Sq Noosa Heads Qld 4567
RP Description	Lot 24 RP 88934
Land Area	779m²
Existing Use of Land	Existing Dwelling
PROPOSAL
The application seeks approval for an Operational Works - Vehicle Crossover.
site details
Background
Owner wishes to replace an existing driveway due to slip hazard for users. The current as well as the proposed driveway are not strictly in compliance with the required grades in the standard drawing but are considered acceptable given the existing controlling levels and is generally consistent with other driveways in the area.
Site Description

Site Plan
assessment
Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development:
State Planning Policy;
Planning Regulation 2017
The Noosa Plan.
The following codes from the Noosa Plan are applicable to this development:
Engineering Works Codes
conclusion & reasons for decision
The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW19/0092 for a Operational Works - Vehicle Crossover situated at 12 Mainsails Sq Noosa Heads Qld 4567 and described as Lot 24 RP 88934 , it is recommended the application be approved in accordance with the following details for the Decision Notice:
application details
Application No:	OPW19/0092
Street address:	12 Mainsails Sq Noosa Heads Qld 4567
Real property description:	Lot 24 RP 88934
Planning Scheme:	The Noosa Plan (8 June 2018)
Decision details
Council decided to issue the following type of approval:
Development Permit Approval for Operational Works - Vehicle Crossover
CURRENCY PERIOD of approval
The currency period for this development approval is 2 years starting the day that this development approval takes effect.
assessment manager conditions
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan Description	Date
-	-	Replacement Driveway – Non Standard Design	-
PRIOR TO COMMENCEMENT OF WORKS
A condition report including photographs of the frontage of the site, including kerb line and road pavement, must be completed for future reference and made available to Council at the prestart meeting.
The principal contractor must have all the appropriate insurance and public liability documentation to carry out the works. The principal contractor is also responsible to ensure that any subcontractors also have the appropriate insurance and public liability documentation. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting.
A traffic management measures must be implemented prior to commencement of works and must specifically address the following:
Appropriate traffic signage in accordance with the Manual of Uniform Traffic Control Devices (MUTCD) to provide warning to drivers and road users of any safety hazard or changes to traffic conditions due to the proposed works.
Fencing to the work site during the construction phase as may be necessary to ensure the safety of the public and the road users.
Provision for safe pedestrian and traffic access across the frontage of the site both during daily construction and after daily construction has ceased.
Appropriate measures to minimising adverse impacts on traffic flows in the local roads and ensuring no obstruction to vehicular access for neighbouring properties.
DURING CONSTRUCTION
General
The developer must repair and/or meet any costs to repair damage to any Council’s and/or public assets (on or off maintenance assets) during carrying out the works, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with this development.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans and conditions of this permit approval.
All relevant Noosa Council Planning Scheme Policies, standard specifications, standard drawings and guidelines.
Driveways
Driveway crossover must be designed and constructed in accordance with the approved plans and generally in compliance with IPWEA Standard Drawings  RS-049 and RS-050, and must (*):
Have maximum width of 5.0m at kerb line unless approved otherwise by Council.
Have grades and profile that ensure that standard vehicles entering or exiting the site will not scrape or bottom down.
Have surface consists of either an approved hot mixed asphaltic concrete or plain/patterned concrete.
Have a slip resistant surface.
Provide smooth transition with the existing surfaces without creating fall, trip or slip hazards.
Be constructed so as not to concentrate stormwater runoff, increase flows or cause ponding onto the subject site, neighbouring properties and road verge.
Have a minimum clearance of 500mm from any Unitywater/Telstra asset, unless a written approval is obtained from Unitywater/ Telstra and submitted to Council.
Be located a minimum of 1m clear of any existing power poles, streetlights and street signage.
(*) also refer to Advisory Notes of this permit
Works within Road Reserve
Any existing kerb & channel and/or concrete footpath sections requiring removal due to the new works must be saw-cut and removed to allow for a smooth and neat finish with the new works.
Verge area must be reinstated in a manner to match the footpath, kerb and/or verge treatments without creating fall, trip or slip hazards to the public road users and must be maintained by the developer/owner until established.
Note: In order to mitigate the potential of public liabilities due to trip and similar hazards, Council does not permit any unauthorized works within the road reserve such as steps, sleeper steppers, hazardous landscaping and the like.
Pavement Design and Construction
Pavement design for privately owned works must be undertaken in accordance with the relevant standards.  Structural integrity of the driveway and car park areas will remain the responsibility of the property owner/developer and should be generally certified by an RPEQ.
Stormwater Drainage
Any proposed surface stormwater grated channel or pit must be located wholly within the private property boundaries.
The proposed driveway and associated works must be provided with adequate stormwater drainage and must not adversely impact on the existing drainage conditions on other properties.
Erosion and Sediment Control
Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
The contractor must ensure non-essential exposure of soil is prevented by restricting the extent of works and minimising the duration of soil exposure to adverse weather conditions. Exposed areas must be suitably covered/stabilised/reinstated as soon as practicable and prior to any predicted rainfall occurring.
Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site, particular attention must be given to prevent sediment from entering into Council’s street stormwater drainage system. The erosion and sediment control measures must be designed, installed and maintained in accordance with current best practice standards (refer to advisory notes).
FOLLOWING CONSTRUCTION
Certification and Final Inspection
Upon completion of the work, a final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required.  Please contact Council on 5329 6245 to arrange for the inspection.
referral agencies
Not applicable.
Advisory notes
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works.  A detailed check of the drawings has not been undertaken.  The developer/owner bears full responsibility for all aspects of the design.  It is recommended that a professional advice or design by a Registered Professional Engineer Queensland (RPEQ) is obtained prior to construction.
If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time.
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Not applicable.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

[word/footer1.xml]
Page 5 of 6

[word/header1.xml]
3

[word/header2.xml]
DEVELOPMENT ASSESSMENT DELEGATED REPORT

Used in these records

About this file

File size
585 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW19 0092.docx · 585 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.