Attachment G - Stormwater Quality Management plan
Callaghan & Toth
TABLE 4.1 MUSIC CATCHMENT AREAS (DEVELOPED)
Catchment Land Use Music Area (ha)
Impervious
Catchment 1 – Event Precinct Urban Residential 10% 0.127
Catchment 2 – Water Play + area adjacent creek 20% 0.110
(NOTE: water feature surface area is not part of Urban Residential
stormwater catchment in MUSIC)
Catchment 3 – playground area Urban Residential 30% 0.156
Catchment 4 – Climbing precinct Urban residential 30% 0.180
Catchment 5 – northern picnic shelter area Urban residential 30% 0.084
Catchment 6 – Frog Pond area Urban residential 30% 0.068
Catchment 7 – entry area Urban residential 10% 0.048
TOTAL 0.773ha
4.2.2 Treatment Nodes
The “MUSIC Modelling Guidelines for South East Queensland” Version 1.0 prepared by Water
by Design and dated December 2010 has been used to set the rainfall runoff parameters and
pollutant export parameters for the site.
The land use type used for this model was “Industrial” and the values in the guideline shown in
Table 3.7 and Table 3.8 of the guidelines have been used in this model. Figure 4.1 shows the
MUSIC Model layout for the site.
Tree Pits were placed in catchments 2, 3, 4 and 5 to treat runoff from the adjacent playground
areas and to connect into the subsurface drainage system. These tree pits have been designed
in accordance with IPWEAQ DS-077 and DS-078 (see Appendix C) and are generally 2.6m2
with 0.1m detention depth and 03m filter depth.
Biopods were placed in catchment 2, 3, 4, 5 and 7 to treat flows from the proposed pathways,
landscaped areas and softfall areas. These are all 5m2 in size, with a filter layer depth of 0.4m,
transition layer depth of 0.1m and drainage layer depth of 0.2m and an extended detention
depth of 0.2m. The size and depth of these systems has been designed in accordance with
Water by Design guidelines. A typical section of a bioretention system is shown in Appendix C
in IPWEAQ standard drawing WSUD-001and WSUD – 003.
BioSwale – this bioswale will treat flows from the event precinct open field – Catchment 1. It
has been modelled as being 60m long, with a bed slope of 1%, a top width of 2.0m.
Vegetated Swale – the existing swale will form part of the treatment train, with this existing
vegetated swale accepting flows from Catchment 4, 6 and 7. The swale has been modelled at
11
2001 Hinterland Playground SWMP February 2020
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Attachment G - Stormwater Quality Management plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.