Decision Notice - Negotiated - OPW22 0299 [As Published] · OPW22/0299

of 15

Text shows just the words. Original shows the document exactly as it was published.

                                                                             Officer:            Mark Lewis
                                                                             Direct Telephone:   07 5329 6290
                                                                             Our Reference:      OPW22/0299
                                                                             Your Reference:     0283

               15 May 2023


               Mark Bain Constructions Pty Ltd
               C/- Pivotal Perspective Pty Ltd
               4/59 Mary Street
               NOOSAVILLE QLD 4566
               [email protected]



               Dear Sir/Madam,
                                              Negotiated Decision Notice
                                                       Planning Act 2016

               I refer to your application and the representations you made in respect to the decision notice. On
               15 May 2023, Council decided your representations. This negotiated decision notice replaces the
               decision notice of 18 April 2023.
               Details of the negotiated decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:           OPW22/0299

                   Street address:           10 Natasha Ave Noosa Heads Qld 4567

                   Real property description: Lot 2 RP 122891, Lot 135 RP 92518

                   Planning Scheme:          Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council on 18 April 2023, decided to issue the following type of approval:
               •       Operational Works - Drainage Works, Earthworks, Landscaping, Roadworks, Stormwater,
                       Clearing Vegetation under planning scheme
               In relation to representations, Council on 15 May 2023 decided to:
               A.      Agree to amend condition1.
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

               ABN 97.969.214.121                                                               PO Box 141
               noosa.qld.gov.au                                                          Tewantin QLD 4565
               [email protected]                                                          07 5329 6500
                                                                                                        Page 1 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023
Full text of the other 14 pages

Page 2

                        Plan No.          Rev.   Plan/Document Name        Date

                        21617-C001        D      Locality Plan & Drawing 19 April 2023
                                                 Index prepared by TOD
                                                 Engineers and Project
                                                 Management

                        21617-C100        C      Nominal Bulk Earthworks 23 February 2023
                                                 prepared    by     TOD
                                                 Engineers and Project
                                                 Management

                        21617-C200        D      General   Arrangement 19 April 2023
                                                 prepared   by    TOD
                                                 Engineers and Project
                                                 Management

                        21617-C201        C      Site Sections prepared 23 February 2023
                                                 by TOD Engineers and
                                                 Project Management

                        21617-C202        D      Roadworks     Sections 19 April 2023
                                                 prepared   by    TOD
                                                 Engineers and Project
                                                 Management

                        21617-C301        D      Stormwater     Drainage 19 April 2023
                                                 Details and Calculations
                                                 prepared    by     TOD
                                                 Engineers and Project
                                                 Management

                        ED 22116 OPW-01          Sheet   Layout Plan 9 November 2022
                                                 prepared by Element
                                                 Design
                                                 As      amended      by
                                                 conditions

                        ED 22117 OPW-02          Planting Plan prepared    9 November 2022
                                                 by Element Design
                                                 As      amended      by
                                                 conditions

                        ED 22116 OPW-03          Planting Plan prepared    9 November 2022
                                                 by Element Design
                                                 As      amended      by
                                                 conditions

                        ED 22116 OPW-04          Planting Plan prepared    9 November 2022
                                                 by Element Design
                                                 As      amended      by
                                                 conditions




                                                                                  Page 2 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 3

                        ED 22116 OPW-05                             Planting Plan prepared by 9 November 2022
                                                                    Element Design
                                                                    As amended by
                                                                    conditions

                        ED 22116 OPW-06                             Planting Plan prepared by 9 November 2022
                                                                    Element Design
                                                                    As amended by
                                                                    conditions

                        ED 22116 OPW-07                             Planting Plan prepared by 9 November 2022
                                                                    Element Design
                                                                    As amended by
                                                                    conditions

                        ED 22116 OPW-08                             Details Plan prepared by     9 November 2022
                                                                    Element Design
                                                                    As amended by
                                                                    conditions

                        ED 22116 OPW-09                             Planting Plan prepared by 9 November 2022
                                                                    Element Design
                                                                    As amended by
                                                                    conditions

                        ED 22116 OPW-10                             Planting Plan prepared by 9 November 2022
                                                                    Element Design
                                                                    As amended by
                                                                    conditions

                        22_10_31_AIA_Markbain_Natas          1      Arboricultural Impact        31 October 2022
                        ha Katharina                                Assessment by Consult
                                                                    Arborist


               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 18 April 2025, unless an application to extend the currency period is
                      approved by Council.
                      Site Specific Conditions
               3.     All earthworks and associated retaining structures/batters, both above and below ground,
                      both temporary and permanent, must be contained entirely within the subject site unless
                      written permission from the respective landowner(s) is provided to Council.
               4.     Prior to requesting a prestart meeting:
                      a.      Submit to Council updated landscape plans that include all changes approved as part
                              of the higher order MCU22/0231.01.
                      b.      Submit to Council the Fauna Management Plan.
                      c.      Tree protection fencing must be installed under the supervision of the qualified person*.
                              (Refer to Advisory Note)
                      *(Refer to Advisory Note)


                                                                                                         Page 3 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 4

               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               5.     Tree protection fencing must be installed under the supervision of the Project Arborist. (Refer
                      to Retention of Existing Trees Conditions).
               6.     All necessary approvals from external service providers (eg Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               7.     A condition report of the Council drainage system in Katharina Street must be completed for
                      agreement at the prestart meeting. The condition report is to include a CCTV inspection of
                      the existing pipe and structures and must include the existing pits and pipes located in the
                      frontage of No 22 Katharina Street and extend to the existing pits and pipes in the frontage
                      of No 28 Katharina Street.
               8.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to Council at the prestart meeting / prior to any works commencing.
               9.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               10.    Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Arboreal works.
                      c.      Fauna management works.
                      d.      Landscape works;
                      e.      Erosion and sediment control works;
                      f.      Other relevant parties
               11.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction.
                              ii.      Maintenance of safe vehicle and pedestrian access across the frontages of the
                                       site both during daily construction and after daily construction has ceased
                              iii.     Proposed fencing to the site during the construction phase of the development
                              iv.      Adequate parking arrangements for construction workers
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures
                      c.      Works programme identifying key components of the works and their respective
                              durations
                      d.      Establishment of a communication protocol with the general public, adjoining owners
                              and emergency services to advise of agreed construction times, impacts on traffic and
                              services and other relevant issues




                                                                                                        Page 4 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 5

                      e.      Include a post out to the local residents advising of the proposed development, the
                              expected time frames and the site contact details
                      f.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      g.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager
                              ii.      dispute resolution procedures
                      h.      details on the location of external fill/dump sites, the haulage route, type of vehicle to
                              be utilised during filling operations and frequency of usage. NB any damage to the
                              existing road system as a result of haulage operations must be fully repaired at the
                              applicant’s expense.
               12.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               13.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               14.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice
                      b.      The relevant conditions of the higher order Material Change of Use approval viz.
                              MCU22/0299.01 to which this approval relates
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site
                      Roadworks (External Roadworks & Road Widening Works)
               17.    All pavement widening or construction of new pavement must join neatly to the existing
                      pavement so that there are no irregularities in line or level resulting at or adjacent to the join
                      for the length of the construction. Where necessary the existing pavement must be brought
                      to a satisfactory standard to allow for the above.
               18.    All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
                      asphaltic concrete, unless other pavement types are approved as feature areas in
                      intersection thresholds, speed control devices, turning areas, indented parking etc.
               19.    The developer must notify Council’s Traffic Engineer for any works involving the removal or
                      modification of existing Council traffic signs and/or parking bays prior to such works
                      commencing.


                                                                                                         Page 5 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 6

               20.    Root barriers are required to be installed behind the back of kerb for all new kerbs within 5m
                      of a trunk of a tree.
                      Pavement Design and Construction
               21.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveways and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Works within Road Reserve/Reinstatement
               22.    Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               23.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               24.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Pathways
               25.    All pathways must be constructed in accordance with the following requirements:
                      a.      All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
                      b.      Provision must be made for disabled access at all kerb crossings associated with
                              pathways, in accordance with Council's current standards.
                      c.      All paths must have a slip resistant surface.
                      d.      Expansion and contraction joints must provide a flush finish. Installation of joints by
                              saw cutting is preferred to ensure a smooth ride for cyclists.
                      e.      The required work includes any modifications to ensure the footpath finishes flush with
                              all existing service covers and the like, or alternatively these services are raised or
                              altered, so as not to create a pedestrian safety hazard.
               26.    Pathways must:
                      a.      terminate in a manner that ensures smooth transition to existing surfaces for public
                              safety.
                      b.      be designed and constructed to comply with the Disability Discrimination Act (DDA),
                              Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
                              access and mobility.
                      Site Access and Driveways
               27.    Driveway crossovers must be constructed in accordance with Council’s Standard Drawing
                      RS-049, RS-050 and any associated addendum.
               28.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               29.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete.




                                                                                                       Page 6 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 7

                      b.      The driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties.
                      c.      Underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway
                      d.      Where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path.
                      e.      The property access must be located a minimum of 1m clear of existing power poles,
                              streetlights or other signage. The developer is responsible for any necessary relocation
                              of existing services to provide this clearance and must contact the relevant service
                              authorities and comply with their requirements in relation to these works.
                      Earthworks and Retaining Walls
               30.    All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with the Standard.
               31.    Fall protection must be provided to retaining walls that are over 1m high.
               32.    Slope and batters are a maximum grade of:
                      a.      1 in 6 where in proximity to waterbodies
                      b.      1 in 4 for grassed areas.
                      c.      1 in 3 for planted areas.
                      d.      1 in 2 for combined structural engineering and planting solutions.
                      Stormwater Drainage
               33.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               34.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (eg by blocking or interfering with natural overland flows).
               35.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Erosion and Sediment Control
               36.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.
               37.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods,
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods,
                      c.      Been revised to address predicted rainfall events, and
                      d.      Achieve the desired environmental outcomes.




                                                                                                        Page 7 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 8

                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               38.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the supervising engineer instructions and the current best practice
                      standards * (Refer to Advisory Note).
               39.    The developer must ensure non-essential exposure of soil is prevented by restricting the
                      extent of disturbance and minimising the duration of soil exposure to adverse weather
                      conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
                      to rainfall occurring.
               40.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.
               41.    Prior to the completion of the development and commencement of use, all site surfaces must
                      be effectively stabilised using methods which have achieved effective short-term stabilisation
                      and which will continue to achieve effective stabilisation in the medium to long-term. For the
                      purpose of this condition, an effectively stabilised surface is defined as one that does not, or
                      is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
                      lead to sedimentation, or lead to water contamination.
                      Landscape
                      Retention of Existing Trees and Vegetation
               42.    All trees and vegetation identified for retention must be protected in accordance with AS
                      4970, Protection of trees on development sites.
               43.    A qualified person * must be engaged for the duration of the works to:
                      a.      Ensure works are carried out in accordance with the approved Arborist Report
                      b.      Oversee installation of all tree protection fencing prior to commencement of any works
                              onsite (including any clearing).
                      c.      Supervise tree protection within the development site and frontages, prior to, during
                              and following construction in accordance with AS 4970, Protection of trees on
                              development sites.
                      d.      Supervise and undertake necessary tree protection for all trees affected by the
                              development on neighbouring Lots. This includes tree identified in Appendix 3 of the
                              approved arborist report that are identified as outside project scope – TPZ conflict.
                      e.      Oversee approved tree removal in proximity to retained trees.
                      f.      Undertake a risk assessment of all trees on neighbouring properties affected by the
                              development within striking distance of the development works and site and carry out
                              hazard removal and amenity pruning in accordance with AS 4373, Pruning of amenity
                              trees.
                      *(Refer to Advisory Note)




                                                                                                         Page 8 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 9

                      Fauna Management
               44.    A qualified person* must be engaged to manage fauna in accordance with a fauna
                      management plan submitted prior to a prestart meeting. The fauna management plan must
                      include the following:
                      a.      Ensure works are carried out in accordance the Nature Conservation Act 1992.
                      b.      Undertake pre-clearing inspections including fauna relocation and removal or blocking
                              of all vacant hollows.
                      c.      Ensure clearing works avoids nesting times of animals and birds.
                      d.      Co-ordinate staging and sequence of clearing with fauna protection.
                      e.      Protect and recover fauna during clearing operations.
                      f.      Manage the translocation of animals and recovery procedures in accordance with
                              relevant legislation.
                      g.      Undertake protection works for mulching of any stockpiled vegetation.
                      *(Refer to Advisory Note)
                      Removal of Existing Trees and Vegetation
               45.    Removal of existing trees and vegetation must be undertaken by a qualified person* and
                      must include:
                      a.      Stump grinding to below finished surface level.
                      b.      Rectification to the finished surface levels and materials.
                      c.      No damage to other vegetation for retention.
                      d.      Legal disposal of all removed vegetation and debris.
                      e.      Replanting at a ratio of 5 replacement trees of the same species for each removed
                              tree.
                      *(Refer to Advisory Note)
               46.    Vegetation removal, felling and lopping must:
                      a.      Retain old growth tree hollows and suitably relocate and distribute for nesting fauna.
                      b.      Mulch all other wood and leaf material (without root balls, soil or debris and minimising
                              weed seeds) for re-usable mulch.
                      c.      Have mulch for re-use in landscape or rehabilitation stockpiled and aged for a minimum
                              of three months.
                      d.      Have mulch stockpiles no larger than 1000m3, 2.5m in height and with 10m separation
                              between piles.
                      e.      Allow for existing endemic ground flora to be translocated to suitable landscaping and
                              rehabilitation areas.
                      f.      Conclude with the area being stabilised against erosion, landscaped, rehabilitated and
                              revegetated.
                      *(Refer to Advisory Note)




                                                                                                         Page 9 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 10

                      Landscaping Works
               47.    Landscape works must be supervised, undertaken and certified by qualified persons*. All
                      works must be completed in accordance with this Decision Notice. Updated landscape plans
                      must be resubmitted prior to a prestart meeting that include all changes approved as part of
                      the higher order MCU22/0231.01.
                      (* Refer to Advisory Note)
               48.    Where damage occurs to any Council asset as a result of the development works, it must be
                      repaired immediately where it creates a hazard that presents risk to person or property. Other
                      damage must be repaired prior to completion of works.
               49.    Landscape works must:
                      a.      Ensure amenity or sales signage and ancillary infrastructure is not installed within the
                              road reserve.
                      b.      Ensure permanent irrigation is not installed within the road reserve.
                      c.      Ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of
                              foreign matter including anthropogenic waste, rock, soil/sediment contamination and is
                              applied to all planting areas to ensure a minimum 100mm depth once settled.
                              (* Refer to Advisory Note)
               50.    Public amenity trees* must:
                      a.      Meet AS 2302 – Tree Stock for landscape use.
                      b.      Be located in accordance with engineering requirements for safe vehicle and
                              pedestrian sight lines.
                      c.      Be located from services and infrastructure a minimum of:
                              i.       6m from electricity poles and pillars.
                              ii.      4m from street lighting.
                              iii.     2m from stormwater catchment pits.
                              iv.      2m from any adjoining driveway.
                      *(Refer to Advisory Note)
               51.    Turfed areas must be free of pest, diseases and weeds and level with adjoining surfaces.
               52.    Soil for landscaping must:
                      a.      Provide for healthy and sustained site specific vegetation performance.
                      b.      comply with AS 4419, Soils for landscaping and garden use.
                      Damage to Services and Assets
               53.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               FOLLOWING CONSTRUCTION / PRIOR TO COMMENCEMENT OF THE USE
                      Certification
               54.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.



                                                                                                        Page 10 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 11

               55.    Prior to commencement of use the following (prepared by respective qualified persons* and
                      certifying compliance with approvals) must be submitted to Council:
                      a.      Landscaping certification.
                      b.      Arboreal certification.
                      c.      Fauna Report documenting the findings and outcome of the fauna protection works
                              undertaken.
                      Bonds
               56.    Bonds must:
                      a.      meet the requirements of council’s relevant Planning Scheme Policy for performance
                              and uncompleted works.
                      b.      be calculated using a schedule of works and relevant bond equation.
                      c.      have approval of the bond calculations and amount from Council prior to lodgement
                      d.      be lodged with Council and accompanied by the Bond Administration Fee/s.
                      e.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.
                      As Constructed Plans and ADAC XML Files (Council)
               57.    Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                      “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                      information shall include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection.
                              Please Note: Further information and advice relating to the as-constructed drawing
                              presentation, as-constructed survey capture and associated guidelines for preparation
                              of a compliant ADAC XML digital file are available on the webpage titled “As-
                              Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
                              Development / Development Tools & Guidelines / As-Constructed Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.       Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                       conformance with applicable standards and specifications, along with the
                                       relevant descriptions of assets, services and structures and;
                              ii.      Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
                                       information, levels and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards”, and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.
                      e.      Landscaping, including all assets and improvements within parks, open space and road
                              reserves areas are to be shown on an accompanying separate landscape plan
                              (prepared in .dwg file format with accompanying hardcopy PDFs) and include a
                              complaint ADAC XML file. Details of the landscaping and all associated assets and
                              improvements may be included in the ADAC XML digital file prepared for associated
                              civil infrastructure, or alternatively, be provided as a separate ADAC XML digital file
                              containing landscape and asset information only.



                                                                                                      Page 11 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 12

                      On Maintenance
               58.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy prior to the commencement of the use. To
                      achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
                      a.      certification that all works have been undertaken and completed in accordance with the
                              requirements of this Permit.
                      b.      as Constructed details in accordance with Council’s Planning Scheme Policy.
                      c.      maintenance and operational manuals for all proprietary or site specific devices
                      Off Maintenance
               59.    Prior to requesting an Off Maintenance inspection the developer must provide a written
                      request for the Off Maintenance inspection.
               60.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      a Council inspection reveals works do not comply with approval requirements
                      b.      submitted certification falsely states works comply with approval requirements.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     As the driveways are private structures, the owner bears full responsibly for the standard of
                      their construction, maintenance and any liabilities associated with their construction. It is
                      recommended that professional advice be sought for the construction of the driveways to
                      ensure that the driveways are constructed in accordance with the relevant standards.
               2.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               3.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               4.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, On and Off Maintenance Inspections Request
               5.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days notice of preferred inspection time.
               6.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               7.     A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise.



                                                                                                      Page 12 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 13

                      Environmental Advisory Notes
               8.     The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               9.     Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               10.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               11.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the final inspection:
                      a.      Methods of stabilisation are:
                              •      appropriate for slopes and slope lengths; and
                              •      are consistent with best practice environmental management practices such as in
                                     the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                      Retention of Existing Trees
               12.    The existing trees on adjoining properties must be retained and protected during construction
                      wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
                      operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
                      construction of the development which is the subject of this development approval.
                      Removal of Existing Trees and Vegetation
               13.    Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
                      well as optimum weed seed sterilisation.
                      Qualified Person
               14.    Qualified Person, for the purpose of:
                      a.      Supervising landscape works and preparing a landscape certification, is considered to
                              be a landscape architect, landscape designer or horticulturist with a minimum of three
                              years current experience in the field of landscape design.
                      b.      Undertaking landscape construction and establishment works is considered to be a
                              person with five years current experience in commercial landscape construction
                              projects.
                      c.      Undertaking, supervising tree works and preparing arboriculture certification, is
                              considered to be a person with a minimum three years current experience in tree
                              protection, hazard identification/mitigation and assessment and either:
                              iii.     International Society of Arboriculture (ISA) certification; or
                              iv.      A Diploma of Arboriculture.
                      d.      Undertaking Fauna site works and calculating compensatory habitat is considered to
                              be a Fauna Spotter Catcher with current certification under the Queensland Parks and
                              Wildlife Service.
                      e.      Preparing certification and managing declared plant pests, is considered to be:




                                                                                                        Page 13 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 14

                              i.       an environmental consultant with a minimum of 3 years current experience in the
                                       field of pest plant management.
                      f.      Assessing and certifying soil quality is considered to be an Agronomist or
                              Horticulturalist with three years current experience in soil testing.
                      Landscape Works
               15.    The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges
                      Register where:
                      a.      An inspection revealed that any constructed rehabilitation/landscape works do not
                              comply with the conditions of the Decision Notice, Approved Plans and or Approved
                              Documents
                      b.      Certification is submitted to Council falsely stating that works comply with the approved
                              plans, documents and or conditions of the Decision Notice.
               16.    Public amenity trees are defined as any tree located within public streets, parks or areas that
                      will become publicly owned as a result of this development.
                      Aboriginal Cultural Heritage Act 2003
               17.    There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
                      approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                      The ACH Act establishes a cultural heritage duty of care which provides that: “A person who
                      carries out an activity must take all reasonable and practicable measures to ensure the
                      activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the
                      duty of care. Substantial monetary penalties may apply to individuals or corporations
                      breaching this duty of care. Injunctions may also be issued by the Land and Resources
                      Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity
                      that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value
                      of Aboriginal cultural heritage.
                      You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act.
                      Infrastructure Charges
               18.    All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
               7.     PROPERTY NOTES

               Not applicable.
               8.     VARIATION APPROVAL DETAILS

               Not applicable.
               9.     FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               10.    SUBMISSIONS

               Not applicable.
               11.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If


                                                                                                        Page 14 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Page 15

               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               12.       OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.




               Yours faithfully,




               Mark Lewis
               Coordinator-Engineering



               Enc:      Appeal Rights
                         Approved Plans/Documents
               cc.       Unitywater




               DECISION NOTICE HISTORY
               •     Original Decision Notice – 18 April 2023.
               •     Negotiated Decision Notice – 15 May 2023, with an amendment to condition 1.




                                                                                                     Page 15 of 15
Document Set ID: 22425549
Version: 3, Version Date: 15/05/2023

Used in these records

About this file

File size
168 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Negotiated - OPW22 0299 [As Published].pdf · 168 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.