Delegated Report - Code - Planning OPW23 0121 [As Published]
i. International Society of Arboriculture (ISA) certification; or
ii. A Diploma of Arboriculture.
d. Managing Fauna protection, preparing Fauna reporting and certification and
calculating compensatory habitat, is considered to be an Ecologist or Environmental
Scientist with a minimum of three years current experience in the field of fauna
assessment and management.
Retention of Existing Trees
6. The existing trees on adjoining properties must be retained and protected during construction
wherever achievable. To avoid doubt, this advisory note is not intended to exclude the
operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011 following
construction of the development which is the subject of this development approval.
Removal of Existing Trees and Vegetation
7. Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
well as optimum weed seed sterilisation.
Prestart Inspections Request
8. Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
business days’ notice of preferred inspection time.
It should be noted prior to arranging a pre-start meeting the Appeal Period of 20 business
days must have passed or the applicant must have provided Council with written confirmation
that the applicant has accepted the conditions of Decision Notice and waived their appeal
rights.
9. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
Environmental Advisory Notes
10. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
11. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control
7. PROPERTY NOTES
Not applicable.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Not applicable.
10. SUBMISSIONS
Not applicable.
Page 10 of 11
Document Set ID: 22566308
Version: 4, Version Date: 26/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.