Delegated Report - Code - Planning OPW23 0121 [As Published]

of 11

Page text shows just the words. Original shows the document exactly as it was published.

                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               6.     Bonds must:
                      a.      meet the requirements of council’s relevant Planning Scheme Policy for performance
                              and uncompleted works.
                      b.      be lodged with Council and accompanied by the Bond Administration Fee/s.
                      c.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.
                      GENERAL CONDITIONS
                      Engineering
               7.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to Council at the prestart meeting.
               8.     The principal contractor must have all the appropriate insurance and public liability
                      documentation to carry out the works. The principal contractor is also responsible to ensure
                      that any subcontractors also have the appropriate insurance and public liability
                      documentation. Certificates demonstrating currency of public liability insurance and works
                      insurance covering the works must be submitted to Council prior to the prestart meeting.
               9.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Principal contractor; and
                      c.      Landscaping works.
               10.    An amended Construction Management Plan must be submitted to Council prior to the pre-
                      start meeting and must specifically address the following:
                      a.      management of the expected volume and type of vehicles accessing the site (i.e.,
                              concrete pump, concrete truck, deliveries, piling rig, etc.).
                      b.      traffic Management during the construction phase.
                      c.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD)
                      d.      provision for safe vehicle and pedestrian access across the frontage of the site both.
               11.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction must be notified to council in writing within five business days of the
                      change occurring.
               12.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Fauna Management
               13.    A qualified person* must be engaged to manage fauna prior and during clearing to:
                      a.      Ensure works are carried out in accordance with the Nature Conservation Act 1992.
                      b.      Undertake pre-clearing inspections including fauna relocation and removal or blocking
                              of all vacant hollows.
                      c.      Ensure clearing works avoids nesting times of animals and birds.


                                                                                                       Page 6 of 11

Document Set ID: 22566308
Version: 4, Version Date: 26/10/2023
Log in to download the original file

Delegated Report - Code - Planning OPW23 0121 [As Published].pdf · 1.3 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.