SUPERSEDED - Decision Notice - Minor Change - 51993 564 01 [As Published] · 51993.564.01
7. Payment of contributions in accordance with Council’s Policy on Water Supply and Sewerage
Headworks. An estimate only of the charges as at April, 1993 under the current policy is as
follows: -
Water Supply $3176
Sewerage $1944
TOTAL: $5120
Headworks contributions shall be calculated and paid in accordance with one of the following
alternatives: -
a. Prior to the issue of a Building Approval, in the amount calculated under the Policy at
that date: or
b. Deferred to the soonest of the following dates: -
i. Prior to Council sealing plans of the development for titling purposes;
ii. Prior to the issue of a Certificate of Classification for any building approved under
this application; or
iii. Prior to commencement of the approved use at the relevant premises.
Where the option of a deferred payment is used in accordance with b. above, the
following conditions shall also apply: -
A. Prior to the issue of Building Approval, a trading bank guarantee is to be submitted
to the value of the headworks which are due, plus 20%.
B. The subsequent payment of headworks shall include interest charged at the rate
set by the Queensland Treasury Corporation for Local Government borrowings as
they apply to Noosa Shire and current at the time the trading bank guarantee is
submitted.
C. Should the contributions not be paid at the due time, Council shall call upon the
sum secured by the trading bank guarantee.
D. The trading bank guarantee will be returned on payment of the required
contributions plus interest or on expiry of the relevant Building Approval, whichever
is the sooner.
8. The footpath across the frontage of the site is to be upgraded by the provision of a 1.2 metres
wide concrete footpath and the forming, grassing and topsoiling of the remaining area to the
satisfaction of the Shire Engineer. The footpath is to be generally located 0.9 metres from
the property alignment and is to be integrated with any existing slopes and vegetation within
the road reserve.
9. The developer shall bear the cost of alteration of any public utility or other facilities
necessitated by the development of the land or associated construction works external to the
site.
10. Connection to Council’s existing water supply and sewerage reticulation systems at the
developer’s expense to the standards and requirements of the Shire Engineer.
11. The developer shall provided a metered water connection from the water supply system to
the proposed development, in accordance with Council’s standards and to the satisfaction of
the Shire Engineer.
12. Roof and surface water is to be collected on site and is to be discharged through a single
underground drain line into existing drainage in Sunseeker Close to the satisfaction of the
Shire Engineer. A Building Approval shall not be granted until the Shire Engineer has
approved of the drainage scheme.
13. Provisions of approved refuse containers in accordance with the requirements of the Refuse
Management Regulations of 1983 for the storage and collection of refuse to the satisfaction
of the Environmental Health Officer.
Page 3 of 6
Document Set ID: 22535679
Version: 4, Version Date: 11/08/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED - Decision Notice - Minor Change - 51993 564 01 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 171 KB (small file)
- File type
No other editions are linked here.