                                                      (iii)    storing other waste
                                                               with a high
                                                               potential to cause
                                                               pollution if washed
                                                               or leaked from the
                                                               bins, including
                                                               waste oil or
                                                               putrescibles.

PO7                                          AO7.1
Demolition, removal, relocation or           Infrastructure including reticulated
associated works do not result in:           water, sewerage, stormwater, and
(a) 'live' or 'active' infrastructure that   electricity are protected from damage
    may present risk to people using         and made safe to the standard
    the site or surrounding areas; or        required by the regulatory authority.
(b) damage to infrastructure or other
    works.                                   AO7.2
                                             Infrastructure is disconnected,
                                             capped or sealed including:
Editor's note— An approval will be
required from Council's Building and         (a) electricity meters are removed
Plumbing Services for                             and electrical wires
decommissioning plumbing                          disconnected;
apparatus including:                         (b) telephone lines are
(a) sanitary drains or reticulated                disconnected; and
    water supply; and                        (c) data cables are disconnected
(b) septic tanks, holding tanks or on-            and removed.
    site treatment systems.
                                             AO7.3
                                             A temporary crossing is provided to
                                             protect road reserve infrastructure
                                             including kerb and channel.

                                             AO7.4
                                             Any damage to footpaths, street
                                             plantings, natural vegetation, kerb
                                             and channel, bridges or roadways at
                                             the removal site, the new site or
                                             between the sites is repaired or
                                             reinstated to at least pre-existing
                                             conditions.
PO8                                          AO8.1
Waste materials are removed from             Waste materials are removed from
the site to avoid causing unhealthy          the site.
conditions including:
(a) potential fire hazard;                   AO8.2
(b) ponding of water; and                    If a development permit has not been
                                             issued for the future use of the site:
(c) breeding of vermin.
                                             (a) hard surfaced areas including
                                                   concrete slabs are removed or
                                                   covered with a minimum of 300
                                                   millimetres of soil; and
                                             (b) disturbed areas are revegetated.
PO9                                          No acceptable outcome provided
The potential for movement from the
site, of soils or similar materials is
minimised.
PO10                                         No acceptable outcome provided
Vacant sites do not have an adverse
impact upon the amenity of the
surrounding areas.
PO11                                         AO11.1
The demolition or removal of a               All building materials containing
building does not cause a health risk.       asbestos, including asbestos cement
                                             sheeting or roofing and lagging, are
Editor's note— Council may require           removed from the building prior to
a report identifying any asbestos            demolition or relocation.


                                                                                      Page 88 of 89
Log in to download the original file

planning report Other Change.pdf · 1.8 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.