Appendix J - Civil Engineering Report and SBSMP
Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions
PERFORMANCE OUTCOMES ACCEPTABLE OUTCOMES COMMENTS
PO5 AO5 N/A Noosa Shire Council mapping
For reconfiguring a lot or operational works, development In the Flood Hazard Overlay, or in areas otherwise indicates that the development is
does not directly, indirectly or cumulatively alter the flood determined to be subject to the DFE or DSTE, development outside flood effected areas.
characteristics external to the development site for all
ensures:
flooding and inundation events up to and including
the DFE or DSTE based on: 1. there is no loss of on-site flood storage
capacity;
1. current climate conditions; and 2. all changes to level, depth, duration and
2. incorporating an appropriate allowance for the velocity of floodwaters are contained within
predicted impacts of climate change. the site for all flood events up to and
including the DFE based on current climate
and predicted impacts of climate change at
2100;
3. there is no acceleration or retardation of
flows, or any retardation in flood warning
times, elsewhere on the floodplain and to any
overland flow paths; and
4. there is no increased stormwater ponding on
sites upstream, downstream or in the general
vicinity of the site.
Resilient building design and form AO6.1 N/A Noosa Shire Council mapping
PO6 Buildings are designed to integrate well with the street indicates that the development is
Development ensures that building design and building form: level and the levels of adjoining properties to facilitate outside flood effected areas.
1. accounts for potential flood risk;
pedestrian flows and visual and physical connectivity
2. is resilient to flood events; and
between the footpath and ground floors.
Page 4 of 9
June 2021
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix J - Civil Engineering Report and SBSMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.