17481 SARA Pre-Referral
Attached to the e-mail Operational Works Application OPW20/0243 - DA Form 1 - Owners Consent - Plans - SARA Pre Referral - 27 Cooran Court NOOSA HEADS.
2011-19754 SER
Attachment 1—Conditions to be imposed
No. Conditions Condition timing
Operational work for prescribed tidal works (removal of an existing jetty and the construction
of a pontoon)
10.17.3.1.1―Tidal works or work in a coastal management district—The chief executive administering
the Planning Act 2016 nominates the Director-General of the Department of Environment and Science
to be the enforcement authority for the development to which this development approval relates for the
administration and enforcement of any matter relating to the following conditions:
1. The pontoon must be carried out generally in accordance with the For the duration of the
following plan: works and to be
maintained.
Site Plan, Elevation and General Notes prepared by Superior
Jetties, dated 10/08/2020, reference 17481 – D01 and
revision B.
2. The works to which this approval relates are to be for a private At all times.
purpose only.
3. Any operator and contractor involved in the works to which this During construction.
approval relates must:
a) be provided a copy of these referral agency conditions;
b) install all measures, plant and equipment necessary to
ensure compliance with the conditions of this approval;
c) maintain such measures, plant and equipment in a proper
and efficient condition; and
d) operate such measures, plant and equipment in a proper
and efficient manner.
4. For the pontoon works only use materials which are free from During construction.
contaminants as defined under section 11 of the Environmental
Protection Act 1994.
5. Should the works become damaged as a result of erosion, flooding At all times.
or storm tide inundation, the registered landowner(s) of the subject
land shall be responsible for the removal of all debris at their own
expense.
10.17.3.2.1―Tidal works or work in a coastal management district—The chief executive administering
the Planning Act 2016 nominates the Director-General of the Department of Transport and Main
Roads to be the enforcement authority for the development to which this development approval relates
for the administration and enforcement of any matter relating to the following conditions:
6. The development must be carried out generally in accordance with For the duration of the
the following plans: works.
Site Plan, Elevation and General Notes prepared by Superior
Jetties, dated 10/08/2020, reference 17481 – D01 and
revision B.
7. a) Provide written notice to: a) At least two (2)
Regional Harbour Master weeks prior to the
Maritime Safety Queensland commencement of
Macarthur Avenue East works.
Pinkenba, Qld, [email protected]
State Assessment and Referral Agency Page 3 of 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.