Council archive · source document
Extension to Currency Period - Approved MCU21 0182 01 {As Published} · MCU21/0182.01
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such
as in the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
If at the time of request for plan sealing, the method of short-term stabilisation has
not achieved a level of stability that Council's Officers believe will have a high
probability of achieving long term stability (i.e. until house construction has
occurred on all lots), Council Officers may take the following matters into
consideration in determining whether the site is capable of achieving medium to
long-term stability:
• evidence that the site has been effectively stabilised in the short term;
• evidence that soil has been adequately ameliorated;
• evidence that seed of annual and perennial grass species has been applied
at an adequate rate; and
• that grass seed has germinated at a density that is likely to achieve an
effective grass cover.
Resubmission of Amended Documents Required
15. The conditions of this Decision Notice require resubmission of the referenced
Landscape Plans to Council with amendments. Please address the amended document
to Council’s Planning Assessment Branch with the Reference No. MCU21/0182, prior to
the Operational Works pre-start as detailed within conditions included within the
Decision Notice. Should the amended document not be submitted, the applicant is
advised that the required Operational Works pre-start meeting will not be approved.
Retention of Existing Trees
16. The existing trees on adjoining properties must be retained and protected during
construction wherever achievable. To avoid doubt, this advisory note is not intended to
exclude the operation of Chapter 3 of the Neighbourhood Dispute Resolution Act 2011
following construction of the development which is the subject of this development
approval.
Qualified Person
17. Qualified Person, for the purpose of:
a. Supervising landscape works and preparing a landscape certification, is
considered to be a landscape architect, landscape designer or horticulturist with a
minimum of three years current experience in the field of landscape design.
b. Undertaking, supervising tree works and preparing arboriculture certification, is
considered to be a person with a minimum three years current experience in tree
protection, hazard identification/mitigation and Specifying Trees – a guide to
assessment of tree quality (NATSPEC) assessment and either:
i. International Society of Arboriculture (ISA) certification; or
ii. A Diploma of Arboriculture.
18. Managing Fauna protection is considered to be a certified Fauna Spotter Catcher.
Document Set ID: 23016595
Version: 3, Version Date: 14/05/2024 Page 15 of 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Extension to Currency Period - Approved MCU21 0182 01 {As Published}.pdfRelated documentApplication case desk ↗
About this file
- File size
- 212 KB (small file)
- File type
No other editions are linked here.