Construction Environmental 06683025-3000(AA)
Management Plan October 2006
Commercial Development

Rev: 000 Page 12
Eenie Creek Road, Noosaville

 

 

 

 

 

14.5 Solid Waste

Solid wastes will be produced from a range of waste streams. Waste management practices
will be to achieve, where possible, the adoption of the following waste management
hierarchy:

« Waste Avoidance;

e Waste Reuse;
e Waste Recycling;
e Energy Recovery From Waste; and

e Waste Disposal.

14.5.1 Storage and Disposal of Construction Waste

Wastes would be sorted by type with each contractor being responsible for ensuring that
wastes are placed in the appropriate bin or disposal location. Bins/skips would be colour
coded or labelled according to the type of waste to be deposited with clear signage on each
bin and around the construction site. Bins would be provided where appropriate depending on
the stage of the development.

In keeping with the waste hierarchy, the first step in the waste management process would
involve reducing the production of wastes through efficient planning of resources. Secondly,
those wastes produced would be reused on the site where possible. Where reuse is not
possible the waste would be recycled via the colour coded bins/skips. For non-recycled
wastes energy recovery methods would be employed before final disposal to landfill.

14.6 Dangerous Goods

It is expected that during construction quantities of flammable and combustibles on the site
will be less than the minor storage volumes listed in AS1940 — The Storage and Handling of
Flammable and Combustible Liquids.

14.7. Control of Nuisances

The management for the control of nuisances created during earthworks and construction
phases, including dust and noise created by vehicular traffic on and off the site, is detailed in
Appendices A (General Site Management), C (Noise Management), and D (Air Quality).

Golder Associates

Used in these records

About this file

File size
10.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Application part 3 [As Published].pdf · 10.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.