2206-29385 SPD - Changed referral agency response minor change to development approval
Attached to the e-mail Change to SARA response & approval - MCU19/0001 & MCU19/0001.01.
2206-29385 SPD
Attachment 1—Changed conditions to be imposed
No. Conditions of development approval Condition timing
Material change of use – Commercial business – type 1 office, multiple housing – type 4
conventional, retail business – type 2 shop & salon
Schedule 10, Part 9, Division 4, Subdivision 2, Table 4, Item 1 (Planning Regulation 2017)—The
chief executive administering the Planning Act 2016 nominates the Director-General of the
Department of Transport and Main Roads to be the enforcement authority for the development to
which this development approval relates for the administration and enforcement of any matter
relating to the following conditions:
1. The proposed development, including the awnings and all At all times
permanent structures, must be carried out generally in
accordance with the following plans as amended in red, to show
all permanent structures must not extend into the state-controlled
road corridor: must be carried out to ensure all permanent
structures are fully contained within the subject site, awnings
located within the state-controlled road corridor are to be
cantilevered with at least 2.5m clearance under the awning
(including from signs hanging off the awning) generally in
accordance with the following plans:
Proposed Site Plan prepared by Verve Building Design
CO, dated 16.04.2019 06.10.2020, reference 18043-DA02
and revision C E.
Building Elevations and Perspectives Plan prepared by
Verve Building Design CO, dated 16.04.2019 06.10.2020,
reference 18043-DA03 and revision B D.
Building Elevations and Perspectives Plan, prepared by
Verve Building Design CO, dated 16.04.2019 06.10.2020,
reference 18043-DA04 and revision B D.
Building Elevations and Perspectives Plan prepared by
Verve Building Design CO, dated 16.04.2019 06.10.2020,
reference 18043-DA05 and revision B D.
Level 1 & Roof Plan prepared by Verve Building Design
CO, dated 16.04.2019 06.10.2020, reference 18043-
DA06 and revision A C.
2. Balconies on all units of the north facing elevation as shown on Prior to the
Building Elevations and Perspectives Plan prepared by Verve commencement of
Building Design dated 16.04.2019 06.10.2020 reference 18043 use and to be
maintained at all
DA03 and revision B D must include:
times
(a) balustrades that are solid, gap-free and continuous for
their complete length other than gaps required for
drainage purposes in accordance with the Building Code
of Australia; and
State Assessment and Referral Agency Page 3 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.