4.5 Is any part of the premises subject to an easement in favour of the holder of Pipeline Licence Number
1 issued under the Petroleum Act 1923 for the construction or operation of the Moonie to Brisbane
strategic pipeline?
® No
q
NoYe s •
End of part 4 of this checklist.
This application requries assessment by the pipeline licence holder as an advice agency.
Section reference:
• Sustainable Planning Regulation 2009, schedule 7, table 3, items 9(a), 9(b) and 17
Part 8 - Taking or interfering with water
8.8 Is any of the proposed operational work for any thing constructed or installed that allows, under the
Water Act 2000, for taking or interfering with artesian water (other than using a water truck to pump
water)?
No
• You must complete Taking artesian or sub-artesian water - IDAS form 12.
q Yes This application requires assessment by the Department of Environment and Resource
Management as a concurrence agency.
8.9 Is any of the proposed operational work for any thing constructed or installed that allows, under the
Water Act 2000, for taking overland flow water (other than using a water truck to pump water)?
® No Go to question 8.12.
E] Yes
8.12 Is any of the proposed operational work for any thing constructed or installed that allows, under the
Water Act 2000, for taking or interfering with subartesian water (other than using a water truck to
pump water)?
® No Go to question 8.14
F-1 Yes
8.14 Does any of the proposed operational work for any thing constructed or installed that allows, under
the Water Act 2000, for interfering with overland flow water (other than using a water truck to pump
water)?
® No Go to question 8.19
F-1 Yes
8.19 Is the proposed operational work for the following?
for the construction of a referable dam as defined under the Water Supply (Safety
El Yes ®No
and Reliability) Act 2008
to increase the storage capacity of a referable dam by more than 10 per cent E] Yes ®No
If yes to any of the above you must complete Referable dam - IDAS form 16.
• This application requires assessment by the Department of Environment and Resource Management
(DERM). If DERM is not the assessment manager for the application, the role of the agency will be as a
concurrence agency and you must give DERM a copy of the application
Operat/c.i - IDAS checklist 4
Version 1.0 December 2009
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application - Part 1 of 2 - IDAS Forms 1 & 6 and checklist 4Related documentApplication case desk ↗
About this file
- File size
- 2.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.