Original source · versioned page text
3_Minor Change Letter
Table 4: Substantially different development criteria
In accordance with Schedule 1 of the Response:
Development Assessment rules, a change may
be considered to result in substantially different
development if any of the following apply to the
change:
(a) involves a new use; or The proposed change does not introduce a new
use.
(b) results in the application applying to a new The proposed change does not introduce a new
parcel of land; or parcel of land.
(c) dramatically changes the built form in terms of The proposed change does not dramatically
scale, bulk and appearance; or change the bulk form of the building with only
minor works being undertaken to the arbor and
booster.
(d) changes the ability of the proposed The proposed change does not prevent the
development to operate as intended; or development operating as intended. The change
is to allow the building services to achieve
compliance and the supporting documentation
supports the reduced rate of parking as a result.
(e) removes a component that is integral to the The alterations proposed does not remove a
operation of the development; or component that is integral to the operation of the
development. As demonstrated in the attached
letter by SLR Consulting the reduced parking rate
will not result in a substantially different
development to that previously approved from a
traffic engineering perspective.
(f) significantly impacts on traffic flow and the The proposed change is not anticipated to impact
transport network, such as increasing traffic to traffic flow or the ability to access the site. This
the site; or item is supported by the attached letter provided
by SLR Consulting.
(g) introduces new impacts or increase the severity The amendments will not result in any new
of known impacts; or impacts or increase the severity of known
impacts.
(h) removes an incentive or offset component that No offset or incentive is removed as part of the
would have balanced a negative impact of the change.
development; or
(i) impacts on infrastructure provisions. The change does not affect the infrastructure
provisions on the site.
Referral agencies
In accordance with Section 80(1)(a) of the Planning Act 2016, no affected entities are required
to be notified of this minor change application. Referral was triggered to the chief executive,
who is not required to be notified of this minor change application.
Supporting information
In support of this application, the following information will be provided to satisfy the
requirements of Section 79 of the Planning Act 2016:
DA Form 5
Land owners consent from the body corporate
Amended architectural plans by Buchan Architecture
Traffic Advice by SLR Consulting
Conditional Building Approval
See the original
The page text is free to read. Viewing or downloading an original file needs an account.