Attachment E - Previous Extension to Currency Period 5-10-18
Noosa Council documents
25. Easements of between 3 and 10 metres must be provided over all Unitywater sewers located
within property boundaries in accordance with the SEQ standards. Easements shall be
centred over the pipe. Easement terms shall be the most current registered dealing held by
the Department of Natural Resources & Mines and shall not be altered or amended.
26. Written approval to enter and construct must be obtained from the owners of properties
through which external watermains will traverse. This must include approval for an easement
over the mains, and be submitted with lodgment of the associated development application
for Operational Works.
27. A minimum clearance of 1.5 metres must be maintained between Unitywater sewers and
proposed building envelopes, buildings and other structures.
28. Stormwater retention systems and gross pollutant traps must maintain a minimum clearance
of 1.5 meters from Unitywater water supply and sewerage infrastructure
29. Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from Unitywater
water mains and 1.5 metres from Unitywater sewerage mains. Landscaping plants within
these clearances must be low growing when mature and suitable Unitywater approved
varieties.
30. Construction works undertaken in the vicinity of Unitywater water supply or sewerage
infrastructure must not adversely affect the integrity of the infrastructure. All costs associated
with repair, replacement or alteration of infrastructure must be met by the applicant.
5. REFERRAL AGENCIES
Not Applicable
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Building and Construction Industry (Portable Long Service Leave) Levy
1. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
Co-ordination of Operational Works Assessment
2. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
3. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
(a) traffic management during all aspects of the construction phase including:
(i) a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction
(ii) maintenance of safe pedestrian access for the areas affected by the works during
and after daily construction has ceased
(iii) proposed fencing to the site during the construction phase of the development
(iv) approval of the Traffic Management Control Plan by the Department of Transport
and Main Roads (DTMR) for any works on State controlled roads
(v) provision for worker car parking
Page 5 of 8
Document Set ID: 20709606
Version: 4, Version Date: 05/10/2018 Print Date: 5 October 2018, 11:29 AM